Financier | Commitments |
---|---|
Asian Infrastructure Investment Bank | 250.00 |
International Bank for Reconstruction and Development | 500.00 |
Borrower/Recipient | 321.40 |
P173704
Active
Kartik Pental
Ministry of Finance
August 31, 2020
(as of board presentation)
March 24, 2021
July 1, 2021
US$ 2783.10 million
Education Department, Government of Gujarat
2021
US$ 750.00 million
N/A
May 14, 2024
September 30, 2027
BANK APPROVED
Financier | Commitments |
---|---|
Asian Infrastructure Investment Bank | 250.00 |
International Bank for Reconstruction and Development | 500.00 |
Borrower/Recipient | 321.40 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 500.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 500.00 |
Lending Instrument | |
---|---|
Grant Amount | 250.00 |
Total Project Cost** | 2783.10 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jun 15, 2023 | IBRD-92190 | Int Charges | 380,028.62 |
Jun 15, 2023 | IBRD-94220 | Int Charges | 248.28 |
Jun 15, 2023 | IBRD-94220 | Int Charges | 4,572.94 |
Jun 15, 2023 | IBRD-94220 | Int Charges | 309,253.78 |
Jun 15, 2023 | IBRD-94220 | Int Charges | 52,194.38 |
Sep 15, 2023 | IBRD-94220 | Loan Disb | 12,000,000.00 |
Mar 3, 2023 | IBRD-92190 | Loan Disb | 2,000,000.00 |
Mar 24, 2021 | IBRD-92190 | Loan Commitment | 500,000,000.00 |
Jun 21, 2022 | IBRD-94220 | Loan Commitment | 250,000,000.00 |
Dec 15, 2022 | IBRD-94220 | Int Charges | 140,162.67 |
Dec 15, 2022 | IBRD-92190 | Int Charges | 965.76 |
Feb 13, 2024 | IBRD-92190 | Loan Disb | 24,000,000.00 |
May 15, 2024 | IBRD-94220 | Loan Disb | 27,337,500.00 |
Jun 15, 2024 | IBRD-92190 | Int Charges | 361,518.72 |
May 14, 2024 | IBRD-92190 | Loan Disb | 42,500,000.00 |
Jun 15, 2024 | IBRD-94220 | Int Charges | 1,331.75 |
Jun 15, 2024 | IBRD-94220 | Int Charges | 289,255.12 |
Jun 15, 2024 | IBRD-92190 | Int Charges | 380,338.22 |
Jun 15, 2024 | IBRD-92190 | Int Charges | 27,855.39 |
Jun 15, 2024 | IBRD-92190 | Int Charges | 5,855,525.00 |
Jun 15, 2024 | IBRD-94220 | Int Charges | 462,985.53 |
Dec 15, 2022 | IBRD-92190 | Int Charges | 3,068.41 |
Dec 15, 2022 | IBRD-92190 | Int Charges | 576,474.30 |
Dec 15, 2022 | IBRD-92190 | Int Charges | 468,361.34 |
Oct 18, 2022 | IBRD-94220 | Loan Disb | 625,000.00 |
Oct 18, 2022 | IBRD-94220 | Fee Charges | 625,000.00 |
Oct 17, 2022 | IBRD-92190 | Loan Disb | 46,000,000.00 |
Dec 29, 2022 | IBRD-92190 | Loan Disb | 45,750,000.00 |
Dec 29, 2022 | IBRD-94220 | Loan Disb | 1,400,000.00 |
Dec 15, 2021 | IBRD-92190 | Int Charges | 512,414.38 |
Dec 15, 2021 | IBRD-92190 | Int Charges | 5,102.78 |
Dec 21, 2021 | IBRD-92190 | Loan Disb | 7,000,000.00 |
Feb 4, 2022 | IBRD-92190 | Loan Disb | 5,000,000.00 |
Jan 25, 2022 | IBRD-92190 | Loan Disb | 9,000,000.00 |
Apr 29, 2022 | IBRD-92190 | Loan Disb | 3,000,000.00 |
Jun 15, 2022 | IBRD-92190 | Int Charges | 599,147.25 |
Jun 15, 2022 | IBRD-92190 | Int Charges | 96,805.68 |
Jul 1, 2021 | IBRD-92190 | Loan Disb | 1,250,000.00 |
Jul 1, 2021 | IBRD-92190 | Fee Charges | 1,250,000.00 |
Dec 15, 2023 | IBRD-94220 | Int Charges | 1,056.76 |
Dec 15, 2023 | IBRD-94220 | Int Charges | 303,338.53 |
Dec 15, 2023 | IBRD-94220 | Int Charges | 249,932.11 |
Dec 15, 2023 | IBRD-92190 | Int Charges | 62,463.33 |
Dec 15, 2023 | IBRD-92190 | Int Charges | 444,000.00 |
Dec 15, 2023 | IBRD-92190 | Int Charges | 4,542,990.00 |
Sep 14, 2023 | IBRD-92190 | Loan Disb | 53,250,000.00 |
Jun 15, 2023 | IBRD-92190 | Int Charges | 3,117,508.20 |
Jun 15, 2023 | IBRD-92190 | Int Charges | 18,589.04 |
Jun 15, 2023 | IBRD-92190 | Int Charges | 480,400.70 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Decentralized planning systems institutionalized | Value | Limited use of AWPBs based on data and process-bas | 33 District Planning Teams trained by a National/S | An additional 6 District, including at least 1 add |
Date | December 31, 2020 | November 6, 2023 | September 30, 2027 | |
Comment |
Improved school quality through performance evaluation and incentives | Value | State proposes to institute a grading system to ev | 110 schools, including at least 10 schools in Prio | 55 additional schools, including at least 5 additi |
Date | December 31, 2020 | May 2, 2024 | September 30, 2027 | |
Comment |
Improved foundational learning outcomes at the lower primary level, gender disaggregated | Value | Baseline assessment for foundational learning to b | Baseline learning outcomes assessment for Grade 4 | An additional 2 percentage point improvement in pe |
Date | December 31, 2020 | November 6, 2023 | September 30, 2027 | |
Comment |
Strengthened teacher development for classroom performance | Value | State yet to institute teacher training needs asse | First teacher training needs assessment completed, | Third teacher training needs assessment completed, |
Date | December 31, 2020 | May 2, 2024 | September 30, 2027 | |
Comment |
Improved learning environment in schools and teacher education institutes | Value | State plans to upgrade the learning environment in | Inclusive state strategy for school learning envir | (i) Strengthened child-friendly learning environme |
Date | December 31, 2020 | May 2, 2024 | September 30, 2027 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Access to Early Childhood Education (ECE) Programs for preschoolers | Value | State is yet to roll out a model of Early Childhoo | Package for training of ECE teachers/facilitators | NA |
Date | December 31, 2020 | May 2, 2024 | September 30, 2027 | |
Comment |
COVID 19 response strategies built in for systemic resilience | Value | State has instituted a continuous learning plan as | At least 80 percent of educators have been trained | (i) An additional 15 percent of educators trained |
Date | December 31, 2020 | May 2, 2024 | September 30, 2027 | |
Comment |
Teacher training and management systems strengthened for performance tracking | Value | Teachers have limited access to opportunities for | State level agency designated for carrying out per | NA |
Date | December 31, 2020 | November 6, 2023 | September 30, 2027 | |
Comment |
Performance-based selection of schools for learning environment and technology infrastructure improvement | Value | State yet to initiate an enrolment and performance | Based on enrolment and performance-based criteria, | NA |
Date | December 31, 2020 | November 6, 2023 | September 30, 2027 | |
Comment |
District based planning systems enabled through capacity building support for decentralized education functionaries including SRGBVprevention protocols, complaint and referral mechanisms implemented | Value | Limited capacity for evidence-based planning and a | Stakeholder composition of District Planning Teams | (i) State level unit and all District Planning Tea |
Date | December 31, 2020 | May 2, 2024 | September 30, 2027 | |
Comment |
Students benefiting from direct interventions to enhance learning | Value | 0.00 | 7385300.00 | 7240000.00 |
Date | December 31, 2020 | November 6, 2023 | September 30, 2027 | |
Comment |
Strengthened state level learning assessment systems | Value | State planning on establishing an Assessment Cell | Gujarat Assessment Center (GAC) for managing class | Timely completion of end-line Grade 4 learning ass |
Date | December 31, 2020 | May 2, 2024 | September 30, 2027 | |
Comment |
Quality remedial program based on classroom-based assessments, and improved learning outcomes based on summative assessment tests | Value | State is yet to roll out a state-wide remedial edu | Completion of Digital device mapping to support st | (i) An additional 20 percent of schools covered un |
Date | December 31, 2020 | November 6, 2023 | September 30, 2027 | |
Comment |
Improved enrolment in residential schools for out of school girls and girls from vulnerable groups | Value | About 25,000 | NA | Enrolment increased by an additional 20,000 |
Date | December 31, 2020 | November 6, 2023 | September 29, 2027 | |
Comment |
School level AWPBs enhanced through community participation | Value | Limited capacity of SMCs to participate in develop | Modules developed for training of SMCs on process | NA |
Date | December 31, 2020 | May 2, 2024 | September 30, 2027 | |
Comment |
Students benefiting from direct interventions to enhance learning - Female | Value | 0.00 | 3491590.00 | 3530000.00 |
Date | ||||
Comment |
Improved technology enabled infrastructure in educational institutions | Value | State plans to strengthen DIETs to provide teacher | State plans to strengthen DIETs to provide teacher | An additional 3 DIETs operating with the minimum b |
Date | December 31, 2020 | November 6, 2023 | September 30, 2027 | |
Comment |
Performance grants instituted for schools to incentivize improved outcomes | Value | State yet to institute a mechanism for providing p | Performance based grants mechanism with school sel | 550 additional schools, including at least 50 addi |
Date | December 31, 2020 | May 2, 2024 | September 30, 2027 | |
Comment |
Large-scale primary/secondary learning assessments completed | Value | 0.00 | 1.00 | 3.00 |
Date | December 31, 2020 | November 6, 2023 | September 30, 2027 | |
Comment |