Connecting Madagascar for Inclusive Growth

Abstract*

Madagascar has lots of growth potentials, such as agrobusiness, tourism, light manufacturing and mining. However, they are spatially fragmented and poorly connected to the country's transport systems. In particular in rural areas, only 11.4 percent of population has access to the road network. Many rural farmers and local businesses are not connected to domestic markets, let alone the global market. The proposed project aims at supporting the Government's...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To improve the connectivity, resilience, and management of key infrastructure to enhance access to social and economic opportunities for rural communities and to support international trade and logistics.

Key Details

Project Details

  • P173711

  • Active

  • Wei Yan , Alphonse Soh, Vincent Vesin

  • REPUBLIC OF MADAGASCAR

  • Madagascar

  • February 19, 2021

  • (as of board presentation)

    March 25, 2022

  • August 16, 2022

  • US$ 400.00 million

  • N/A

  • January 29, 2024

  • June 30, 2028

  • TBD

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 200.00
IDA Grant 200.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 400.00
IBRD + IDA Commitment 400.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 400.00

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jun 6, 2024 IDA-D9820 Loan Disb 3,862,967.00
Mar 25, 2022 IDA-70600 Loan Commitment 200,000,000.00
Mar 25, 2022 IDA-D9820 Loan Commitment 200,000,000.00
Jun 5, 2024 IDA-D9820 Loan Disb 8,932,931.00
May 16, 2024 IDA-D9820 Loan Disb 25,000,000.00
May 16, 2024 IDA-70600 Loan Disb 25,000,000.00
May 25, 2023 IDA-D9820 Loan Disb 7,018.34
Dec 5, 2023 IDA-D9820 Loan Disb 7,069.48
Mar 14, 2024 IDA-D9820 Loan Disb 39,076.34
Nov 14, 2022 IDA-D9820 Loan Disb 16,000,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Satisfactory 2024-09-18
Monitoring and Evaluation Satisfactory 2024-09-18
Overall Implementation Progress (IP) Moderately Satisfactory 2024-09-18
Project Management Satisfactory 2024-09-18
Procurement Moderately Satisfactory 2024-09-18
Financial Management Moderately Satisfactory 2024-09-18

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Rural population with access to an all-season roadValue400000.00400000.002000000.00
    DateJuly 1, 2022October 25, 2023July 3, 2028
    Comment
  • Number of rural women with access to an all-season roadValue200000.00200000.00700000.00
    Date
    Comment
  • Travel time on RN10 from Toliara to Ambovonbe (Hours)Value22.0022.008.00
    DateJuly 1, 2022October 25, 2023July 3, 2028
    Comment
  • Travel time on RN31 between Mangoaka and BealalanaValue11.0011.002.50
    DateJuly 1, 2022October 25, 2023July 3, 2028
    Comment
  • Duration of road traffic disruptions per year on RN10 due to weather events (number of days per year)Value30.0030.005.00
    DateJuly 1, 2022October 25, 2023July 3, 2028
    Comment
  • Roads in good condition as a share of total length of roadsValue0.000.00100.00
    DateJuly 1, 2022October 25, 2023July 3, 2028
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Length of national road sections rehabilitated following the climate resilient national technical design standards.Value0.000.00500.00
    DateJuly 1, 2022October 25, 2023July 3, 2028
    Comment
  • Percentage of grievances recorded and processed as per the project's GRM (Citizen engagement)Value0.000.00100.00
    DateJuly 1, 2022October 25, 2023July 3, 2028
    Comment
  • PBC Contracts on Unpaved roadsValue0.000.005.00
    DateJuly 1, 2022October 25, 2023July 3, 2028
    Comment
  • Share of construction workers that have signed the Code of ConductValue0.000.00100.00
    DateJuly 1, 2022October 25, 2023July 3, 2028
    Comment
  • Number of community-based micro-enterprises involved in roadworksValue0.000.0050.00
    DateJuly 1, 2022October 25, 2023July 3, 2028
    Comment
  • Completed road safety audits on RN10 and RN31ValueNoNoYes
    DateJuly 1, 2022October 25, 2023July 3, 2028
    Comment
  • Percentage of people contracted in civil works that are womenValue0.000.0010.00
    DateJuly 3, 2023October 25, 2023July 3, 2028
    Comment
  • Local communities consulted during the selection of feeder roadsValue0.000.0050.00
    DateJuly 1, 2022October 25, 2023July 3, 2028
    Comment
  • Number of schools in the project areas with improved road accessValue0.000.001000.00
    DateJuly 1, 2022October 25, 2023July 3, 2028
    Comment
  • Number of health centers in the project areas with improved road accessValue0.000.00100.00
    DateJuly 1, 2022October 25, 2023July 3, 2028
    Comment
  • Number of GBV and HIV/AIDS awareness-raising campaigns carried out in the project areasValue0.000.0020.00
    DateJuly 1, 2022October 25, 2023July 3, 2028
    Comment
  • Length of feeder roads rehabilitated following the climate resilient national technical design standards.Value0.000.00500.00
    DateJuly 1, 2022October 25, 2023July 3, 2028
    Comment