Kakheti Connectivity Improvement Project

Abstract*

The project aims to (a) improve the connectivity and integration between a leading region (Tbilisi) and a relatively lagging one (Kakheti) - through modern highway infrastructure conceptualized as a corridor that will eventually be extended to an alternative Georgia-Azerbaijan border crossing point and thus with long-term implications for cross-border trade, regional integration, network operational resilience, tourism, and growth; (b) support primary...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Project Development Objective (PDO) is to improve connectivity and safety of road transportation in the Kakheti region along the Sagarejo-Badiauri section of the Tbilisi-Bakurtsikhe-Lagodekhi highway.

Key Details

Project Details

  • P173782

  • Active

  • Elena Lungu , Mesfin Jijo

  • Ministry of Finance

  • Georgia

  • March 10, 2021

  • (as of board presentation)

    March 22, 2022

  • July 25, 2022

  • US$ 109.00 million

  • Roads Department of the Ministry of Regional Development and Infrastructure

  • Europe and Central Asia

  • 2022

  • US$ 109.00 million

  • N/A

  • December 9, 2023

  • December 31, 2027

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 109.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 109.00
IDA Commitment N/A
IBRD + IDA Commitment 109.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 109.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jan 18, 2024 IBRD-93610 Loan Disb 190,172.45
Dec 11, 2023 IBRD-93610 Loan Disb 126,166.52
Oct 25, 2023 IBRD-93610 Loan Disb 129,841.86
Jul 8, 2024 IBRD-93610 Loan Disb 300,368.78
Aug 29, 2024 IBRD-93610 Loan Disb 52,543.53
May 2, 2024 IBRD-93610 Loan Disb 404,523.75
Apr 15, 2024 IBRD-93610 Int Charges 3,860.83
Apr 15, 2024 IBRD-93610 Int Charges 65,503.37
Apr 15, 2024 IBRD-93610 Int Charges 98,587.16
Apr 15, 2024 IBRD-93610 Int Charges 643,634.00
May 2, 2024 IBRD-93610 Loan Disb 424,934.06
Aug 29, 2024 IBRD-93610 Loan Disb 205,023.48
Jul 8, 2024 IBRD-93610 Loan Disb 293,316.10
Jun 6, 2024 IBRD-93610 Loan Disb 581,202.80
Jun 6, 2024 IBRD-93610 Loan Disb 580,160.20
Mar 6, 2024 IBRD-93610 Loan Disb 517,236.94
Apr 8, 2024 IBRD-93610 Loan Disb 544,855.70
Apr 8, 2024 IBRD-93610 Loan Disb 593,665.10
Mar 6, 2024 IBRD-93610 Loan Disb 544,415.44
Oct 15, 2022 IBRD-93610 Int Charges 90,417.28
Oct 15, 2022 IBRD-93610 Int Charges 341.20
Jul 25, 2022 IBRD-93610 Loan Disb 249,977.66
Jul 25, 2022 IBRD-93610 Fee Charges 249,977.66
Apr 17, 2023 IBRD-93610 Loan Disb 4,923,828.50
Apr 15, 2023 IBRD-93610 Int Charges 133,822.60
Apr 15, 2023 IBRD-93610 Int Charges 4,082.94
Apr 20, 2023 IBRD-93610 Loan Disb 5,513,954.50
Feb 28, 2023 IBRD-93610 Loan Disb 1,591,350.00
Sep 18, 2023 IBRD-93610 Loan Disb 238,740.52
Jun 23, 2023 IBRD-93610 Loan Disb 161,555.86
Sep 14, 2023 IBRD-93610 Loan Disb 224,539.36
Aug 17, 2023 IBRD-93610 Loan Disb 171,740.23
Jun 22, 2023 IBRD-93610 Loan Disb 309,765.22
Aug 22, 2023 IBRD-93610 Loan Disb 5,277,470.50
Aug 22, 2023 IBRD-93610 Loan Disb 4,945,659.50
Oct 15, 2023 IBRD-93610 Int Charges 5,530.62
Oct 15, 2023 IBRD-93610 Int Charges 110,046.79
Oct 15, 2023 IBRD-93610 Int Charges 268,516.60
Oct 15, 2023 IBRD-93610 Int Charges 497.07
Nov 28, 2023 IBRD-93610 Loan Disb 597,260.60
Nov 28, 2023 IBRD-93610 Loan Disb 614,792.70
Mar 22, 2022 IBRD-93610 Loan Commitment 109,000,000.00
Aug 28, 2024 IBRD-93610 Loan Disb 47,981.23
Aug 28, 2024 IBRD-93610 Loan Disb 197,689.08
Jul 26, 2024 IBRD-93610 Loan Disb 128,599.95
Jul 26, 2024 IBRD-93610 Loan Disb 93,421.56
Dec 20, 2023 IBRD-93610 Loan Disb 527,362.94
Dec 20, 2023 IBRD-93610 Loan Disb 549,536.10
Dec 20, 2023 IBRD-93610 Loan Disb 53,412.63
Jan 18, 2024 IBRD-93610 Loan Disb 180,322.28

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Financial Management Satisfactory 2024-12-17
Procurement Moderately Satisfactory 2024-12-17
Progress towards achievement of PDO Satisfactory 2024-12-17
Project Management Satisfactory 2024-12-17
Monitoring and Evaluation Satisfactory 2024-12-17
Overall Implementation Progress (IP) Moderately Satisfactory 2024-12-17

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Travel time along the target section of the highway corridorValue17.0017.0011.30
    DateDecember 31, 2021December 11, 2023August 31, 2027
    Comment
  • Number of fatal accidents per 100 million vehicle-km traveled along the target section of the highway corridorValue4.704.703.76
    DateDecember 31, 2021December 11, 2023August 31, 2027
    Comment
  • Average Annual Daily Traffic of freight vehicles on the corridorValue1013.001013.001275.00
    DateFebruary 11, 2022December 11, 2023August 31, 2027
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Roads constructedValue0.000.0017.00
    DateMarch 31, 2022December 11, 2023August 31, 2027
    Comment
  • Market stalls in the new Badiauri marketplace reserved to women tradersValue0.000.0050.00
    DateJanuary 17, 2022December 11, 2023August 31, 2027
    Comment
  • Percentage of staff at RD receiving training in contract managementValue0.000.0070.00
    DateJanuary 30, 2022December 11, 2023August 31, 2027
    Comment
  • At least 50 women receiving tailored business advisory services on how to start and/or expand their entrepreneurial activitiesValue0.000.0050.00
    DateJanuary 17, 2022December 11, 2023August 31, 2027
    Comment
  • Roads constructed - ruralValue0.000.000.00
    Date
    Comment
  • Roads constructed - non-ruralValue0.000.007.00
    Date
    Comment
  • Number of km built to climate resilient standards (designed to 100-year climate events for bridges and culverts)Value0.000.0017.00
    DateDecember 31, 2021December 11, 2023August 31, 2027
    Comment
  • Satisfaction of road users at target highway corridor (Percentage)ValueTo be determined the first yearTo be determined20% increase from the baseline
    DateJanuary 17, 2022December 11, 2023August 31, 2027
    Comment
  • Number of accidents involving pedestrians per 100 million vehicle-km travelled on the target sectionValue2.402.401.92
    DateFebruary 11, 2022December 11, 2023August 31, 2027
    Comment
  • Share of citizens who assess the information and consultation measures under the project as effectiveValue0.000.0070.00
    DateJanuary 17, 2022December 11, 2023August 31, 2027
    Comment