Financier | Commitments |
---|---|
IDA Grant | 115.00 |
P173804
Active
Christopher Trimble , Abdul Akhundzada
Republic of Tajikistan
May 12, 2020
(as of board presentation)
June 26, 2020
May 13, 2021
US$ 191.90 million
Ministry of Finance,Barqi Tojik,Ministry of Energy and Water Resources
2020
US$ 115.00 million
N/A
May 20, 2024
December 31, 2032
Yes
BANK APPROVED
Financier | Commitments |
---|---|
IDA Grant | 115.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 115.00 |
IBRD + IDA Commitment | 115.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 191.90 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jun 26, 2020 | IDA-D6850 | Loan Commitment | 50,000,000.00 |
Dec 21, 2021 | IDA-D9540 | Loan Commitment | 65,000,000.00 |
Apr 23, 2024 | IDA-D6850 | Loan Disb | 385,796.38 |
Apr 23, 2024 | IDA-D6850 | Loan Disb | 12,760,555.00 |
Aug 5, 2024 | IDA-D6850 | Loan Disb | 74,552.13 |
Name | Review | Date |
---|---|---|
Procurement | Moderately Satisfactory | 2024-12-04 |
Project Management | Satisfactory | 2024-12-04 |
Financial Management | Moderately Satisfactory | 2024-12-04 |
Progress towards achievement of PDO | Satisfactory | 2024-12-04 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2024-12-04 |
Monitoring and Evaluation | Satisfactory | 2024-12-04 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Generation capacity of energy constructed or rehabilitated | Value | 0.00 | 0.00 | 1875.00 |
Date | May 1, 2020 | April 26, 2024 | December 31, 2032 | |
Comment |
Improved dam safety against geological and seismic hazards | Value | No | No, Dam safety assessment is underway under phase | Yes |
Date | December 1, 2023 | April 26, 2024 | December 31, 2030 | |
Comment |
Estimated increase of total annual electricity generation of rehabilitated units due to efficiency improvements | Value | 0.00 | 0.00 | 515.00 |
Date | December 31, 2019 | April 26, 2024 | December 31, 2032 | |
Comment |
People provided with new or improved electricity service | Value | 0.00 | 0.00 | 9720000.00 |
Date | May 1, 2020 | April 26, 2024 | December 31, 2032 | |
Comment |
Hydropower generation capacity rehabilitated under the project | Value | 0.00 | 0.00 | 1875.00 |
Date | May 1, 2020 | April 26, 2024 | December 31, 2032 | |
Comment |
Estimated total annual electricity generation of five units included in the scope of the project | Value | 6250.00 | 6250.00 | 6765.00 |
Date | December 31, 2019 | April 26, 2024 | December 31, 2032 | |
Comment |
People provided with new or improved electricity service - Female | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Cumulative number of generating units rehabilitated | Value | 0.00 | 0.00 | 5.00 |
Date | May 1, 2020 | April 26, 2024 | December 31, 2032 | |
Comment |
Project Management Consultant (PMC) is hired for Nurek phase 2 | Value | No | Yes | Yes |
Date | November 30, 2023 | April 30, 2024 | December 31, 2026 | |
Comment |
Contractor for dam safety civil work is hired | Value | No | No | Yes |
Date | November 30, 2023 | April 30, 2024 | September 30, 2025 | |
Comment |
Rehabilitation of first unit under Nurek Phase 2 (Unit E/5) is completed. | Value | No | No | Yes |
Date | November 30, 2023 | April 26, 2024 | June 30, 2027 | |
Comment |
Percentage of women employed by BT | Value | 11.00 | 14.10 | 17.00 |
Date | May 1, 2020 | April 30, 2024 | December 31, 2030 | |
Comment |
Dam Safety Civil works for enhancement of safety against geological and seismic hazards are completed. | Value | No | No | Yes |
Date | November 30, 2023 | April 30, 2024 | December 31, 2030 | |
Comment |
Rehabilitation of 2nd Unit under phase 2 (Unit 6/F) is completed | Value | No | No | Yes |
Date | November 30, 2023 | April 26, 2024 | June 30, 2028 | |
Comment |
Percentage of citizens who believe that the Project has established effective engagement processes | Value | To be defined by the end of 2021 | 67.4% The result shows arithmetic unweighted aver | At least 75 percent. |
Date | May 1, 2020 | April 30, 2024 | December 31, 2030 | |
Comment |
Avoided CO2 emissions during the project lifetime | Value | 0.00 | 0.00 | 45.00 |
Date | May 1, 2020 | April 26, 2024 | December 31, 2032 | |
Comment |
Rehabilitation of Nurek bridge completed | Value | No | No | Yes |
Date | May 1, 2020 | April 26, 2024 | December 31, 2032 | |
Comment |
Procurement of machinery for Nurek HPP completed | Value | No | No | Yes |
Date | May 1, 2020 | April 30, 2024 | December 31, 2032 | |
Comment |