Nurek Hydropower Rehabilitation Project Phase 2

Abstract*

Component 1: Rehabilitation of six generating units and related penstocks, and strengthening of Nurek HPP capacity to operate and maintain the power plant. This would include: (a) rehabilitation of six power generating units, including generators, turbines, main inlet valves, and transformers, and supply of spare parts to ensure sustainable operation of rehabilitated units; (b) rehabilitation of penstocks related to six units to be rehabilitated;...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The objectives of the Project are to rehabilitate and increase the generating capacity of Nurek hydropower plant, improve its efficiency, and strengthen the safety of the Nurek dam.

Key Details

Project Details

  • P173804

  • Active

  • Christopher Trimble , Abdul Akhundzada

  • Republic of Tajikistan

  • Tajikistan

  • May 12, 2020

  • (as of board presentation)

    June 26, 2020

  • May 13, 2021

  • US$ 191.90 million

  • Ministry of Finance,Barqi Tojik,Ministry of Energy and Water Resources

  • Europe and Central Asia

  • 2020

  • US$ 115.00 million

  • N/A

  • May 20, 2024

  • December 31, 2032

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Grant 115.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 115.00
IBRD + IDA Commitment 115.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 191.90

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jun 26, 2020 IDA-D6850 Loan Commitment 50,000,000.00
Dec 21, 2021 IDA-D9540 Loan Commitment 65,000,000.00
Apr 23, 2024 IDA-D6850 Loan Disb 385,796.38
Apr 23, 2024 IDA-D6850 Loan Disb 12,760,555.00
Aug 5, 2024 IDA-D6850 Loan Disb 74,552.13

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Moderately Satisfactory 2024-12-04
Project Management Satisfactory 2024-12-04
Financial Management Moderately Satisfactory 2024-12-04
Progress towards achievement of PDO Satisfactory 2024-12-04
Overall Implementation Progress (IP) Moderately Satisfactory 2024-12-04
Monitoring and Evaluation Satisfactory 2024-12-04

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Generation capacity of energy constructed or rehabilitatedValue0.000.001875.00
    DateMay 1, 2020April 26, 2024December 31, 2032
    Comment
  • Improved dam safety against geological and seismic hazardsValueNoNo, Dam safety assessment is underway under phaseYes
    DateDecember 1, 2023April 26, 2024December 31, 2030
    Comment
  • Estimated increase of total annual electricity generation of rehabilitated units due to efficiency improvementsValue0.000.00515.00
    DateDecember 31, 2019April 26, 2024December 31, 2032
    Comment
  • People provided with new or improved electricity serviceValue0.000.009720000.00
    DateMay 1, 2020April 26, 2024December 31, 2032
    Comment
  • Hydropower generation capacity rehabilitated under the projectValue0.000.001875.00
    DateMay 1, 2020April 26, 2024December 31, 2032
    Comment
  • Estimated total annual electricity generation of five units included in the scope of the projectValue6250.006250.006765.00
    DateDecember 31, 2019April 26, 2024December 31, 2032
    Comment
  • People provided with new or improved electricity service - FemaleValue0.000.000.00
    Date
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Cumulative number of generating units rehabilitatedValue0.000.005.00
    DateMay 1, 2020April 26, 2024December 31, 2032
    Comment
  • Project Management Consultant (PMC) is hired for Nurek phase 2ValueNoYesYes
    DateNovember 30, 2023April 30, 2024December 31, 2026
    Comment
  • Contractor for dam safety civil work is hiredValueNoNoYes
    DateNovember 30, 2023April 30, 2024September 30, 2025
    Comment
  • Rehabilitation of first unit under Nurek Phase 2 (Unit E/5) is completed.ValueNoNoYes
    DateNovember 30, 2023April 26, 2024June 30, 2027
    Comment
  • Percentage of women employed by BTValue11.0014.1017.00
    DateMay 1, 2020April 30, 2024December 31, 2030
    Comment
  • Dam Safety Civil works for enhancement of safety against geological and seismic hazards are completed.ValueNoNoYes
    DateNovember 30, 2023April 30, 2024December 31, 2030
    Comment
  • Rehabilitation of 2nd Unit under phase 2 (Unit 6/F) is completedValueNoNoYes
    DateNovember 30, 2023April 26, 2024June 30, 2028
    Comment
  • Percentage of citizens who believe that the Project has established effective engagement processesValueTo be defined by the end of 202167.4% The result shows arithmetic unweighted averAt least 75 percent.
    DateMay 1, 2020April 30, 2024December 31, 2030
    Comment
  • Avoided CO2 emissions during the project lifetimeValue0.000.0045.00
    DateMay 1, 2020April 26, 2024December 31, 2032
    Comment
  • Rehabilitation of Nurek bridge completedValueNoNoYes
    DateMay 1, 2020April 26, 2024December 31, 2032
    Comment
  • Procurement of machinery for Nurek HPP completedValueNoNoYes
    DateMay 1, 2020April 30, 2024December 31, 2032
    Comment