Cabo Verde: COVID-19 Emergency Response Project

Abstract*

This Project Appraisal Document (PAD) describes the emergency response in Cabo Verde under the COVID-19 Strategic Preparedness And Response Program (SPRP) using the Multi-phase Programmatic Approach (MPA), approved by the World Bank’s Board of Executive Directorson March 20, 2020. The Project is structured around two complementary components, which will support the Government of Cabo Verde in the implementation of its National COVID-19 Preparedness...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

Project development objective is to prepare and respond to the COVID-19 pandemic in Cabo Verde

Key Details

Project Details

  • P173857

  • Active

  • Andre Carletto

  • Ministério das Finanças

  • Cabo Verde

  • March 25, 2020

  • (as of board presentation)

    April 2, 2020

  • April 9, 2020

  • US$ 5.00 million

  • N/A

  • April 12, 2024

  • December 31, 2025

  • No

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 5.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 5.00
IBRD + IDA Commitment 5.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 5.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Dec 15, 2023 IDA-68370 Int Charges 16,953.77
Dec 15, 2023 IDA-65970 Int Charges 287.44
Jun 7, 2023 IDA-68370 Loan Disb 153,902.12
Jun 7, 2023 IDA-68370 Loan Disb 25,267.13
Jul 10, 2023 IDA-68370 Loan Disb 22,068.91
Jun 15, 2023 IDA-68370 Int Charges 916.01
Jun 15, 2023 IDA-68370 Int Charges 916.01
Jun 15, 2023 IDA-68370 Int Charges 16,293.59
Jun 15, 2023 IDA-68370 Int Charges 16,293.59
Jun 26, 2023 IDA-69770 Loan Cancel 5,010,597.00
Feb 3, 2023 IDA-68370 Loan Disb 98,685.77
Feb 3, 2023 IDA-68370 Loan Disb 112,315.36
Dec 15, 2022 IDA-65970 Int Charges 17,183.29
Dec 15, 2022 IDA-65970 Int Charges 17,183.29
Dec 15, 2022 IDA-65970 Int Charges 478.44
Dec 15, 2022 IDA-65970 Int Charges 478.44
Feb 8, 2023 IDA-68370 Loan Disb 262,200.56
Jun 15, 2023 IDA-65970 Int Charges 753.60
Nov 14, 2022 IDA-68370 Loan Disb 83,006.75
Nov 14, 2022 IDA-68370 Loan Disb 32,857.94
Jun 15, 2024 IDA-69770 Int Charges 2,229.43
Jun 15, 2024 IDA-68370 Int Charges 17,276.26
Jun 15, 2024 IDA-68370 Int Charges 17,276.26
Jun 15, 2024 IDA-65970 Int Charges 419.73
Jun 15, 2024 IDA-65970 Int Charges 419.73
Jun 15, 2024 IDA-65970 Int Charges 18,212.97
Dec 15, 2023 IDA-65970 Int Charges 287.44
Feb 27, 2024 IDA-69770 Loan Disb 1,000,000.00
Jun 15, 2024 IDA-65970 Int Charges 18,212.97
Jun 15, 2024 IDA-68370 Int Charges 397.89
Jun 15, 2024 IDA-68370 Int Charges 397.89
Jun 15, 2024 IDA-69770 Int Charges 2,229.43
Feb 11, 2021 IDA-68370 Loan Commitment 5,000,000.00
Jun 29, 2021 IDA-69770 Loan Commitment 10,000,000.00
Apr 2, 2020 IDA-65970 Loan Commitment 5,000,000.00
Dec 15, 2020 IDA-65970 Int Charges 16,430.99
Dec 15, 2020 IDA-65970 Int Charges 16,430.99
Oct 8, 2020 IDA-65970 Loan Disb 409,853.44
Sep 20, 2021 IDA-68370 Loan Disb 206,245.23
Dec 16, 2021 IDA-65970 Int Charges 19,340.18
Dec 16, 2021 IDA-65970 Int Charges 19,340.18
Dec 16, 2021 IDA-68370 Int Charges 600.72
Dec 16, 2021 IDA-68370 Int Charges 600.72
Dec 16, 2021 IDA-68370 Int Charges 5,289.15
Dec 16, 2021 IDA-68370 Int Charges 5,289.15
May 13, 2022 IDA-68370 Loan Disb 202,481.86
Jun 15, 2022 IDA-65970 Int Charges 196.12
Jun 15, 2022 IDA-65970 Int Charges 196.12
Jun 15, 2022 IDA-65970 Int Charges 18,231.02
Jun 15, 2022 IDA-65970 Int Charges 18,231.02
Jun 15, 2022 IDA-65970 Int Charges -25.94
Jun 15, 2022 IDA-65970 Int Charges 25.94
Jun 15, 2023 IDA-65970 Int Charges 753.60
Jun 15, 2023 IDA-65970 Int Charges 18,466.02
Jun 15, 2023 IDA-65970 Int Charges 18,466.02
Dec 15, 2023 IDA-65970 Int Charges 17,836.70
Dec 15, 2023 IDA-65970 Int Charges 17,836.70
Dec 15, 2023 IDA-68370 Int Charges 226.97
Dec 15, 2023 IDA-68370 Int Charges 226.97
Dec 15, 2023 IDA-68370 Int Charges 16,953.77
Nov 30, 2021 IDA-68370 Loan Disb 8,856.22
Nov 30, 2021 IDA-68370 Loan Disb 90,579.73
Jul 27, 2022 IDA-68370 Loan Disb 146,945.97
Jun 15, 2022 IDA-68370 Int Charges 15.12
Jun 15, 2022 IDA-68370 Int Charges 15.12
Jun 15, 2022 IDA-68370 Int Charges 7,599.17
Jun 15, 2022 IDA-68370 Int Charges 7,599.17
Jul 30, 2021 IDA-65970 Loan Cancel 14,835.36
Apr 16, 2021 IDA-68370 Loan Disb 500,000.00
Jun 21, 2021 IDA-68370 Loan Disb 751,312.94
Aug 5, 2021 IDA-68370 Loan Disb 145,168.20
Apr 29, 2020 IDA-65970 Loan Disb 2,098,415.80
May 7, 2020 IDA-65970 Loan Disb 20,000.00
Jun 26, 2020 IDA-65970 Loan Disb 480,000.00
Jul 30, 2020 IDA-65970 Loan Disb 2,107,501.50
Jun 15, 2021 IDA-65970 Int Charges 348.35
Jun 15, 2021 IDA-65970 Int Charges 348.35
Jun 15, 2021 IDA-65970 Int Charges 19,763.65
Jun 15, 2021 IDA-65970 Int Charges 19,763.65
Dec 15, 2020 IDA-65970 Int Charges 2,136.88
Dec 15, 2020 IDA-65970 Int Charges 2,136.88
Nov 29, 2022 IDA-68370 Loan Disb 757,592.25
Nov 21, 2022 IDA-68370 Loan Disb 102,784.78
Nov 28, 2022 IDA-68370 Loan Disb 191,792.16
Dec 15, 2022 IDA-68370 Int Charges 59.09
Dec 15, 2022 IDA-68370 Int Charges 59.09
Dec 15, 2022 IDA-68370 Int Charges 9,077.06
Dec 15, 2022 IDA-68370 Int Charges 9,077.06
Sep 22, 2022 IDA-68370 Loan Disb 9,880.15
Sep 15, 2022 IDA-68370 Loan Disb 73,808.58
Sep 15, 2022 IDA-68370 Loan Disb 77,644.47
Sep 22, 2022 IDA-68370 Loan Disb 65,038.52
Nov 14, 2022 IDA-68370 Loan Disb 109,309.80
Apr 13, 2022 IDA-68370 Loan Disb 183,572.56
Dec 15, 2021 IDA-68370 Loan Disb 192,151.52
Dec 15, 2021 IDA-68370 Loan Disb 99,030.98
Dec 6, 2021 IDA-68370 Loan Disb 67,900.77
Dec 16, 2021 IDA-65970 Int Charges 144.52
Dec 16, 2021 IDA-65970 Int Charges 144.52

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Overall Implementation Progress (IP) Highly Satisfactory 2024-11-13
Progress towards achievement of PDO Highly Satisfactory 2024-11-13
Procurement Satisfactory 2024-11-13
Financial Management Highly Satisfactory 2024-11-13
Project Management Highly Satisfactory 2024-11-13
Monitoring and Evaluation Satisfactory 2024-11-13
Procurement Satisfactory 2024-11-13
Project Management Highly Satisfactory 2024-11-13
Financial Management Moderately Satisfactory 2024-11-13
Progress towards achievement of PDO Highly Satisfactory 2024-11-13
Monitoring and Evaluation Satisfactory 2024-11-13
Overall Implementation Progress (IP) Highly Satisfactory 2024-11-13

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Percentage of suspected cases of COVID-19 tested per approved protocolValue0.00100.0085.00
    DateMarch 20, 2020September 21, 2022March 31, 2021
    Comment
  • National virology laboratory equipped with COVID-19 diagnostic equipment, test kits, and reagents per Ministry of Health guidelinesValueNoYesYes
    DateMarch 20, 2020December 5, 2020March 31, 2021
    Comment
  • Percentage of diagnosed cases treated per approved protocolValue0.00100.0050.00
    DateMarch 20, 2020September 21, 2022March 31, 2021
    Comment
  • Population vaccinated, which is included in the priority population targets defined in national plan [by sex].Value0.0098.70100.00
    DateDecember 31, 2021March 28, 2024December 31, 2024
    Comment
  • FemalesValue0.0048.3945.00
    DateFebruary 1, 2021June 15, 2023March 31, 2022
    Comment
  • Adult population fully vaccinated [by sex];Value0.0086.5370.00
    DateDecember 31, 2020June 15, 2023December 31, 2021
    Comment
  • FemalesValue0.0042.3940.00
    DateFebruary 1, 2021June 15, 2023December 31, 2022
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Percentage of health districts with pandemic preparedness and response plans per Ministry of Health GuidelinesValue18.00100.00100.00
    DateMarch 20, 2020September 21, 2022March 31, 2021
    Comment
  • Percentage of claims registered in the Project's grievance redress mechanism (GRM) resolved in a timely mannerValue0.00100.0040.00
    DateMarch 20, 2020June 15, 2023March 31, 2021
    Comment
  • Percentages of health facilities with personal protective equipment and infection control products and supplies, without stock-outsin preceding two weeksValue32.00100.00100.00
    DateMarch 20, 2020September 21, 2022March 31, 2021
    Comment
  • Country has prepared a referral system to care for COVID-19 patientsValueNoYesYes
    DateMarch 20, 2020December 5, 2020April 30, 2020
    Comment
  • Number of additional ICU beds equipped and operationalValue0.0020.0020.00
    DateMarch 20, 2020September 21, 2022March 31, 2021
    Comment
  • Protective personal equipment (PPE) distributed to the general populationValue0.00100000.00100000.00
    DateApril 2, 2020December 5, 2020October 30, 2020
    Comment
  • Number of additional intermediary care beds equipped and operational in Sal and Boa Vista IslandsValue0.0010.0020.00
    DateJanuary 22, 2021March 28, 2024December 31, 2024
    Comment
  • National COVID-19 Immunization Plan Developed and ApprovedValueNoYesYes
    DateJanuary 22, 2021February 18, 2021March 12, 2021
    Comment
  • Essential and frontline health workers benefitting from the first phase of the vaccine who are women (as percentage of the total women among essential and frontline health workers)Value0.00100.00100.00
    DateJanuary 22, 2021September 21, 2022June 30, 2021
    Comment
  • Pharmacovigilance System (PVS) adapted to detect Adverse Events Following Vaccination (AEFI) for the COVID19 vaccineValueNoYesYes
    DateJanuary 22, 2021June 11, 2021February 26, 2021
    Comment
  • Communication/Community engagement campaigns produced and implemented focusing on COVID-19 prevention activities and vaccine hesitancy among target priority groupsValue1.002.002.00
    DateApril 1, 2021September 21, 2022December 31, 2022
    Comment
  • Digital platform operational to receive individual vaccination dataValueNoYesYes
    DateJune 23, 2021September 21, 2022December 31, 2022
    Comment