Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 20.00 |
P173876
Closed
Daniela Romero , Vanina Camporeale
The Oriental Republic of Uruguay
May 11, 2020
(as of board presentation)
May 15, 2020
August 10, 2020
US$ 20.00 million
Ministry of Economy and Finance,Ministry of Public Health
2020
US$ 20.00 million
N/A
April 25, 2024
May 31, 2022
Yes
BANK APPROVED
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 20.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 20.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 20.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 20.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Sep 24, 2021 | IBRD-91250 | Loan Disb | 16,000,000.00 |
Feb 15, 2024 | IBRD-91250 | Int Charges | 5,815.81 |
Apr 4, 2022 | IBRD-91250 | Loan Disb | 4,000,000.00 |
Feb 15, 2022 | IBRD-91250 | Int Charges | 3,671.24 |
Feb 15, 2022 | IBRD-91250 | Int Charges | 47,360.00 |
Aug 15, 2022 | IBRD-91250 | Int Charges | 1,315.07 |
Aug 15, 2022 | IBRD-91250 | Int Charges | 118,508.87 |
Aug 15, 2023 | IBRD-91250 | Int Charges | 20,971.47 |
Aug 15, 2023 | IBRD-91250 | Int Charges | 550,858.25 |
Feb 15, 2023 | IBRD-91250 | Int Charges | 32,295.31 |
Feb 15, 2023 | IBRD-91250 | Int Charges | 445,862.62 |
Aug 15, 2024 | IBRD-91250 | Int Charges | 3,675.58 |
Aug 15, 2024 | IBRD-91250 | Int Charges | 641,299.56 |
Aug 15, 2024 | IBRD-91250 | Loan Repay | 1,428,000.00 |
May 15, 2020 | IBRD-91250 | Loan Commitment | 20,000,000.00 |
Feb 15, 2024 | IBRD-91250 | Int Charges | 639,176.20 |
Oct 5, 2020 | IBRD-91250 | Fee Charges | 50,000.00 |
Name | Review | Date |
---|---|---|
Procurement | Satisfactory | 2023-06-23 |
Project Management | Satisfactory | 2023-06-23 |
Overall Implementation Progress (IP) | Satisfactory | 2023-06-23 |
Progress towards achievement of PDO | Satisfactory | 2023-06-23 |
Financial Management | Satisfactory | 2023-06-23 |
Monitoring and Evaluation | Satisfactory | 2023-06-23 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 11-28-2022 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | |
Bank Performance | Substantial |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of treated COVID-19 patients covered through NHIS that required inpatient services per approved protocols | Value | 0.00 | 1370.00 | 0.00 |
Date | March 31, 2020 | May 31, 2022 | ||
Comment |
Number of people covered through NHIS that have been tested for COVID-19 at least once | Value | 0.00 | 126500.00 | 0.00 |
Date | March 31, 2020 | May 31, 2022 | ||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Proportion of health providers within the National Health Insurance that report the utilization of inpatient care services with patient level information through the electronic medical records | Value | 0.00 | 85.00 | 0.00 |
Date | March 31, 2020 | May 31, 2022 | ||
Comment |
Number of health workers that have been tested for COVID-19 | Value | 0.00 | 20000.00 | 0.00 |
Date | March 31, 2020 | May 31, 2022 | ||
Comment |