Skip to Main Navigation

North Macedonia Emergency COVID-19 Response Project

Abstract*

This Project Appraisal Document (PAD) describes the emergency response to North Macedonia under the coronavirus disease (COVID-19). The COVID-19 Strategic Preparedness and Response Program (SPRP) using the Multiphase Programmatic Approach (MPA), was approved by the World Bank’s Board of Executive Directors on April 2, 2020 (PCBASIC0219761) with an overall Program financing envelope of up to US $6.00 billion. The project has three components: (1)...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To prevent, detect and respond to the threat posed by COVID-19 and strengthen national systems for public health preparedness in North Macedonia.

Key Details

Project Details

  • P173916

  • Closed

  • Federica Secci , Sarah Coll-Black, Yoshini Rupasinghe

  • Republic of North Macedonia

  • North Macedonia

  • April 22, 2020

  • (as of board presentation)

    April 30, 2020

  • October 29, 2020

  • US$ 100.00 million

  • Ministry of Health,Ministry of Labor and Social Policy

  • Europe and Central Asia

  • 2020

  • US$ 98.50 million

  • N/A

  • Substantial

  • December 31, 2022

  • No

  • BANK APPROVED

  • March 28, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 98.50

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 98.50
IDA Commitment N/A
IBRD + IDA Commitment 98.50
Lending Instrument
Grant Amount N/A
Total Project Cost** 100.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Nov 30, 2020 IBRD-91090 Loan Disb 8,874,854.00
Sep 15, 2023 IBRD-91090 Int Charges 1,875,718.90
Nov 5, 2020 IBRD-91090 Loan Disb 11,811,500.00
Oct 29, 2020 IBRD-91090 Loan Disb 264,105.00
Oct 29, 2020 IBRD-91090 Fee Charges 264,105.00
Jan 22, 2021 IBRD-91090 Loan Disb 4,974,135.50
Mar 15, 2022 IBRD-91090 Int Charges 18,020.88
Mar 15, 2022 IBRD-91090 Int Charges 3,368.13
Mar 31, 2022 IBRD-91090 Loan Disb 8,875,200.00
Aug 16, 2021 IBRD-91090 Loan Disb 898,328.90
Nov 9, 2021 IBRD-91090 Loan Disb 3,564,291.50
Sep 28, 2021 IBRD-91090 Loan Disb 10,528,889.00
Sep 15, 2021 IBRD-91090 Int Charges 139.56
May 18, 2021 IBRD-91090 Loan Disb 8,545,600.00
May 5, 2021 IBRD-91090 Loan Disb 872,270.25
Jul 13, 2021 IBRD-91090 Loan Disb 6,797,483.50
Jun 21, 2021 IBRD-91090 Loan Disb 414,442.12
Mar 15, 2021 IBRD-91090 Int Charges 2,360.19
Dec 3, 2020 IBRD-91090 Loan Disb 12,129,000.00
Apr 27, 2023 IBRD-91090 Loan Disb -786,202.06
Feb 17, 2023 IBRD-91090 Loan Disb 6,139,652.00
Dec 15, 2022 IBRD-91090 Loan Disb -1,374,810.20
Mar 15, 2023 IBRD-91090 Int Charges 12,365.15
Mar 15, 2023 IBRD-91090 Int Charges 852,068.30
Feb 10, 2023 IBRD-91090 Loan Disb 2,582,930.00
Sep 15, 2022 IBRD-91090 Int Charges 25,401.39
Sep 15, 2022 IBRD-91090 Int Charges 24,924.42
Oct 6, 2022 IBRD-91090 Loan Disb 7,056,479.00
Nov 29, 2022 IBRD-91090 Loan Disb 1,253,320.90
Nov 29, 2022 IBRD-91090 Loan Disb 417,773.66
Nov 30, 2022 IBRD-91090 Loan Disb 3,991,005.00
Apr 30, 2020 IBRD-91090 Loan Commitment 98,500,000.00
Mar 15, 2024 IBRD-91090 Int Charges 2,052,125.80
Mar 15, 2024 IBRD-91090 Loan Repay 5,406,692.00
May 9, 2023 IBRD-91090 Loan Cancel 782,649.75
Sep 15, 2023 IBRD-91090 Int Charges 1,678.13
Sep 15, 2023 IBRD-91090 Int Charges 12,001.36
Sep 15, 2023 IBRD-91090 Int Charges 62.73
Sep 15, 2023 IBRD-91090 Loan Repay 5,290,029.00
Nov 30, 2020 IBRD-91090 Loan Disb 4,940,801.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Overall Implementation Progress (IP) Satisfactory 2023-12-01
Progress towards achievement of PDO Satisfactory 2023-12-01
Financial Management Satisfactory 2023-12-01
Monitoring and Evaluation Satisfactory 2023-12-01
Procurement Satisfactory 2023-12-01
Project Management Satisfactory 2023-12-01

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of people tested for COVID-19 identification per MoH approved protocolValue11556.000.000.00
    DateMay 18, 2020June 22, 2021
    Comment
  • Recovery rate from COVID-19Value77.0096.500.00
    DateMay 18, 2020June 22, 2021
    Comment
  • Number of new beneficiaries receiving financial support to enable social distancingValue0.0089647.000.00
    DateMay 18, 2020June 22, 2021
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of GMI beneficiariesValue27000.0033605.000.00
    DateMay 18, 2020June 22, 2021
    Comment
  • Number of designated laboratories with COVID-19 diagnostic equipment, test kits, and reagents per MoH guidelinesValue2.0060.000.00
    DateMay 18, 2020June 22, 2021
    Comment
  • Number of unemployment insurance beneficiariesValue4700.000.000.00
    DateMay 18, 2020June 22, 2021
    Comment
  • Number of acute healthcare facilities with isolation capacityValue0.0017.000.00
    DateMay 18, 2020June 22, 2021
    Comment
  • Number of households (recipients of means-tested programs) provided with food and hygienic packagesValue0.000.000.00
    DateMay 18, 2020June 22, 2021
    Comment
  • Number of ventilators purchasedValue0.000.000.00
    DateMay 18, 2020June 22, 2021
    Comment
  • Implementation of new application procedures for COVID-19 pandemic related social protection measuresValuenot implementedSystem functional but not yet in use
    DateMay 18, 2020June 22, 2021
    Comment
  • Number of personal protective equipment (PPE) purchasedValue0.000.000.00
    DateMay 18, 2020June 22, 2021
    Comment
  • Percentage of beneficiaries reporting satisfaction with the community engagement processesValue0.000.000.00
    DateDecember 1, 2020June 22, 2021
    Comment
  • Number of additional fully equipped ICU beds for treatment of COVID-19 casesValue0.00583.000.00
    DateMay 18, 2020June 22, 2021
    Comment
  • Number of health care workers trained in infection prevention and control per MoH approved protocol.Value0.000.000.00
    DateMay 18, 2020June 22, 2021
    Comment
  • Number of doctors and nurses trained to treat patients with COVID-19 per approved MoH protocolValue126.000.000.00
    DateMay 18, 2020June 22, 2021
    Comment