Skip to Main Navigation

Lesotho COVID-19 Emergency Preparedness and Response Project

Abstract*

The objective of the COVID-19 (Coronavirus) Emergency Preparedness and Response Project for Lesotho is to prevent, detect and respond to the threat posed by COVID-19 and strengthen national systems for public health preparedness. The project has two components. 1. Emergency COVID-19 Response component consists of: a) strengthening COVID-19 case detection, confirmation, contact tracing, recording and reporting. The focus will be on: (i) screening travelers...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To prevent, detect and respond to the threat posed by COVID-19 to the Kingdom of Lesotho.

Key Details

Project Details

  • P173939

  • Closed

  • Noel Chisaka , Nkosinathi Mbuya

  • Kingdom of Lesotho

  • Lesotho

  • April 30, 2020

  • (as of board presentation)

    May 9, 2020

  • May 27, 2020

  • US$ 7.50 million

  • N/A

  • Substantial

  • December 31, 2024

  • Yes

  • BANK APPROVED

  • June 12, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 7.50

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 7.50
IBRD + IDA Commitment 7.50
Lending Instrument
Grant Amount N/A
Total Project Cost** 7.50

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Aug 15, 2021 IDA-66770 Int Charges 42,039.72
Aug 15, 2021 IDA-66770 Int Charges 42,039.72
Aug 15, 2021 IDA-66770 Int Charges 43,995.07
Jun 9, 2021 IDA-66770 Loan Disb 57,967.18
Sep 16, 2021 IDA-69300 Loan Disb 2,073,612.00
Oct 22, 2021 IDA-69300 Loan Disb 1,102,248.00
Aug 20, 2021 IDA-69300 Loan Disb 1,963,849.00
Feb 22, 2022 IDA-69300 Loan Disb 225,010.60
Mar 21, 2022 IDA-69300 Int Charges 39,515.01
Mar 21, 2022 IDA-69300 Int Charges 998.04
Mar 21, 2022 IDA-69300 Int Charges 998.04
Mar 21, 2022 IDA-69300 Int Charges 1,663.40
Mar 21, 2022 IDA-69300 Int Charges 23,708.98
Mar 21, 2022 IDA-69300 Int Charges 23,708.98
Mar 1, 2022 IDA-66770 Loan Disb 133,283.88
Jan 5, 2022 IDA-69300 Loan Disb 109,578.62
May 29, 2020 IDA-66770 Loan Disb 825,141.20
Jun 18, 2020 IDA-66770 Loan Disb 4,493,949.00
Dec 23, 2022 IDA-69300 Loan Disb 1,410,193.90
Sep 28, 2022 IDA-66770 Loan Disb 195,413.30
Sep 28, 2022 IDA-69300 Loan Disb 1,046,336.44
Aug 24, 2022 IDA-66770 Int Charges 46,202.53
Sep 19, 2022 IDA-69300 Int Charges 49,773.18
Sep 15, 2022 IDA-69300 Int Charges 951.88
Sep 15, 2022 IDA-69300 Int Charges 951.88
Sep 19, 2022 IDA-69300 Int Charges 28,912.59
Sep 19, 2022 IDA-69300 Int Charges 28,912.59
Feb 15, 2023 IDA-66770 Int Charges 13,717.64
Feb 15, 2023 IDA-66770 Int Charges 13,717.64
Feb 15, 2023 IDA-66770 Int Charges 39,265.99
Feb 15, 2023 IDA-66770 Int Charges 24,366.16
Feb 15, 2023 IDA-66770 Int Charges 24,366.16
Feb 15, 2023 IDA-66770 Int Charges 7,219.30
Feb 15, 2023 IDA-66770 Int Charges 7,219.30
Feb 15, 2023 IDA-66770 Int Charges 7,902.18
Mar 20, 2023 IDA-69300 Int Charges 37,634.13
Mar 20, 2023 IDA-69300 Int Charges 37,634.13
Mar 20, 2023 IDA-69300 Int Charges 61,251.24
Mar 15, 2023 IDA-69300 Int Charges 934.17
Mar 15, 2023 IDA-69300 Int Charges 934.17
Feb 24, 2023 IDA-69300 Loan Disb 3,129,502.00
Feb 24, 2023 IDA-66770 Loan Disb 89,598.79
Apr 24, 2023 IDA-69300 Loan Disb -109,578.48
Apr 24, 2023 IDA-69300 Loan Disb 109,578.48
Mar 18, 2021 IDA-66770 Int Charges 6,827.23
Mar 18, 2021 IDA-66770 Int Charges 6,827.23
Mar 18, 2021 IDA-66770 Int Charges 11,957.48
Mar 18, 2021 IDA-66770 Loan Disb 921,186.10
Sep 8, 2020 IDA-66770 Int Charges 4,598.80
Sep 8, 2020 IDA-66770 Int Charges 4,598.80
Nov 12, 2020 IDA-66770 Loan Disb 425,141.03
Mar 18, 2021 IDA-66770 Int Charges 35,724.91
Mar 18, 2021 IDA-66770 Int Charges 35,724.91
Mar 18, 2021 IDA-66770 Int Charges 37,386.53
Jun 1, 2021 IDA-69300 Loan Commitment 22,000,000.00
May 9, 2020 IDA-66770 Loan Commitment 7,500,000.00
Mar 15, 2024 IDA-69300 Int Charges 3,801.98
Mar 15, 2024 IDA-69300 Int Charges 3,801.98
Mar 15, 2024 IDA-69300 Int Charges 48,111.64
Mar 15, 2024 IDA-69300 Int Charges 48,111.64
Mar 15, 2024 IDA-69300 Int Charges 86,522.73
May 16, 2024 IDA-66770 Loan Disb 294,799.38
Apr 8, 2024 IDA-66770 Loan Disb -294,799.38
Aug 15, 2023 IDA-66770 Int Charges 48,603.63
Sep 15, 2023 IDA-69300 Int Charges 51,411.49
Sep 15, 2023 IDA-69300 Int Charges 51,411.49
Aug 15, 2023 IDA-66770 Int Charges 242.04
Aug 15, 2023 IDA-66770 Int Charges 46,444.33
Aug 15, 2023 IDA-66770 Int Charges 46,444.33
Sep 15, 2023 IDA-69300 Int Charges 2,991.44
Sep 15, 2023 IDA-69300 Int Charges 85,685.84
Aug 16, 2024 IDA-66770 Int Charges 345.97
Aug 16, 2024 IDA-66770 Int Charges 47,973.59
Aug 16, 2024 IDA-66770 Int Charges 47,973.59
Aug 16, 2024 IDA-66770 Int Charges 50,204.91
Feb 29, 2024 IDA-66770 Int Charges 48,465.69
Jan 29, 2024 IDA-66770 Loan Disb 294,849.88
Jul 26, 2024 IDA-69300 Loan Disb -875,157.00
Feb 29, 2024 IDA-66770 Int Charges 46,642.27
Feb 29, 2024 IDA-66770 Int Charges 46,642.27
Feb 29, 2024 IDA-66770 Int Charges 0.87
Aug 24, 2022 IDA-66770 Int Charges 44,149.10
Aug 24, 2022 IDA-66770 Int Charges 44,149.10
Mar 1, 2022 IDA-66770 Int Charges 45,382.86
Mar 1, 2022 IDA-66770 Int Charges 43,365.84
Mar 1, 2022 IDA-66770 Int Charges 43,365.84
Dec 21, 2021 IDA-69300 Loan Disb 3,201,768.00
Dec 23, 2022 IDA-66770 Loan Disb 63,469.57

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Overall Implementation Progress (IP) Satisfactory 2025-03-26
Procurement Satisfactory 2025-03-26
Progress towards achievement of PDO Satisfactory 2025-03-26
Project Management Satisfactory 2025-03-26
Financial Management Satisfactory 2025-03-26
Monitoring and Evaluation Satisfactory 2025-03-26

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Diagnosed cases treated per approved protocolValue0.0093.0090.00
    DateApril 27, 2020June 28, 2024December 31, 2024
    Comment
  • Total population vaccinatedValue0.0048.0050.00
    DateApril 16, 2021June 28, 2024December 31, 2024
    Comment
  • Total female population vaccinatedValue0.0027.000.00
    Date
    Comment
  • Total male population vaccinatedValue0.0018.000.00
    Date
    Comment
  • COVID-19 PCR tests processed within two daysValue15.00100.0070.00
    DateApril 16, 2021June 28, 2024December 31, 2024
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Grievances addressed on time (as specified in the Stakeholder Engagement Plan)Value0.0084.00100.00
    DateDecember 1, 2020June 28, 2024December 31, 2024
    Comment
  • Doses of eligible COVID-19 vaccines procuredValue892800.00741600.00800000.00
    DateMay 31, 2022June 28, 2024December 31, 2024
    Comment
  • Health staff trained in COVID-19 vaccination deployment per MOH-approved protocolsValue0.00270.00400.00
    DateApril 19, 2021June 28, 2024December 31, 2024
    Comment
  • Female health staff trained in COVID-19 vaccination deployment per MOH-approved protocolsValue0.00211.00300.00
    DateApril 19, 2021June 28, 2024December 31, 2024
    Comment
  • Male health staff trained in COVID-19 vaccination deployment per MOH-approved protocolsValue0.0059.00100.00
    DateApril 19, 2021June 28, 2024December 31, 2024
    Comment
  • A patient feedback mechanism for COVID-19 vaccinations is in place and functionalValueNoYesYes
    DateApril 19, 2021June 28, 2024December 31, 2024
    Comment
  • COVID-19 related information and education sessions targeting womenValue0.00773.00500.00
    DateApril 19, 2021June 28, 2024December 31, 2024
    Comment
  • Serious AEFI after COVID-19 vaccination investigatedValue0.0092.0095.00
    DateApril 19, 2021June 28, 2024December 31, 2024
    Comment
  • Intensive Care Units refurbishedValue1.002.003.00
    DateApril 19, 2021June 28, 2024December 31, 2024
    Comment
  • National Reference Laboratory is expanded, equipped and functionalValueNoNoYes
    DateApril 19, 2021June 28, 2024December 31, 2024
    Comment
  • Health staff trained in COVID-19 case management per MOH-approved protocolsValue0.0060.0085.00
    DateApril 19, 2021June 28, 2024December 31, 2024
    Comment
  • Oxygen plants establishedValue0.002.002.00
    DateApril 19, 2021June 28, 2024December 31, 2024
    Comment