Financier | Commitments |
---|---|
IDA Credit | 142.00 |
Global P'ship for Sust. and Resilient Landscapes - PROGREEN | 8.00 |
Korea WB Partnership Facility | 3.00 |
P174135
Active
Asferachew Abebe
Republic of Uzbekistan
Central Asia
November 11, 2020
(as of board presentation)
June 7, 2022
March 29, 2024
US$ 153.00 million
Forestry Agency
2022
US$ 153.00 million
N/A
October 23, 2023
September 15, 2028
No
BANK APPROVED
Financier | Commitments |
---|---|
IDA Credit | 142.00 |
Global P'ship for Sust. and Resilient Landscapes - PROGREEN | 8.00 |
Korea WB Partnership Facility | 3.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 142.00 |
IBRD + IDA Commitment | 142.00 |
Lending Instrument | |
---|---|
Grant Amount | 11.00 |
Total Project Cost** | 153.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Aug 15, 2024 | IDA-71380 | Int Charges | 2,427.97 |
Aug 15, 2024 | IDA-71380 | Int Charges | 2,427.97 |
Jun 6, 2024 | IDA-71380 | Loan Disb | 967,000.00 |
Aug 15, 2024 | IDA-71380 | Int Charges | 2,502.12 |
Jun 7, 2022 | IDA-71380 | Loan Commitment | 142,000,000.00 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2024-12-03 |
Monitoring and Evaluation | Satisfactory | 2024-12-03 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2024-12-03 |
Financial Management | Satisfactory | 2024-12-03 |
Procurement | Satisfactory | 2024-12-03 |
Project Management | Moderately Satisfactory | 2024-12-03 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Land area under sustainable landscape management practices | Value | 0.00 | 0.00 | 280000.00 |
Date | May 17, 2022 | September 20, 2023 | September 15, 2028 | |
Comment |
Transboundary sustainable landscape management policies harmonized | Value | 0.00 | 0.00 | 5.00 |
Date | May 17, 2022 | September 20, 2023 | September 15, 2028 | |
Comment |
People benefiting from landscape management practices | Value | 0.00 | 0.00 | 500000.00 |
Date | May 17, 2022 | September 20, 2023 | September 15, 2028 | |
Comment |
People benefiting from landscape management practices - Female | Value | 0.00 | 0.00 | 150000.00 |
Date | May 17, 2022 | September 20, 2023 | September 15, 2028 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Beneficiaries reporting effective engagement processes through the regional online database | Value | 0.00 | 0.00 | 80.00 |
Date | May 17, 2022 | September 20, 2023 | September 15, 2028 | |
Comment |
Beneficiaries of job-focused interventions - Female | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Beneficiaries satisfied with project-supported services | Value | 0.00 | 0.00 | 80.00 |
Date | May 17, 2022 | September 20, 2023 | September 15, 2028 | |
Comment |
Beneficiaries reporting effective engagement processes through the regional online database - female | Value | 0.00 | 0.00 | 80.00 |
Date | May 17, 2022 | September 20, 2023 | September 15, 2028 | |
Comment |
Beneficiaries satisfied with project-supported services- Female | Value | 0.00 | 0.00 | 80.00 |
Date | May 17, 2022 | September 20, 2023 | September 15, 2028 | |
Comment |
Net greenhouse gas (GHG) emissions | Value | 0.00 | 0.00 | 373893.00 |
Date | May 17, 2022 | September 20, 2023 | September 15, 2028 | |
Comment |
Enabling environment for Land Degradation Neutrality and Nationally Determined Contribution targets improved | Value | No | No | Yes |
Date | May 17, 2022 | September 20, 2023 | September 15, 2028 | |
Comment |
Land area under improved agroforestry systems, plantation, reforestation, and/or grazing management | Value | 0.00 | 0.00 | 253464.00 |
Date | May 17, 2022 | September 20, 2023 | September 15, 2028 | |
Comment |
Protected area under improved management | Value | 0.00 | 0.00 | 26536.00 |
Date | May 17, 2022 | September 20, 2023 | September 15, 2028 | |
Comment |
Feedback/grievances resolved within the stipulated service standards for response time | Value | 0.00 | 0.00 | 80.00 |
Date | May 17, 2022 | September 20, 2023 | September 15, 2028 | |
Comment |
A technology-based National Forest Inventory developed and operational | Value | No NFI in place | No NFI in place | First cycle NFI in place |
Date | May 17, 2022 | September 20, 2023 | September 15, 2028 | |
Comment |
Land-users adopting landscape restoration practices | Value | 0.00 | 0.00 | 25000.00 |
Date | May 17, 2022 | September 20, 2023 | September 15, 2028 | |
Comment |
A National ICT Platform for Forest Landscape Restoration and Management developed and operational | Value | No ICT platform in place | No ICT platform in place | ICT Platform in place and operational |
Date | May 17, 2022 | September 20, 2023 | September 15, 2028 | |
Comment |
Increase in Protected Areas Management Effectiveness Tracking Tool (METT) score | Value | 0.00 | 0.00 | 10.00 |
Date | May 17, 2022 | September 20, 2023 | September 15, 2028 | |
Comment |
Land-users adopting landscape restoration practices - female | Value | 0.00 | 0.00 | 7500.00 |
Date | May 17, 2022 | September 20, 2023 | September 15, 2028 | |
Comment |
New or existing natural resource-based enterprises that receive financing | Value | 0.00 | 0.00 | 250.00 |
Date | May 17, 2022 | September 20, 2023 | September 15, 2028 | |
Comment |
Nature-based tourism infrastructure established or upgraded in Protected Areas and State Forest Fund Land | Value | 0.00 | 0.00 | 20.00 |
Date | May 17, 2022 | September 20, 2023 | September 15, 2028 | |
Comment |
New or existing natural resource-based enterprises owned by women that receive financing | Value | 0.00 | 0.00 | 125.00 |
Date | May 17, 2022 | September 20, 2023 | September 15, 2028 | |
Comment |
Regional online database established and operational | Value | A thematic portal on energy, water, climate, agric | A thematic portal on energy, water, climate, agric | A regional online database on sustainable landscap |
Date | May 17, 2022 | September 20, 2023 | September 15, 2028 | |
Comment |
Beneficiaries of job-focused interventions | Value | 0.00 | 0.00 | 8500.00 |
Date | May 17, 2022 | September 20, 2023 | September 15, 2028 | |
Comment |