Nghe An Province's Vinh City Priority Infrastructure and Urban Resilience Development Project

Abstract*

The development objective of the Nghe An Province’s Vinh City Priority Infrastructure and Urban Resilience Development Project for Vietnam is to reduce flood risk in the core urban area, strengthen capacity for urban resilience management, and support the development of integrated infrastructure in Vinh city. The project comprises of four components. The first component, integrated drainage, environmental sanitation, and connectivity investments will...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Project Development Objective (PDO) is to reduce flood risk in the core urban area, strengthen capacity for urban resilience management, and support the development of integrated infrastructure in Vinh City.

Key Details

Project Details

  • P174157

  • Active

  • Cuong Dang , Thu Nguyen

  • The Socialist Republic of Vietnam

  • Viet Nam

  • June 24, 2020

  • (as of board presentation)

    July 28, 2023

  • December 2, 2024

  • US$ 194.50 million

  • People's Committee of Nghe An Province

  • East Asia and Pacific

  • 2024

  • US$ 129.60 million

  • N/A

  • November 10, 2023

  • December 2, 2030

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrower/Recipient 64.90
International Bank for Reconstruction and Development 129.60

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 129.60
IDA Commitment N/A
IBRD + IDA Commitment 129.60
Lending Instrument
Grant Amount N/A
Total Project Cost** 194.50

Summary Status of World Bank Financing (US$ Millions) as of January 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of January 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jul 28, 2023 IBRD-95820 Loan Commitment 129,600,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Satisfactory 2024-10-19
Project Management Satisfactory 2024-10-19
Progress towards achievement of PDO Satisfactory 2024-10-19
Financial Management Satisfactory 2024-10-19
Monitoring and Evaluation Satisfactory 2024-10-19
Overall Implementation Progress (IP) Satisfactory 2024-10-19

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Area under enhanced flood protectionValue0.000.001500.00
    DateJune 30, 2023October 16, 2023November 30, 2029
    Comment
  • Operationalization of integrated flood risk management systemValueNoNoYes
    DateJune 30, 2023October 16, 2023November 30, 2029
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Additional wastewater pumping capacity installed or upgraded (Cubic meters/hour)Value001,200
    DateJune 30, 2023October 16, 2023November 30, 2029
    Comment
  • Stormwater conveyance capacity of the municipal system (Cubic meters/hour)Value1,800,0001,800,0006,500,000
    DateJune 30, 2023October 16, 2023November 30, 2029
    Comment
  • Length of new or upgraded embankment builtValue0.000.0011.60
    DateJune 30, 2023October 16, 2023November 30, 2029
    Comment
  • Flood risk management equipment installedValueNoNoYes
    DateJune 30, 2023October 16, 2023November 30, 2029
    Comment
  • Households provided with access to new or rehabilitated secondary and tertiary sewersValue0.000.0030000.00
    DateJune 30, 2023October 16, 2023November 30, 2029
    Comment
  • Additional stormwater retention capacity producedValue0.000.00800000.00
    DateJune 30, 2023October 16, 2023November 30, 2029
    Comment
  • Level of water pollution discharged to the Vinh river (biochemical oxygen demand (milligrams/liter)Value989825
    DateJune 30, 2023October 16, 2023November 30, 2029
    Comment
  • Operation procedures for integrated flood risk management system adoptedValueNoNoYes
    DateJune 30, 2023October 16, 2023November 30, 2029
    Comment
  • Length of new or rehabilitated sewers and drains installedValue0.000.0070.00
    DateJune 30, 2023October 16, 2023November 30, 2029
    Comment
  • Additional stormwater pumping capacity installed or upgraded (Cubic meters/hour)Value00115,000
    DateJune 30, 2023October 16, 2023November 30, 2029
    Comment
  • Operation procedures for wastewater treatment plant adoptedValueNoNoYes
    DateJune 30, 2023October 16, 2023November 30, 2029
    Comment
  • Reduction in amount of time spent by women on unpaid housework after flooding, including cleaningValue0.000.0050.00
    DateJune 30, 2023October 16, 2023November 30, 2029
    Comment
  • Beneficiaries involved in consultations for project planning/ implementation/ evaluationValue0.000.002000.00
    DateJune 30, 2023October 16, 2023November 30, 2029
    Comment
  • Of which Female beneficiariesValue0.000.0052.00
    Date
    Comment
  • Share of grievances received that are addressedValue0.000.0098.00
    DateJune 30, 2023October 16, 2023November 30, 2029
    Comment