Financier | Commitments |
---|---|
FRANCE: French Agency for Development | 200.00 |
International Bank for Reconstruction and Development | 100.00 |
P174251
Active
Sudeshna Mitra , Axel Baeumler
Republic of Serbia
February 10, 2021
(as of board presentation)
March 9, 2022
May 18, 2023
US$ 300.00 million
Ministry of Construction, Transport, and Infrastructure
2022
US$ 300.00 million
N/A
Moderate
November 30, 2028
TBD
BANK APPROVED
January 23, 2024
Financier | Commitments |
---|---|
FRANCE: French Agency for Development | 200.00 |
International Bank for Reconstruction and Development | 100.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 100.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 100.00 |
Lending Instrument | |
---|---|
Grant Amount | 200.00 |
Total Project Cost** | 300.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Nov 15, 2023 | IBRD-93390 | Loan Disb | 3,436,091.00 |
Mar 9, 2022 | IBRD-93390 | Loan Commitment | 100,000,000.00 |
Jun 12, 2023 | IBRD-93390 | Fee Charges | 238,083.30 |
Jun 15, 2024 | IBRD-93390 | Int Charges | 77,041.40 |
Jun 15, 2024 | IBRD-93390 | Int Charges | 114,013.20 |
Dec 15, 2023 | IBRD-93390 | Int Charges | 120,826.76 |
Dec 15, 2023 | IBRD-93390 | Int Charges | 81,690.49 |
Jun 15, 2024 | IBRD-93390 | Int Charges | 695.13 |
Jun 15, 2024 | IBRD-93390 | Int Charges | 11,511.73 |
Name | Review | Date |
---|---|---|
Procurement | Moderately Unsatisfactory | 2025-01-28 |
Progress towards achievement of PDO | Satisfactory | 2025-01-28 |
Financial Management | Satisfactory | 2025-01-28 |
Project Management | Moderately Satisfactory | 2025-01-28 |
Monitoring and Evaluation | Moderately Satisfactory | 2025-01-28 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2025-01-28 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
LSGs with developed annual and multi-annual budgets corresponding to development plans and asset management systems | Value | 0.00 | 0.00 | 15.00 |
Date | October 25, 2021 | January 23, 2024 | November 30, 2028 | |
Comment |
Commercial and social services connected by improved, safe and resilient transport network | Value | 0.00 | 0.00 | 420.00 |
Date | October 25, 2021 | January 23, 2024 | November 30, 2028 | |
Comment |
Subprojects supporting climate adaptation and/or mitigation actions | Value | 0.00 | 0.00 | 100.00 |
Date | October 25, 2021 | January 23, 2024 | December 29, 2028 | |
Comment |
LSGs utilizing simple road asset management methods developed under the project | Value | 0.00 | 0.00 | 50.00 |
Date | October 25, 2021 | January 23, 2024 | November 30, 2028 | |
Comment |
Citizens reporting satisfaction with process of infrastructure service delivery, gender disaggregated | Value | 0.00 | 0.00 | 70.00 |
Date | October 25, 2021 | January 23, 2024 | November 30, 2028 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
SUMPs and Action Plans adopted by LSGs | Value | 9.00 | 9.00 | 34.00 |
Date | October 25, 2021 | January 23, 2024 | November 30, 2028 | |
Comment |
Awareness campaigns on greening of infrastructure and sustainable mobility delivered | Value | 0.00 | 0.00 | 10.00 |
Date | October 25, 2021 | January 23, 2024 | November 30, 2028 | |
Comment |
LSGs piloted enhanced strategic participatory planning approaches | Value | 0.00 | 0.00 | 10.00 |
Date | September 16, 2021 | January 23, 2024 | November 30, 2028 | |
Comment |
Smart mobility pilots implemented | Value | 0.00 | 0.00 | 5.00 |
Date | September 16, 2021 | January 23, 2024 | November 30, 2028 | |
Comment |
Roadmap for improved access to financing developed | Value | No | No | Yes |
Date | September 16, 2021 | January 23, 2024 | November 30, 2028 | |
Comment |
LSGs with road safety interventions for children identified and budgeted | Value | 0.00 | 0.00 | 15.00 |
Date | September 16, 2021 | January 23, 2024 | November 30, 2028 | |
Comment |
Database for public investments at the local level, compatible to central level PIMIS developed | Value | No | No | Yes |
Date | October 25, 2021 | January 23, 2024 | November 30, 2028 | |
Comment |
Framework Agreements signed between LSGs and central government | Value | 0.00 | 145.00 | 145.00 |
Date | October 25, 2021 | January 23, 2024 | November 30, 2028 | |
Comment |
Increase in number of works contracts finished within planned time | Value | 0.00 | 0.00 | 50.00 |
Date | September 16, 2021 | January 23, 2024 | November 30, 2028 | |
Comment |
Share of investments dedicated to non motorized transport | Value | 0.00 | 0.00 | 20.00 |
Date | October 25, 2021 | January 23, 2024 | November 30, 2028 | |
Comment |
Pipeline of urban development and municipal infrastructure projects prepared | Value | 0.00 | 0.00 | 10.00 |
Date | October 25, 2021 | January 23, 2024 | November 30, 2028 | |
Comment |
Number of internships completed, with women making at least 70 percent | Value | 0.00 | 0.00 | 40.00 |
Date | October 25, 2021 | January 23, 2024 | November 30, 2028 | |
Comment |