Skip to Main Navigation

Bangladesh COVID 19 School Sector Response (GPE)

Abstract*

This Bangladesh COVID 19 School Sector Response Project will provide grant in the amount of US$14,800,000 through the Global Partnership for Education (GPE) Accelerated Funding window for COVID 19 response in basic education. The proposed GPE fund is in response to a request from the Government of Bangladesh (GOB). The World Bank has been selected as the Grant Agent (GA) for processing and supervising the proposed grant through the consensus of the...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Project Development Objectives (PDOs) are to (i) strengthen the basic school system’s institutional capacity to respond to, and recover from, the COVID-19 crisis; and (ii) build resilience to face future crises from preprimary to secondary levels.

Key Details

Project Details

  • P174268

  • Closed

  • Tashmina Rahman , Mokhlesur Rahman

  • PEOPLE’S REPUBLIC OF BANGLADESH

  • Bangladesh

  • August 14, 2020

  • (as of board presentation)

    October 20, 2020

  • February 15, 2021

  • US$ 14.80 million

  • Ministry of Primary and Mass Education

  • South Asia

  • 2021

  • US$ 14.80 million

  • N/A

  • June 21, 2023

  • December 31, 2022

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Education for All - Fast Track Initiative 14.80

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 14.80
Total Project Cost** 14.80

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Overall Implementation Progress (IP) Satisfactory 2022-12-22
Progress towards achievement of PDO Satisfactory 2022-12-22
Procurement Satisfactory 2022-12-22
Project Management Satisfactory 2022-12-22
Financial Management Satisfactory 2022-12-22
Monitoring and Evaluation Satisfactory 2022-12-22

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 06-21-2023
OutcomesSubstantial
Risk to Development Outcome
Bank PerformanceSubstantial
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 11-21-2023PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingSatisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceSatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceN/a
Implementing AgencyN/a
Icr QualityHighN/a
M&e QualityHighN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number (and % of children in the relevant age-group in the program area) of children supported with inclusive distance learning programs (disaggregated by gender)Value0.002500000.000.00
    DateJune 30, 2020December 30, 2022
    Comment
  • Remote learning system integrated into the basic education school systemValueUnderdeveloped Remote Learning SystemRemote learning System fully functional and integr
    DateApril 30, 2020December 30, 2022
    Comment
  • Number (and %) of children who were enrolled in grant-supported preprimary and primary level government schools before the COVID-19pandemic have returned to schoolsValue0.003240000.000.00
    DateJune 30, 2020December 30, 2022
    Comment
  • BoysValue0.001205000.000.00
    DateJune 30, 2020December 30, 2022
    Comment
  • BoysValue0.001590000.000.00
    DateJune 30, 2020December 30, 2022
    Comment
  • GirlsValue0.001295000.000.00
    DateJune 30, 2020December 30, 2022
    Comment
  • GirlsValue0.001650000.000.00
    DateJune 30, 2020December 30, 2022
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of grade - subject programs with complete and appropriate digital contents supported for the whole academic year for Grade 1-10 (Number)Value0.0035.000.00
    DateApril 30, 2020December 30, 2022
    Comment
  • Number (and %) of primary schools re-opened following implementation of Safe School Re-opening PlanValue0.0020000.000.00
    DateJune 30, 2020December 30, 2022
    Comment
  • Sustainability Plan for the Remote Learning System in place for basic school systemValueNo Sustainability Plan is in placeSustainability Plan for the Remote Learning System
    DateApril 30, 2020December 30, 2022
    Comment
  • Number of hard-to-reach children provided with learning materials/packagesValue0.00150000.000.00
    DateJune 30, 2020December 30, 2022
    Comment
  • Standard Emergency Operation Procedures for junior secondary school system preparedValueNo Standard Emergency Operation Procedures in placStandard Emergency Operation Procedures for junior
    DateApril 30, 2020December 30, 2022
    Comment
  • Percentage of primary schools re-opened following implementation of Safe School Re-opening PlanValue0.0031.000.00
    DateJune 30, 2020December 30, 2022
    Comment
  • Number (and % of children in program area) of children whose learning was assessed to evaluate loss of learning during school closureValue0.0060000.000.00
    DateJune 30, 2020December 30, 2022
    Comment
  • Students benefiting from direct interventions to enhance learningValue0.0035900000.000.00
    DateJune 30, 2020December 30, 2022
    Comment
  • Percentage of children in program area whose learning was assessed to evaluate loss of learning during school closureValue0.001.500.00
    DateJune 30, 2020December 30, 2022
    Comment
  • Students benefiting from direct interventions to enhance learning - FemaleValue0.000.000.00
    Date
    Comment
  • Number (and % of teachers in program area) of teachers trained on remedial education, distance learning strategies, and formative and summative assessment practicesValue0.002000.000.00
    DateJune 30, 2020December 30, 2022
    Comment
  • Percentage of teachers trained on remedial education, distance learning strategies, and formative and summative assessment practicesValue0.000.600.00
    DateJune 30, 2020December 30, 2022
    Comment