Financier | Commitments |
---|---|
IBRD Guarantee | 10.00 |
P174322
Active
Bahodir Amonov , Philip Lam
Ministry of Economy and Finance
May 27, 2021
(as of board presentation)
March 7, 2023
N/A
US$ 450.00 million
National Electric Grid of Uzbekistan (NEGU)
2023
US$ 0.00 million
N/A
December 19, 2024
July 1, 2025
BANK APPROVED
Financier | Commitments |
---|---|
IBRD Guarantee | 10.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 450.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Nov 1, 2023 | IBRD-G3940 | Fee Charges | 25,305.00 |
Nov 2, 2023 | IBRD-G3920 | Fee Charges | 124,680.00 |
Nov 1, 2023 | IBRD-G3940 | Int Charges | 25,305.00 |
Nov 1, 2023 | IBRD-G3920 | Fee Charges | 24,680.00 |
Nov 1, 2023 | IBRD-G3920 | Int Charges | 24,680.00 |
Mar 7, 2023 | IBRD-G3930 | Loan Commitment | 12,000,000.00 |
Nov 2, 2023 | IBRD-G3940 | Int Charges | 125,305.00 |
Nov 2, 2023 | IBRD-G3940 | Fee Charges | 125,305.00 |
Nov 2, 2023 | IBRD-G3920 | Int Charges | 124,680.00 |
Name | Review | Date |
---|---|---|
Project Management | Satisfactory | 2024-11-08 |
Financial Management | Satisfactory | 2024-11-08 |
Overall Implementation Progress (IP) | Satisfactory | 2024-11-08 |
Procurement | Satisfactory | 2024-11-08 |
Progress towards achievement of PDO | Satisfactory | 2024-11-08 |
Monitoring and Evaluation | Satisfactory | 2024-11-08 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Power generation capacity constructed (renewable/solar) | Value | 0.00 | 396.00 | 440.00 |
Date | March 7, 2023 | September 11, 2024 | June 30, 2025 | |
Comment |
Electricity supplied by the Project into the grid (renewable/solar) | Value | 0.00 | 437.86 | 1100.00 |
Date | March 7, 2023 | September 11, 2024 | June 30, 2025 | |
Comment |
Private capital mobilized | Value | 0.00 | 0.00 | 205000000.00 |
Date | March 7, 2023 | September 11, 2024 | June 30, 2025 | |
Comment |
Greenhouse gas emissions avoided | Value | 0.00 | 43380.00 | 109000.00 |
Date | March 7, 2023 | September 11, 2024 | June 30, 2025 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Physical implementation progress in generation project constructed (percentage) | Value | 0.00 | 90.00 | 100.00 |
Date | March 7, 2023 | September 11, 2024 | June 30, 2025 | |
Comment |
Project commissioning test completed | Value | No | No | Yes |
Date | March 7, 2023 | September 11, 2024 | June 30, 2025 | |
Comment |