Financier | Commitments |
---|---|
IBRD Guarantee | 29.00 |
P174323
Active
Bahodir Amonov , Philip Lam
Ministry of Economy and Finance
January 21, 2021
(as of board presentation)
May 9, 2023
N/A
US$ 1400.00 million
National Electric Grid of Uzbekistan (NEGU)
2023
US$ 0.00 million
N/A
Not Applicable
June 30, 2026
BANK APPROVED
December 19, 2024
Financier | Commitments |
---|---|
IBRD Guarantee | 29.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 1400.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
May 9, 2023 | IBRD-G3910 | Loan Commitment | 29,000,000.00 |
Feb 29, 2024 | IBRD-G3910 | Fee Charges | 245,000.00 |
Feb 29, 2024 | IBRD-G3910 | Int Charges | 245,000.00 |
Name | Review | Date |
---|---|---|
Project Management | Satisfactory | 2024-09-27 |
Overall Implementation Progress (IP) | Satisfactory | 2024-09-27 |
Procurement | Satisfactory | 2024-09-27 |
Progress towards achievement of PDO | Satisfactory | 2024-09-27 |
Financial Management | Satisfactory | 2024-09-27 |
Monitoring and Evaluation | Satisfactory | 2024-09-27 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Power generation capacity units constructed | Value | 0.00 | 0.00 | 1573.00 |
Date | April 17, 2023 | September 20, 2024 | July 1, 2025 | |
Comment |
Electricity supplied by the Project into the grid | Value | 0.00 | 0.00 | 12800.00 |
Date | April 17, 2023 | September 20, 2024 | June 30, 2026 | |
Comment |
Performance deemed compliant with PPA requirements on availability, efficiency, minimum stable load, start-up time and ramp rates | Value | No | No | Yes |
Date | April 17, 2023 | September 20, 2024 | June 30, 2026 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Private capital mobilized (equity/debt) | Value | 0.00 | 0.00 | 517000000.00 |
Date | April 17, 2023 | February 8, 2024 | July 1, 2025 | |
Comment |
Physical implementation progress in generation project constructed | Value | 0.00 | 0.00 | 100.00 |
Date | April 17, 2023 | February 8, 2024 | July 1, 2025 | |
Comment |
Project commissioning test completed | Value | No | No | Yes |
Date | April 17, 2023 | February 8, 2024 | July 1, 2025 | |
Comment |