Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 500.00 |
Borrower/Recipient | 159.50 |
Canada Clean Energy and Forest Climate Facility Trust Fund | 47.50 |
Clean Technology Fund | 34.00 |
P174350
Active
Sabine Cornieti , Puguh Imanto
PT PLN (Persero)
May 6, 2021
(as of board presentation)
June 26, 2023
July 31, 2024
US$ 1141.00 million
PT PLN Persero (PLN)
2023
US$ 581.50 million
N/A
Not Applicable
June 30, 2029
Yes
BANK APPROVED
October 1, 2023
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 500.00 |
Borrower/Recipient | 159.50 |
Canada Clean Energy and Forest Climate Facility Trust Fund | 47.50 |
Clean Technology Fund | 34.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 500.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 500.00 |
Lending Instrument | |
---|---|
Grant Amount | 81.50 |
Total Project Cost** | 1141.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jun 26, 2023 | TF-C1477 | Loan Commitment | 15,000,000.00 |
Jun 26, 2023 | IBRD-95570 | Loan Commitment | 500,000,000.00 |
Jun 26, 2023 | TF-C1478 | Loan Commitment | 47,500,000.00 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Moderately Satisfactory | 2024-11-22 |
Monitoring and Evaluation | Moderately Satisfactory | 2024-11-22 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2024-11-22 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Generation capacity of energy constructed or rehabilitated | Value | 0.00 | 0.00 | 600.00 |
Date | July 20, 2021 | July 30, 2026 | ||
Comment |
Renewable energy generation capacity (other than hydropower) constructed under the project | Value | 0.00 | 0.00 | 600.00 |
Date | July 1, 2022 | December 30, 2027 | ||
Comment |
Net greenhouse gas (GHG) emissions | Value | 0.00 | 0.00 | 608584.00 |
Date | July 21, 2021 | December 31, 2027 | ||
Comment |
Average Generation Costs in the Maluku and Nusa Tenggara Regions | Value | 0.00 | 0.00 | 20.00 |
Date | July 21, 2021 | October 19, 2028 | ||
Comment |
People provided with new or improved electricity service | Value | 0.00 | 0.00 | 1924000.00 |
Date | July 14, 2021 | July 27, 2028 | ||
Comment |
People provided with new or improved electricity service - Female | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Implementation of a new integrated strategic IT solution including a new Enterprise Resource Plan (ERP) | Value | No | Yes | |
Date | July 27, 2022 | December 31, 2027 | ||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Share of female-headed households provided with new or improved electricity services | Value | 67.00 | 0.00 | 99.00 |
Date | July 28, 2021 | November 25, 2027 | ||
Comment |
Increased energy production of renewable energy | Value | 0 MWh per year | 786,298 MWh per year | |
Date | July 20, 2021 | November 30, 2028 | ||
Comment |
Grievances received and addressed through the project’s Grievance Redress Mechanism within the specified timeframe | Value | 0.00 | 0.00 | 90.00 |
Date | July 28, 2021 | November 30, 2026 | ||
Comment |
MWh of new battery storage equipment installed and operating in the Maluku and Nusa Tenggara Regions | Value | 0.00 | 0.00 | 0.32 |
Date | July 21, 2021 | July 23, 2026 | ||
Comment |
Reporting of new jobs created through the investments by type of job (i.e. permanent/temporary) | Value | No | Yes | |
Date | July 28, 2021 | November 30, 2027 | ||
Comment |
ERP hardware and software installed | Value | No | Yes | |
Date | July 27, 2022 | December 31, 2026 | ||
Comment |