Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 65.00 |
Borrower/Recipient | 30.88 |
P174379
Active
Nijat Valiyev , Muhammad Zulfiqar Ahmed
Ministry of Finance
October 16, 2020
(as of board presentation)
May 20, 2021
December 13, 2021
US$ 95.88 million
State Roads Agency
2021
US$ 65.00 million
N/A
February 7, 2024
March 31, 2026
Yes
BANK APPROVED
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 65.00 |
Borrower/Recipient | 30.88 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 65.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 65.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 95.88 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Apr 15, 2022 | IBRD-92430 | Int Charges | 17,919.07 |
Apr 15, 2022 | IBRD-92430 | Int Charges | 378.53 |
Apr 15, 2022 | IBRD-92430 | Int Charges | 12,156.76 |
Apr 15, 2022 | IBRD-92430 | Int Charges | 626.80 |
Apr 15, 2022 | IBRD-92430 | Int Charges | 420.20 |
Apr 15, 2022 | IBRD-92430 | Int Charges | 856.20 |
Apr 15, 2022 | IBRD-92430 | Int Charges | 1,040.13 |
Apr 15, 2022 | IBRD-92430 | Int Charges | 10,366.00 |
Apr 15, 2022 | IBRD-92430 | Int Charges | 5,452.16 |
May 20, 2021 | IBRD-92430 | Loan Commitment | 65,000,000.00 |
Apr 2, 2024 | IBRD-92430 | Loan Disb | 482,491.70 |
Jun 6, 2024 | IBRD-92430 | Loan Disb | 2,146,013.20 |
Apr 15, 2023 | IBRD-92430 | Int Charges | 102.76 |
Apr 15, 2023 | IBRD-92430 | Int Charges | 9,221.15 |
Apr 15, 2023 | IBRD-92430 | Int Charges | 66,477.04 |
Apr 15, 2023 | IBRD-92430 | Int Charges | 275,558.38 |
Apr 7, 2023 | IBRD-92430 | Loan Disb | 1,883,717.50 |
Mar 30, 2023 | IBRD-92430 | Loan Disb | 202,692.02 |
Apr 4, 2023 | IBRD-92430 | Loan Disb | 807,307.50 |
Nov 16, 2022 | IBRD-92430 | Loan Disb | 406,446.30 |
Nov 16, 2022 | IBRD-92430 | Loan Disb | 188,450.64 |
Oct 3, 2022 | IBRD-92430 | Loan Disb | 454,662.66 |
Oct 6, 2022 | IBRD-92430 | Loan Disb | 1,060,879.50 |
Jan 9, 2023 | IBRD-92430 | Loan Disb | 274,100.30 |
Oct 15, 2022 | IBRD-92430 | Int Charges | 77,244.64 |
Oct 15, 2022 | IBRD-92430 | Int Charges | 51,098.43 |
Nov 30, 2022 | IBRD-92430 | Loan Disb | 902,089.40 |
Nov 21, 2022 | IBRD-92430 | Loan Disb | 948,374.75 |
Jul 19, 2023 | IBRD-92430 | Loan Disb | 1,032,199.94 |
Jun 14, 2023 | IBRD-92430 | Loan Disb | 439,816.66 |
Aug 21, 2023 | IBRD-92430 | Loan Disb | 1,113,632.10 |
Jun 20, 2023 | IBRD-92430 | Loan Disb | 967,902.44 |
Sep 12, 2023 | IBRD-92430 | Loan Disb | 444,422.97 |
Jul 14, 2023 | IBRD-92430 | Loan Disb | 393,968.03 |
Jan 12, 2023 | IBRD-92430 | Loan Disb | 804,273.30 |
Oct 15, 2023 | IBRD-92430 | Int Charges | 186.25 |
Oct 15, 2023 | IBRD-92430 | Int Charges | 542,142.80 |
Dec 5, 2023 | IBRD-92430 | Loan Disb | 668,571.94 |
Oct 17, 2023 | IBRD-92430 | Loan Disb | 439,038.34 |
May 17, 2023 | IBRD-92430 | Loan Disb | 202,687.55 |
May 22, 2023 | IBRD-92430 | Loan Disb | 1,157,643.50 |
Jun 13, 2023 | IBRD-92430 | Loan Disb | 391,622.06 |
Sep 21, 2023 | IBRD-92430 | Loan Disb | 1,036,986.94 |
Aug 16, 2023 | IBRD-92430 | Loan Disb | 477,270.90 |
Apr 15, 2024 | IBRD-92430 | Int Charges | 27,143.36 |
Apr 15, 2024 | IBRD-92430 | Int Charges | 45,881.81 |
Apr 15, 2024 | IBRD-92430 | Int Charges | 888,243.50 |
Apr 15, 2024 | IBRD-92430 | Int Charges | 886.57 |
Nov 13, 2023 | IBRD-92430 | Loan Disb | 478,528.44 |
Jan 8, 2024 | IBRD-92430 | Loan Disb | 1,778,405.80 |
Nov 16, 2023 | IBRD-92430 | Loan Disb | 1,116,566.40 |
Oct 15, 2023 | IBRD-92430 | Int Charges | 10,357.65 |
Oct 15, 2023 | IBRD-92430 | Int Charges | 57,482.92 |
Dec 29, 2023 | IBRD-92430 | Loan Disb | 762,173.90 |
Oct 19, 2023 | IBRD-92430 | Loan Disb | 1,024,422.80 |
Jul 3, 2024 | IBRD-92430 | Loan Disb | 1,111,092.60 |
May 7, 2024 | IBRD-92430 | Loan Disb | 659,671.44 |
Jul 9, 2024 | IBRD-92430 | Loan Disb | 2,592,549.20 |
May 13, 2024 | IBRD-92430 | Loan Disb | 1,539,233.40 |
Apr 8, 2024 | IBRD-92430 | Loan Disb | 1,288,599.20 |
Mar 5, 2024 | IBRD-92430 | Loan Disb | 444,687.06 |
Mar 11, 2024 | IBRD-92430 | Loan Disb | 2,036,790.50 |
Jun 3, 2024 | IBRD-92430 | Loan Disb | 919,719.94 |
Jun 25, 2024 | IBRD-92430 | Loan Disb | 786,194.06 |
Jul 27, 2022 | IBRD-92430 | Loan Disb | 1,962,217.40 |
Dec 14, 2021 | IBRD-92430 | Fee Charges | 162,500.00 |
Aug 1, 2022 | IBRD-92430 | Loan Disb | 377,136.00 |
Aug 1, 2022 | IBRD-92430 | Loan Disb | 4,796,520.00 |
Jan 26, 2022 | IBRD-92430 | Loan Disb | 250,000.00 |
Jul 28, 2022 | IBRD-92430 | Loan Disb | 145,907.84 |
Name | Review | Date |
---|---|---|
Monitoring and Evaluation | Satisfactory | 2024-10-07 |
Progress towards achievement of PDO | Satisfactory | 2024-10-07 |
Procurement | Satisfactory | 2024-10-07 |
Project Management | Satisfactory | 2024-10-07 |
Financial Management | Satisfactory | 2024-10-07 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2024-10-07 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Beneficiaries with enhanced access to road transport as a result of the project | Value | see below | 0/0 | see below |
Date | June 15, 2021 | September 11, 2023 | June 15, 2026 | |
Comment |
Road safety improvements along M3 Salyan-Bilasuvar road expressed as the Project Safety Impact (PSI) using the Road Safety Screening and Appraisal Tool | Value | 1.00 | 1.00 | 0.86 |
Date | June 15, 2021 | September 11, 2023 | June 15, 2026 | |
Comment |
Climate resilience measures incorporated in the project roads | Value | see below | 0/0 | see below |
Date | June 15, 2021 | September 11, 2023 | June 15, 2026 | |
Comment |
Reduction in vehicle operation costs on project roads for medium trucks along the project road | Value | 0.00 | 0.00 | 11.00 |
Date | June 15, 2021 | September 11, 2023 | June 15, 2026 | |
Comment |
Direct Beneficiaries (number of daily road users) | Value | 0.00 | 0.00 | 1000.00 |
Date | ||||
Comment |
Project roads improved with additional climate resistance measures addressing flooding risk | Value | 0.00 | 0.00 | 4.00 |
Date | ||||
Comment |
Indirect Beneficiaries – The number of persons living within two km of the M3 project road. | Value | 0.00 | 0.00 | 15000.00 |
Date | ||||
Comment |
Upgraded bridges with increased flow capacity | Value | 0.00 | 0.00 | 1.00 |
Date | ||||
Comment |
Improvement in the delivery time of agricultural products from farm to market | Value | 80.00 | 90.00 | 70.00 |
Date | June 15, 2021 | September 11, 2023 | December 15, 2024 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Roads rehablitated | Value | 0.00 | 0.00 | 70.00 |
Date | June 15, 2021 | September 11, 2023 | June 15, 2026 | |
Comment |
Road user charges and axle load control options are identified and a decision is made by the SAAAR | Value | No | No | Yes |
Date | June 15, 2021 | September 11, 2023 | June 15, 2026 | |
Comment |
Number of community members provided with training and business advisory services to start their micro businesses | Value | 0.00 | 0.00 | 300.00 |
Date | June 15, 2021 | September 11, 2023 | June 15, 2026 | |
Comment |
Grievance Redress Mechanism complaints addressed and closed out | Value | 0.00 | 100.00 | 100.00 |
Date | June 15, 2021 | September 11, 2023 | June 15, 2026 | |
Comment |
Percentage of beneficiaries in target communities who believe that the project has established effective engagement processes | Value | 0.00 | 0.00 | 70.00 |
Date | June 15, 2021 | September 11, 2023 | June 15, 2026 | |
Comment |
Roads rehabilitated - non-rural | Value | 0.00 | 0.00 | 5.00 |
Date | ||||
Comment |
Out of which at least half are women | Value | 0.00 | 0.00 | 40.00 |
Date | ||||
Comment |
COVID-19 protocols developed, included in the Contractors’ Health and Safety plans, and implemented. | Value | No | Yes | Yes |
Date | June 15, 2021 | September 11, 2023 | June 15, 2026 | |
Comment |
Pre-opening Road Safety audit done and recommendations implemented | Value | No | No | Yes |
Date | June 15, 2021 | September 11, 2023 | June 15, 2026 | |
Comment |
Out of which at least 20% of women are heads of single headed female households | Value | 0.00 | 0.00 | 8.00 |
Date | ||||
Comment |
Jobs for local people engaged in construction of project roads (person-months cumulative) | Value | 0.00 | 1481.00 | 4000.00 |
Date | June 15, 2021 | September 11, 2023 | June 15, 2026 | |
Comment |
Number of community members supported with training, business advisory services and/or hard assets start their micro businesses. | Value | 0.00 | 0.00 | 100.00 |
Date | June 15, 2021 | September 11, 2023 | June 15, 2026 | |
Comment |
Out of which at least half are women | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Out of which at least 30% of women are heads of single headed female households | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Management/operation arrangements for logistics/market facilities are formulated and put in place | Value | 0.00 | 0.00 | 100.00 |
Date | June 15, 2021 | September 11, 2023 | June 15, 2026 | |
Comment |