Second Ethiopia Resilient Landscapes and Livelihoods Project

Abstract*

RLLP-II will support Ethiopia's efforts to scale up and enhance its Sustainable Landscape Management Program. The integrated package of activities will promote green infrastructure and resilient livelihoods and enhance institutional capacity and improve information for better decision-making.

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To improve climate resilience, land productivity and carbon storage, and increase access to diversified livelihood activities in selected rural watersheds.

Key Details

Project Details

  • P174385

  • Active

  • Million Alemayehu Gizaw , Nigel Hughes

  • Ministry of Finance

  • Ethiopia

  • August 16, 2020

  • (as of board presentation)

    March 18, 2021

  • March 31, 2021

  • US$ 178.24 million

  • N/A

  • December 19, 2023

  • April 30, 2026

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Green Climate Fund 165.24
Global P'ship for Sust. and Resilient Landscapes - PROGREEN 13.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 178.24
Total Project Cost** 178.24

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jul 29, 2022 TF-B8450 Loan Commitment 107,174,256.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Moderately Satisfactory 2025-03-25
Financial Management Moderately Satisfactory 2025-03-25
Project Management Satisfactory 2025-03-25
Monitoring and Evaluation Satisfactory 2025-03-25
Overall Implementation Progress (IP) Moderately Satisfactory 2025-03-25
Progress towards achievement of PDO Moderately Satisfactory 2025-03-25

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Land area under sustainable landscape management practicesValue0.000.00419000.00
    DateMay 3, 2021November 17, 2023April 30, 2026
    Comment
  • Net greenhouse gas emissions (tCO2eq/year)Value0.000.00-915000.00
    DateMay 3, 2021November 17, 2023April 30, 2026
    Comment
  • Households adopting diversified livelihood activities supported by the projectValue0.000.0041400.00
    DateMay 3, 2021November 17, 2023April 30, 2026
    Comment
  • Land area restored or reforested/afforestedValue0.000.009925.00
    Date
    Comment
  • Tonnes of carbon dioxide equivalent (t CO2 eq) to be reduced or avoidedValue0.000.000.00
    Date
    Comment
  • Female-headed households participating in diversified livelihood activities supported by the projectValue0.000.000.00
    Date
    Comment
  • Land area with productivity enhancing practices appliedValue0.000.0017000.00
    Date
    Comment
  • Project area showing an increase in NDVI correcting for climate effectsValue0.000.0050.00
    DateMay 3, 2021November 17, 2023April 30, 2026
    Comment
  • Project area showing an increase in LSWI correcting for climate effectsValue0.000.0050.00
    DateMay 3, 2021November 17, 2023April 30, 2026
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • IR 1. Share of target beneficiaries with rating ‘Satisfied’ or above on project interventions (aspects: livelihoods, environmental benefits, others)Value0.000.0065.00
    DateMay 3, 2021November 17, 2023April 30, 2026
    Comment
  • IR 7. Community Watershed Users' Cooperative Societies (CWUCSs) established and strengthenedValue0.000.00522.00
    DateMay 3, 2021November 17, 2023April 30, 2026
    Comment
  • IR 1a. Share of target women beneficiaries with rating ‘Satisfied’ or above on project interventionsValue0.000.000.00
    Date
    Comment
  • IR 7a. CWUCSs with Watershed Management and Use PlanValue0.000.00102.00
    Date
    Comment
  • IR 2. Targeted major watersheds with Multi-Year Development Plan 100% implementedValue0.000.0047.00
    DateMay 3, 2021November 17, 2023April 30, 2026
    Comment
  • IR 8. Woreda information centers being effectively used by project stakeholdersValue0.000.0040.00
    DateMay 3, 2021November 17, 2023April 30, 2026
    Comment
  • IR 14. number of direct beneficiariesValue0.000.00706133.00
    DateMay 3, 2021November 17, 2023April 30, 2026
    Comment
  • IR 2a. Targeted major watersheds with Multi-Year Development Plan approvedValue0.000.000.00
    Date
    Comment
  • IR 3. Area enclosure as a result of the projectValue0.000.0029000.00
    DateMay 3, 2021November 17, 2023April 30, 2026
    Comment
  • IR14a. Number of indirect beneficiariesValue0.000.001365122.00
    Date
    Comment
  • IR 4. Land users adopting sustainable land management practices as a result of the projectValue0.000.0099400.00
    DateMay 3, 2021November 17, 2023April 30, 2026
    Comment
  • IR 15. Number of males and females made aware of climate threats and related appropriate responsesValue0.000.00199094.00
    DateMay 3, 2021November 17, 2023April 30, 2026
    Comment
  • IR15a. Number of females made aware of climate threats and related appropriate responsesValue0.000.00109444.00
    DateMay 3, 2021November 17, 2023April 30, 2026
    Comment
  • IR 4a. Women land users adopting sustainable land management practices as a result of the projectValue0.000.000.00
    Date
    Comment
  • IR 16. Area under sustainable forest managementValue0.000.0030000.00
    DateMay 3, 2021November 17, 2023April 30, 2026
    Comment
  • IR 4b. Female headed households adopting sustainable land management practices as a result of the projectValue0.000.000.00
    Date
    Comment
  • IR 5. Functional Common-Interest Groups (CIGs) established or supported.Value0.000.00673.00
    DateMay 3, 2021November 17, 2023April 30, 2026
    Comment
  • IR 17. Key habitats protectedValue0.000.003.00
    DateMay 3, 2021November 17, 2023April 30, 2026
    Comment
  • IR 6. People participating in income-generating activities supported by the projectValue0.000.0074600.00
    DateJune 9, 2023November 17, 2023April 30, 2026
    Comment
  • IR 6a. Women participating in income generating activities supported by the projectValue0.000.000.00
    Date
    Comment