Skip to Main Navigation

Human Capital Recovery & Resilience Program

Abstract*

The Human Capital Recovery & Resilience Program aims to build, protect and utilize human capital in Bhutan.

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

Support building, protecting, and utilizing human capital in Bhutan

Key Details

Project Details

  • P174399

  • Active

  • Ashiq Aziz , Ingrid Bjerke

  • Ministry of Finance

  • Bhutan

  • November 15, 2021

  • (as of board presentation)

    February 3, 2022

  • March 30, 2022

  • US$ 43.01 million

  • Ministry of Education & Skills Development,Ministry of Health,Ministry of Industry, Commerce & Employment

  • South Asia

  • 2022

  • US$ 36.72 million

  • N/A

  • Not Applicable

  • June 30, 2029

  • Yes

  • BANK APPROVED

  • June 27, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 24.59
Borrower/Recipient 355.37
IDA Grant 12.13

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 36.72
IBRD + IDA Commitment 36.72
Lending Instrument
Grant Amount N/A
Total Project Cost** 43.01

Summary Status of World Bank Financing (US$ Millions) as of June 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of June 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Feb 3, 2022 IDA-70290 Loan Commitment 20,000,000.00
Dec 20, 2022 IDA-70290 Loan Disb 2,856,322.80
Aug 15, 2024 IDA-70290 Loan Disb 952,497.44
Jul 15, 2024 IDA-70290 Int Charges 37,339.27
Jul 15, 2024 IDA-70290 Int Charges 37,339.27
May 28, 2024 IDA-70290 Loan Disb 706,879.56
Jul 15, 2024 IDA-70290 Int Charges 601.01
Jul 15, 2024 IDA-70290 Int Charges 601.01
Jul 13, 2023 IDA-70290 Loan Disb 756,020.10
Aug 30, 2023 IDA-70290 Loan Disb 2,156,115.00
Jan 15, 2023 IDA-70290 Int Charges 6,829.32
Jan 15, 2023 IDA-70290 Int Charges 6,829.32
Jan 15, 2023 IDA-70290 Int Charges 2,154.41
Jan 15, 2023 IDA-70290 Int Charges 2,154.41
Jul 15, 2023 IDA-70290 Int Charges 1,733.60
Jul 15, 2023 IDA-70290 Int Charges 1,733.60
Jul 15, 2023 IDA-70290 Int Charges 17,790.57
Jul 15, 2023 IDA-70290 Int Charges 17,790.57
Jan 17, 2024 IDA-70290 Loan Disb 1,937,287.00
Dec 5, 2023 IDA-70290 Loan Disb 490,056.44
Jan 15, 2024 IDA-70290 Int Charges 26,416.37
Jan 15, 2024 IDA-70290 Int Charges 26,416.37
Jan 15, 2024 IDA-70290 Int Charges 201.10
May 20, 2022 IDA-70290 Loan Disb 1,874,656.00
Jan 15, 2024 IDA-70290 Int Charges 201.10

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Monitoring and Evaluation Moderately Satisfactory 2025-07-06
Overall Implementation Progress (IP) Moderately Satisfactory 2025-07-06
Progress towards achievement of PDO Moderately Satisfactory 2025-07-06

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • P.01. Children enrolled in ECCD services led by facilitator with basic certificateValue26.0037.6630.00
    DateNovember 16, 2021June 30, 2022June 30, 2026
    Comment
  • P.02. Schools accessing, and teachers utilizing, digital content in LMSValue0.0086.0080.00
    DateNovember 16, 2021June 26, 2023June 25, 2026
    Comment
  • P.05. Operational linkages established between MoICE and relevant agenciesValueNo linkagesNo linkagesLinkages established through data sharing and syst
    DateNovember 16, 2021May 30, 2022June 25, 2026
    Comment
  • P.03. Public and SEN schools with proper WASH facilitiesValue0.000.0060.00
    DateMarch 1, 2023March 1, 2023June 25, 2026
    Comment
  • urban areasValue0.0086.0080.00
    DateNovember 16, 2021June 26, 2023June 25, 2026
    Comment
  • rural areasValue0.0058.0040.00
    DateNovember 16, 2021June 26, 2023June 25, 2026
    Comment
  • P.04. Trainees employed within six months of completing SDPValue0.000.0020.00
    DateDecember 1, 2022May 30, 2022June 25, 2026
    Comment
  • female traineesValue0.000.0035.00
    DateDecember 1, 2022May 30, 2022June 25, 2026
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • I.17. Monitoring system for post-SDP tracking establishedValueNoYesYes
    DateNovember 16, 2021December 4, 2023January 25, 2025
    Comment
  • I.08. Teachers trained on digital pedagogyValue0.004000.005000.00
    DateNovember 16, 2021June 26, 2023June 25, 2026
    Comment
  • I.11. Female SDP graduatesValue0.000.0040.00
    DateDecember 1, 2022May 30, 2022June 25, 2026
    Comment
  • I.01. ECCD facilitators having completed or undergoing the Diploma in ECCDValue248.00248.00450.00
    DateNovember 16, 2021May 30, 2022June 25, 2026
    Comment
  • I.18. Graduates from incubation and acceleration programs linked to financing opportunitiesValue0.000.0030.00
    DateNovember 16, 2021May 30, 2022June 25, 2026
    Comment
  • I.12. SDP training delivered outside Thimphu, Paro and PhuentsholingValue0.000.0040.00
    DateDecember 1, 2022May 30, 2022June 25, 2026
    Comment
  • female teachersValue0.001760.000.00
    Date
    Comment
  • I.02. ECCD facilitators with basic certificate in ECCDValue600.00600.00810.00
    DateNovember 16, 2021May 30, 2022June 25, 2026
    Comment
  • I.19. Strategy on climate-responsiveness of SDP training developedValueNoNoYes
    DateNovember 16, 2021May 30, 2022June 25, 2026
    Comment
  • I.09. Schools with remote learning facilities in rural areasValue0.000.0020.00
    DateNovember 16, 2021May 30, 2022June 25, 2026
    Comment
  • I.13. Users requesting services through the BLMIS single intake windowValue0.000.0075.00
    DateNovember 16, 2021May 30, 2022June 25, 2026
    Comment
  • I.03. Focal monitors trainedValue200.00200.00650.00
    DateNovember 16, 2021May 30, 2022June 25, 2026
    Comment
  • I.20. Data sharing and referral system established to link mothers receiving ECCD services to employment promotion servicesValueNoNoYes
    DateNovember 17, 2021May 30, 2022June 25, 2026
    Comment
  • I.10. People using digitally enabled servicesValue0.004000.005000.00
    DateMarch 22, 2022March 21, 2024June 25, 2026
    Comment
  • female usersValue0.000.0050.00
    DateNovember 16, 2021May 30, 2022June 25, 2026
    Comment
  • I.04. ECCD facilitators receiving coaching visit by trained focal monitorValue24.0024.0040.00
    DateNovember 16, 2021May 30, 2022June 25, 2026
    Comment
  • users outside of Thimphu, Paro and PhuentsholingValue0.000.0030.00
    DateNovember 16, 2021May 30, 2022June 25, 2026
    Comment
  • I.05. Integrated ECCD centers (urban) and smaller ECCD centers (rural) establishedValue0.000.00180.00
    DateNovember 16, 2021May 30, 2022June 25, 2026
    Comment
  • I.06. ECCD services that meet basic quality standardsValue0.000.0030.00
    DateNovember 16, 2021May 30, 2022June 25, 2026
    Comment
  • I.14. Registered jobseekers satisfied with employment promotion servicesValue0.0091.5475.00
    DateNovember 16, 2021June 26, 2023June 25, 2026
    Comment
  • I.07. Mothers with improved economic empowerment outcomes in areas of ECCD expansionValue0.000.004.00
    DateNovember 17, 2021May 30, 2022June 25, 2026
    Comment
  • female jobseekersValue0.0093.1450.00
    DateNovember 16, 2021June 26, 2023June 25, 2026
    Comment
  • I.15. SDP program design revisedValueNoYesYes
    DateNovember 17, 2021December 4, 2023June 25, 2026
    Comment
  • I.16. New or better jobsValue0.000.00397.00
    DateDecember 30, 2022March 21, 2024June 25, 2026
    Comment