Madagascar National Water Project

Abstract*

Madagascar is a globally water rich country but its situation of inadequate access to water has been exacerbated by climate change and by low management of Water Resources which should be reinforced to ensure a long-term development of water sector. The proposed project which is an Investment Project Financing and a series of project will address the need for a long-term vision of the development of the water sector in general and will help Government...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The project development objective is to increase access to water services in the Greater Antananarivo area and select secondary towns and to improve the capacity of the water sector.

Key Details

Project Details

  • P174477

  • Active

  • Pierre Boulenger , Juan Casanova Anoll

  • Republic of Madagascar

  • Madagascar

  • May 3, 2021

  • (as of board presentation)

    May 25, 2022

  • September 8, 2022

  • US$ 220.00 million

  • JIRAMA,Ministère Eau, Assainissement et Hygiene (MEAH)

  • Eastern and Southern Africa

  • 2022

  • US$ 220.00 million

  • N/A

  • January 9, 2024

  • September 30, 2027

  • No

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 110.00
IDA Grant 110.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 220.00
IBRD + IDA Commitment 220.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 220.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Apr 23, 2024 IDA-E0400 Loan Disb 308,120.53
Jun 27, 2024 IDA-71210 Loan Disb 21,753.21
May 25, 2022 IDA-E0400 Loan Commitment 110,000,000.00
Jun 26, 2024 IDA-E0400 Loan Disb 39,475.66
Aug 21, 2024 IDA-E0400 Loan Disb 105,050.61
Aug 30, 2024 IDA-E0400 Loan Disb 73,375.65
Apr 29, 2024 IDA-E0400 Loan Disb 11,927.32
Apr 15, 2024 IDA-E0400 Loan Disb 62,461.16
May 9, 2024 IDA-E0400 Loan Disb 39,317.45
Feb 16, 2024 IDA-E0400 Loan Disb 1,070,994.00
Jun 4, 2024 IDA-E0400 Loan Disb 758,884.60
Jul 11, 2024 IDA-E0400 Loan Disb 4,915.38
Apr 8, 2024 IDA-E0400 Loan Disb 34,388.31
Jun 24, 2024 IDA-E0400 Loan Disb 4,000,000.00
Nov 17, 2022 IDA-71210 Loan Disb 2,000,000.00
Nov 17, 2022 IDA-71210 Loan Disb 10,000,000.00
Sep 8, 2022 IDA-71210 Loan Disb 600,937.50
Mar 6, 2023 IDA-71210 Int Charges 28,604.62
Mar 6, 2023 IDA-71210 Int Charges 28,604.62
Aug 15, 2023 IDA-71210 Loan Disb 107,284.06
Sep 1, 2023 IDA-71210 Int Charges 17.20
Sep 1, 2023 IDA-71210 Int Charges 17.20
Sep 6, 2023 IDA-71210 Int Charges 47,733.82
Sep 6, 2023 IDA-71210 Int Charges 47,733.82
Nov 28, 2023 IDA-71210 Loan Disb 45,619.55
Feb 1, 2024 IDA-71210 Loan Disb 151,391.40
Mar 4, 2024 IDA-71210 Int Charges 48,274.26
Mar 4, 2024 IDA-71210 Int Charges 48,274.26
Mar 1, 2024 IDA-71210 Int Charges 225.19
Mar 1, 2024 IDA-71210 Int Charges 225.19
May 25, 2022 IDA-71210 Loan Commitment 110,000,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Financial Management Moderately Satisfactory 2024-11-19
Overall Implementation Progress (IP) Moderately Satisfactory 2024-11-19
Monitoring and Evaluation Satisfactory 2024-11-19
Procurement Moderately Satisfactory 2024-11-19
Project Management Satisfactory 2024-11-19
Progress towards achievement of PDO Satisfactory 2024-11-19

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Increased number of people in project areas with access to water servicesValue0.000.00625000.00
    DateOctober 31, 2021October 26, 2023June 30, 2027
    Comment
  • Ratio of annual JIRAMA (water) O&M costs covered by revenues.Value0.550.551.00
    DateOctober 31, 2021October 26, 2023June 30, 2027
    Comment
  • A centralized WASH information system is established, updated and used to inform decision making.ValueNoNoYes
    DateOctober 31, 2021October 26, 2023June 30, 2027
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • 8- Number of schools and health centers that have achieved "Friend of WASH" certification following project intervention.Value0.000.00330.00
    DateOctober 31, 2021October 26, 2023June 30, 2027
    Comment
  • 8a- Number of schools that have achieved "Friend of WASH" certification following project intervention. (Number)Value0.000.00230.00
    DateOctober 31, 2021October 26, 2023June 30, 2027
    Comment
  • 8b- Number of health centers that have achieved "Friend of WASH" certification following project intervention. (Number)Value0.000.00100.00
    DateOctober 31, 2021October 26, 2023June 30, 2027
    Comment
  • 9 - Number of girls who attest they have missed fewer days of schoolValue0.000.002000.00
    DateOctober 31, 2021October 26, 2023June 30, 2027
    Comment
  • 10- Firewall between water and energy accounts at JIRAMAValueNoNoYes
    DateOctober 31, 2021October 26, 2023June 30, 2027
    Comment
  • 11- SCADA / GIS system set up for JIRAMAValueNoNoYes
    DateOctober 31, 2021October 26, 2023June 30, 2027
    Comment
  • 1- Additional water production capacity developed by the project.Value0.000.0040800.00
    DateOctober 31, 2021October 26, 2023June 30, 2027
    Comment
  • 4- Number of social connections financed by the project.Value0.000.0058500.00
    DateOctober 31, 2021October 26, 2023June 30, 2027
    Comment
  • 14- Number of strategic studies completedValue0.000.006.00
    DateOctober 31, 2021October 26, 2023June 30, 2027
    Comment
  • 12- Number of people in post-cyclone reconstruction project areas with access to secured water services (Number)Value0.000.00425000.00
    DateOctober 31, 2021October 26, 2023June 30, 2027
    Comment
  • 2- Non-revenue water percentageValue49.0049.0035.00
    DateOctober 31, 2021October 26, 2023June 30, 2027
    Comment
  • 5- Number of standpipes built or rehabilitated, thanks to the project.Value0.000.00550.00
    DateOctober 31, 2021October 26, 2023June 30, 2027
    Comment
  • 13- JIRAMA/MEAH have emergency response equipments safely stored and ready to be mobilized to ensure service continuity.ValueNoNoYes
    DateOctober 31, 2021October 26, 2023June 30, 2027
    Comment
  • 3- Number of meters or connections rehabilitatedValue0.000.0060000.00
    DateOctober 31, 2021October 26, 2023June 30, 2027
    Comment
  • 6- Customer complaints resolved by JIRAMA within the agreed timeframeValue25.0025.00100.00
    DateOctober 31, 2021October 26, 2023June 30, 2027
    Comment
  • 7- Additional number of students with access to improved school sanitation.Value0.000.00115000.00
    DateOctober 31, 2021October 26, 2023June 30, 2027
    Comment