Financier | Commitments |
---|---|
Borrower/Recipient | 30.00 |
IDA Grant | 730.00 |
P174485
Active
Stephen Muzira , Bezawit Fantta, Getachew Debela
Federal Democratic Republic of Ethiopia
Eastern and Southern Africa
January 8, 2021
(as of board presentation)
July 20, 2023
November 21, 2023
US$ 650.00 million
Ethiopian Roads Administration,Ministry of Transport and Logistics
2024
US$ 730.00 million
N/A
High
October 31, 2029
Yes
BANK APPROVED
January 19, 2024
Financier | Commitments |
---|---|
Borrower/Recipient | 30.00 |
IDA Grant | 730.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 730.00 |
IBRD + IDA Commitment | 730.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 650.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jul 20, 2023 | IDA-E2160 | Loan Commitment | 730,000,000.00 |
Mar 14, 2024 | IDA-E2160 | Loan Disb | 4,508,500.00 |
Jun 26, 2024 | IDA-E2160 | Loan Disb | 19,876,800.00 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2024-12-19 |
Financial Management | Satisfactory | 2024-12-19 |
Monitoring and Evaluation | Satisfactory | 2024-12-19 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2024-12-19 |
Project Management | Satisfactory | 2024-12-19 |
Procurement | Satisfactory | 2024-12-19 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Reduction in travel time along the Addis-Djibouti Southern route corridor | Value | 0.00 | 0.00 | 30.00 |
Date | May 24, 2021 | September 20, 2023 | June 30, 2027 | |
Comment |
Percentage of the Addis-Djibouti Southern route corridor (142km) that is rated in good condition (IRI < 3) | Value | 50.00 | 50.00 | 100.00 |
Date | May 24, 2021 | September 20, 2023 | June 30, 2027 | |
Comment |
Roads constructed | Value | 0.00 | 0.00 | 142.00 |
Date | May 24, 2021 | September 20, 2023 | June 30, 2027 | |
Comment |
Roads constructed - non-rural | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Roads rehablitated | Value | 0.00 | 0.00 | 50.00 |
Date | May 24, 2021 | September 20, 2023 | June 30, 2027 | |
Comment |
Roads rehabilitated - rural | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Truck processing and clearance times at Dewele border post (hours) | Value | 5.00 | 5.00 | 3.00 |
Date | October 24, 2023 | September 20, 2023 | June 14, 2027 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Percentage of the Addis-Djibouti southern corridor (142km) that has at least a 4-star IRAP rating | Value | 0.00 | 0.00 | 100.00 |
Date | May 24, 2021 | September 20, 2023 | June 30, 2027 | |
Comment |
Number of trade facilitation facilities, storage and roadside markets constructed/rehabilitated | Value | 0.00 | 0.00 | 20.00 |
Date | May 24, 2021 | September 20, 2023 | June 30, 2027 | |
Comment |
Percentage increase in roadside market provision and penetration in 5km buffer of Addis-Djibouti corridor sections that are intervened by the project | Value | 0.00 | 0.00 | 30.00 |
Date | May 24, 2021 | September 20, 2023 | June 30, 2027 | |
Comment |
Percentage of the Miesso Dire Dawa corridor (142km) that offers digital connectivity and ITS applications via optical fiber cable installations | Value | 0.00 | 0.00 | 100.00 |
Date | August 7, 2023 | September 20, 2023 | July 30, 2029 | |
Comment |
OSBP at Dewele constructed with necessary facilities, and equipped with IT infrastructure for full functionality | Value | No | No | Yes |
Date | June 5, 2023 | September 20, 2023 | June 30, 2027 | |
Comment |
Number of employees trained at beneficiary institutions under the trade facilitation and logistics enhancement | Value | 0.00 | 0.00 | 200.00 |
Date | May 24, 2021 | September 20, 2023 | June 30, 2027 | |
Comment |
Percentage of the Mieso-Dire Dawa section (142 km) that is rated as being climate-resilient | Value | 0.00 | 0.00 | 50.00 |
Date | August 7, 2023 | September 20, 2023 | March 20, 2029 | |
Comment |
Freight truck terminals constructed and operational with Communication and Information Exchange System also delivered and functional | Value | No | No | Yes |
Date | May 24, 2021 | September 20, 2023 | June 30, 2027 | |
Comment |
Percentage of business premises infrastructure developed under the project with reserved space for women | Value | 0.00 | 0.00 | 100.00 |
Date | May 24, 2021 | September 20, 2023 | June 30, 2027 | |
Comment |
Share of the target population expressing satisfaction with the provided local infrastructure facilities (roads, wells, markets) | Value | 0.00 | 0.00 | 80.00 |
Date | May 24, 2021 | September 20, 2023 | June 30, 2027 | |
Comment |
Share of trade facilitation facilities, storage and roadside markets constructed/rehabilitated that are leased or used by women in local markets (percentage) | Value | 0.00 | 0.00 | 40.00 |
Date | September 4, 2023 | September 20, 2023 | June 30, 2027 | |
Comment |