Financier | Commitments |
---|---|
IDA Grant | 295.00 |
P174495
Active
Abdou Toure
Republic of Chad
February 25, 2021
(as of board presentation)
March 24, 2022
August 24, 2022
US$ 395.00 million
Socitete Nationale de l'Electricite (SNE),Ministry of Hydrocarbons and Energy
2022
US$ 295.00 million
N/A
Substantial
June 30, 2027
Yes
BANK APPROVED
February 13, 2024
Financier | Commitments |
---|---|
IDA Grant | 295.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 295.00 |
IBRD + IDA Commitment | 295.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 395.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Dec 27, 2022 | IDA-D9850 | Loan Disb | 2,439,024.50 |
Mar 29, 2023 | IDA-D9850 | Loan Disb | 3,295,979.00 |
Jun 9, 2023 | IDA-D9850 | Loan Disb | 81,844.41 |
Nov 17, 2023 | IDA-D9850 | Loan Disb | 220,792.88 |
Jun 23, 2023 | IDA-D9850 | Loan Disb | 249,375.72 |
Jun 26, 2024 | IDA-D9850 | Loan Disb | 730,005.10 |
Aug 27, 2024 | IDA-D9850 | Loan Disb | 599,479.94 |
Mar 24, 2022 | IDA-D9850 | Loan Commitment | 295,000,000.00 |
Jun 20, 2024 | IDA-D9850 | Loan Disb | 507,600.00 |
Jun 27, 2024 | IDA-D9850 | Loan Disb | 4,235,716.00 |
Jun 21, 2024 | IDA-D9850 | Loan Disb | 1,549,395.60 |
Jun 24, 2024 | IDA-D9850 | Loan Disb | 2,990,235.80 |
Jun 10, 2024 | IDA-D9850 | Loan Disb | 1,288,048.60 |
Jun 24, 2024 | IDA-D9850 | Loan Disb | 2,421,900.00 |
Jun 21, 2024 | IDA-D9850 | Loan Disb | 210,281.44 |
Jun 21, 2024 | IDA-D9850 | Loan Disb | 451,235.22 |
Jun 21, 2024 | IDA-D9850 | Loan Disb | 512,766.90 |
Jun 21, 2024 | IDA-D9850 | Loan Disb | 1,881,462.60 |
Jun 21, 2024 | IDA-D9850 | Loan Disb | 4,721,992.50 |
Jun 25, 2024 | IDA-D9850 | Loan Disb | 1,683,728.50 |
Jun 25, 2024 | IDA-D9850 | Loan Disb | 879,900.25 |
Name | Review | Date |
---|---|---|
Project Management | Satisfactory | 2024-12-21 |
Progress towards achievement of PDO | Moderately Satisfactory | 2024-12-21 |
Procurement | Moderately Satisfactory | 2024-12-21 |
Financial Management | Moderately Satisfactory | 2024-12-21 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2024-12-21 |
Monitoring and Evaluation | Satisfactory | 2024-12-21 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
People provided with access to new or improved electricity service, out of which | Value | 0.00 | 0.00 | 1579400.00 |
Date | June 30, 2022 | December 18, 2023 | June 30, 2027 | |
Comment |
Women | Value | 0.00 | 0.00 | 789700.00 |
Date | June 30, 2022 | December 18, 2023 | June 30, 2027 | |
Comment |
Refugees | Value | 0.00 | 0.00 | 100000.00 |
Date | June 30, 2022 | December 18, 2023 | June 30, 2027 | |
Comment |
Host communities | Value | 0.00 | 0.00 | 192000.00 |
Date | June 30, 2022 | December 18, 2023 | June 30, 2027 | |
Comment |
People provided with access to clean cooking, out of which | Value | 0.00 | 0.00 | 132000.00 |
Date | June 30, 2022 | December 18, 2023 | June 30, 2027 | |
Comment |
Refugees | Value | 0.00 | 0.00 | 66000.00 |
Date | June 30, 2022 | December 18, 2023 | June 30, 2027 | |
Comment |
Host communities | Value | 0.00 | 0.00 | 66000.00 |
Date | June 30, 2022 | December 18, 2023 | June 30, 2027 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
In areas housing refugees and host communities | Value | 0.00 | 0.00 | 200.00 |
Date | June 30, 2022 | December 18, 2023 | June 30, 2027 | |
Comment |
Electricity connections (predominantly energized by solar PV and battery storage) in new cities and towns, out of which | Value | 0.00 | 0.00 | 18000.00 |
Date | June 30, 2022 | December 18, 2023 | June 30, 2027 | |
Comment |
Medical centers provided with solar PV electricity, out of which | Value | 0.00 | 0.00 | 40.00 |
Date | July 1, 2022 | December 18, 2023 | June 30, 2027 | |
Comment |
In cities housing host communities | Value | 0.00 | 0.00 | 5000.00 |
Date | June 30, 2022 | December 18, 2023 | June 30, 2027 | |
Comment |
In areas housing refugees and host communities | Value | 0.00 | 0.00 | 40.00 |
Date | June 30, 2022 | December 18, 2023 | June 30, 2027 | |
Comment |
Female-headed households electrified under subcomponents 1.1 - 1.3 | Value | 0.00 | 0.00 | 15.00 |
Date | June 30, 2022 | December 18, 2023 | June 30, 2027 | |
Comment |
Schools provided with solar PV electricity, out of which | Value | 0.00 | 0.00 | 50.00 |
Date | June 30, 2022 | December 18, 2023 | June 30, 2027 | |
Comment |
Women technicians employed in O&M operations under subcomponents 1.1-1.3 | Value | 0.00 | 0.00 | 20.00 |
Date | June 30, 2022 | December 18, 2023 | June 30, 2027 | |
Comment |
In areas housing refugees and host communities | Value | 0.00 | 0.00 | 50.00 |
Date | June 30, 2022 | December 18, 2023 | June 30, 2027 | |
Comment |
SHS delployed, out of which | Value | 0.00 | 0.00 | 250000.00 |
Date | July 1, 2022 | December 18, 2023 | June 30, 2027 | |
Comment |
In areas housing refugees and host communities | Value | 0.00 | 0.00 | 50000.00 |
Date | July 1, 2022 | December 18, 2023 | June 30, 2027 | |
Comment |
Female-headed households | Value | 0.00 | 0.00 | 30000.00 |
Date | ||||
Comment |
New electricity connections in N'Djamena | Value | 0.00 | 0.00 | 15000.00 |
Date | July 1, 2022 | December 18, 2023 | June 30, 2027 | |
Comment |
MSME provided with solar PV electricity, out of which | Value | 0.00 | 0.00 | 1200.00 |
Date | June 30, 2022 | December 18, 2023 | June 30, 2027 | |
Comment |
Community forest resources under integrated and participative management | Value | 0.00 | 0.00 | 100.00 |
Date | June 30, 2022 | December 18, 2023 | June 30, 2027 | |
Comment |
Project related grievances registered and addressed within the project's GRM timeframe | Value | 0.00 | 0.00 | 100.00 |
Date | June 30, 2022 | December 18, 2023 | June 30, 2027 | |
Comment |
New electricity connections (predominantly energized by solar PV and battery storage) in 12 secondary cities | Value | 0.00 | 0.00 | 15000.00 |
Date | June 30, 2022 | December 18, 2023 | June 30, 2027 | |
Comment |
ADERM developed an energy access program, including refugees and host communities | Value | No | No | Yes |
Date | June 30, 2022 | December 18, 2023 | June 30, 2027 | |
Comment |