Support to Panama PPP Program Development for Recovery Project

Abstract*

The proposed project consists of a US$7.5 million IPF focused on technical assistance to strengthen the technical and operating capacity of institutions involved in the management of the Public Private Partnership (PPP) agenda and these institutions' regulatory framework, following international best practices. This project will focus on building-up the capacity of the main institutions involved in the launch of the PPP program, notably the Ministry...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The objective of the Project is to strengthen institutional capacity for mobilizing private capital to finance and manage infrastructures and services in the Republic of Panama.

Key Details

Project Details

  • P174535

  • Active

  • Fabian Hinojosa Couleau , Abel Lopez Dodero, Carlos Murgui Maties

  • Republic of Panama

  • Panama

  • March 17, 2021

  • (as of board presentation)

    September 29, 2022

  • June 6, 2023

  • US$ 7.50 million

  • N/A

  • February 6, 2024

  • December 31, 2026

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 7.50

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 7.50
IDA Commitment N/A
IBRD + IDA Commitment 7.50
Lending Instrument
Grant Amount N/A
Total Project Cost** 7.50

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Sep 29, 2022 IBRD-94420 Loan Commitment 7,500,000.00
Apr 21, 2023 IBRD-94420 Fee Charges 18,750.00
Apr 15, 2024 IBRD-94420 Int Charges 9,385.94
Oct 15, 2023 IBRD-94420 Int Charges 12,174.69

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Moderately Unsatisfactory 2024-10-02
Overall Implementation Progress (IP) Moderately Unsatisfactory 2024-10-02
Project Management Moderately Unsatisfactory 2024-10-02
Financial Management Satisfactory 2024-10-02
Monitoring and Evaluation Satisfactory 2024-10-02
Progress towards achievement of PDO Moderately Unsatisfactory 2024-10-02

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • World Bank Benchmarking Infrastructure Development score for PPP preparationValue29.0029.0044.00
    DateJune 1, 2022September 13, 2023December 31, 2026
    Comment
  • PPP projects approved at the feasibility stage of preparation following standards defined in the new operational GuidelinesValue1.001.005.00
    DateJune 1, 2022September 13, 2023December 31, 2026
    Comment
  • PPP projects tenderedValue0.000.003.00
    DateJune 1, 2022September 13, 2023December 31, 2026
    Comment
  • Institutions with a specialized PPP group operationalized and strengthenedValue1.001.003.00
    DateJune 1, 2022September 13, 2023December 31, 2026
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Institutional reform proposals for improving planning capacity for infrastructure and service provision developed that are gender-responsive and consider climate changeValue0.000.001.00
    DateJune 1, 2022September 13, 2023December 31, 2026
    Comment
  • Infrastructure master plans, including strategies for developing and funding infrastructure and service provision that increases climate change resilience with private participation developedValue0.000.001.00
    DateJune 1, 2022September 13, 2023December 31, 2026
    Comment
  • Staff trained in planning instruments for infrastructure and service provisionValue0.000.0020.00
    DateJune 1, 2022September 13, 2023December 31, 2026
    Comment
  • Proposal for improved regulations that facilitate infrastructure development and service provision aligned with PPP law completed, including gender, climate change and citizen engagement aspectsValueNoNoYes
    DateJune 1, 2022September 13, 2023December 31, 2026
    Comment
  • Staff trained in preparing and executing PPP projects in line with the new operational GuidelinesValue0.000.0050.00
    DateJune 1, 2022September 13, 2023December 31, 2026
    Comment
  • Of which womenValue0.000.0025.00
    DateJune 1, 2022September 13, 2023December 31, 2026
    Comment
  • Share of women promoted or hired in PPP units of total hiring based on equal requirements for skills and competencesValue0.000.0040.00
    DateJune 1, 2022September 13, 2023December 31, 2026
    Comment
  • Share of beneficiaries consulted - disaggregated by gender and ethnicity – who report their feedback has been reflected in the Project’s activities and outputsValue0.000.0070.00
    DateJune 1, 2022September 13, 2023December 31, 2026
    Comment
  • Project preparation facility for preparing eligible PPP projects designedValueNoNoYes
    DateOctober 3, 2022September 13, 2023December 31, 2026
    Comment