Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 108.00 |
Borrower/Recipient | 27.00 |
P174593
Active
Greg Browder , Anup Karanth, Yukio Tanaka
India
December 10, 2020
(as of board presentation)
March 24, 2023
July 28, 2023
US$ 135.00 million
Government of Assam, Water Resources Department,Flood and River Erosion Management Agency of Assam,Assam State Disaster Management Authority
2023
US$ 108.00 million
N/A
January 9, 2024
July 31, 2027
Yes
BANK APPROVED
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 108.00 |
Borrower/Recipient | 27.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 108.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 108.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 135.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Mar 24, 2023 | IBRD-94870 | Loan Commitment | 108,000,000.00 |
Aug 1, 2024 | IBRD-94870 | Loan Disb | 34,917.55 |
Jul 15, 2024 | IBRD-94870 | Int Charges | 192.78 |
Jun 27, 2024 | IBRD-94870 | Loan Disb | 4,747,553.00 |
Jun 25, 2024 | IBRD-94870 | Loan Disb | 3,711,251.00 |
May 16, 2024 | IBRD-94870 | Loan Disb | 1,237,862.20 |
Mar 28, 2024 | IBRD-94870 | Loan Disb | 2,812,657.00 |
Jul 15, 2024 | IBRD-94870 | Int Charges | 242,080.62 |
Jul 15, 2024 | IBRD-94870 | Int Charges | 123,190.08 |
Jul 15, 2024 | IBRD-94870 | Int Charges | 5,355.20 |
Feb 21, 2024 | IBRD-94870 | Loan Disb | 419,242.66 |
Sep 5, 2023 | IBRD-94870 | Loan Disb | 1,379,676.50 |
Sep 5, 2023 | IBRD-94870 | Loan Disb | 151,071.03 |
Sep 18, 2023 | IBRD-94870 | Loan Disb | 3,324,343.80 |
Jul 28, 2023 | IBRD-94870 | Fee Charges | 270,000.00 |
Jul 28, 2023 | IBRD-94870 | Loan Disb | 270,000.00 |
Nov 17, 2023 | IBRD-94870 | Loan Disb | 477,379.60 |
Jan 15, 2024 | IBRD-94870 | Int Charges | 112,271.25 |
Jan 15, 2024 | IBRD-94870 | Int Charges | 110,539.46 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2024-11-07 |
Procurement | Satisfactory | 2024-11-07 |
Project Management | Satisfactory | 2024-11-07 |
Monitoring and Evaluation | Satisfactory | 2024-11-07 |
Overall Implementation Progress (IP) | Satisfactory | 2024-11-07 |
Financial Management | Moderately Satisfactory | 2024-11-07 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Adoption of Assam State Water Policy | Value | No state water policy in place | Initial discussions on state water policy have beg | Water Policy Approved by GoA |
Date | January 31, 2023 | June 1, 2023 | January 31, 2027 | |
Comment |
People with enhanced flood protection in Beki and Buridehing. | Value | 0.00 | 0.00 | 100000.00 |
Date | January 30, 2023 | June 1, 2023 | January 31, 2027 | |
Comment |
People receiving emergency alerts from State EOC | Value | 0.00 | 0.00 | 6000000.00 |
Date | January 30, 2023 | June 1, 2023 | January 31, 2027 | |
Comment |
People with improved flood forecasting information | Value | 0.00 | 0.00 | 4200000.00 |
Date | January 30, 2023 | June 1, 2023 | January 31, 2027 | |
Comment |
People with access to new or enhanced flood shelters | Value | 0.00 | 0.00 | 10000.00 |
Date | January 30, 2023 | June 1, 2023 | January 31, 2027 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Riverbank and flood protection embankments improved | Value | 0.00 | 0.00 | 40.00 |
Date | January 30, 2023 | June 1, 2023 | January 31, 2027 | |
Comment |
Completion of Assam Brahmaputra State of the Basin Report. | Value | None | Discussions have started. | State of the basin report completed. |
Date | January 30, 2023 | June 1, 2023 | January 31, 2027 | |
Comment |
Flood Shelters constructed. | Value | 0.00 | 0.00 | 25.00 |
Date | January 30, 2023 | June 1, 2023 | January 31, 2027 | |
Comment |
Upgrading the flood forecasting system in three basins | Value | None | Procurement started | Flood Forecasting System operational |
Date | January 30, 2023 | June 1, 2023 | January 31, 2027 | |
Comment |
Completion of Disaster Risk Financing Study | Value | None | Procurement Started | Study report completed |
Date | January 30, 2023 | June 1, 2023 | January 31, 2027 | |
Comment |
Upgraded State and District EOCs operational. | Value | None | Discussion Started | Upgraded state EOC and 10 upgraded District EOCs o |
Date | January 30, 2023 | June 1, 2023 | January 31, 2027 | |
Comment |
Preparation of IFRM Plans | Value | None | Procurement started. | Works procurement completed |
Date | January 30, 2023 | June 1, 2023 | January 31, 2027 | |
Comment |
Completion of Flash Flood Forecasting Study | Value | None | Discussions started. | Report submitted |
Date | January 30, 2023 | June 1, 2023 | January 31, 2027 | |
Comment |
CQRT teams receiving basic training | Value | 0.00 | 0.00 | 39.00 |
Date | January 30, 2023 | June 1, 2023 | January 31, 2027 | |
Comment |
Collection of hydrological baseline data | Value | None | Collection Underway | Baseline information utilized. |
Date | January 30, 2023 | June 1, 2023 | January 31, 2027 | |
Comment |
Grievances from PAPs redressed satisfactorily within timelines | Value | 0.00 | 0.00 | 85.00 |
Date | October 20, 2022 | June 1, 2023 | January 31, 2027 | |
Comment |
Climate risk-informed VDMPs developed in a participatory manner with local communities | Value | 0.00 | 0.00 | 40.00 |
Date | January 30, 2023 | June 1, 2023 | January 31, 2027 | |
Comment |
Flood Embankment Asset Management Program | Value | None | Not started | Report finalized |
Date | January 30, 2023 | June 1, 2023 | January 31, 2027 | |
Comment |
Flood shelter management committees have 40% female decision making members | Value | 0.00 | 0.00 | 75.00 |
Date | January 30, 2023 | June 1, 2023 | January 31, 2027 | |
Comment |
VLCDMC have 40% female decision making members | Value | 0.00 | 0.00 | 75.00 |
Date | January 17, 2023 | June 1, 2023 | January 31, 2027 | |
Comment |