Assam Integrated River Basin Management Program

Development Objective

To reduce the vulnerability of people to climate-related disasters and improve integrated water resources management in Assam.

Key Details

Project Details

  • P174593

  • Active

  • Greg Browder , Anup Karanth, Yukio Tanaka

  • India

  • India

  • December 10, 2020

  • (as of board presentation)

    March 24, 2023

  • July 28, 2023

  • US$ 135.00 million

  • Government of Assam, Water Resources Department,Flood and River Erosion Management Agency of Assam,Assam State Disaster Management Authority

  • South Asia

  • 2023

  • US$ 108.00 million

  • N/A

  • January 9, 2024

  • July 31, 2027

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 108.00
Borrower/Recipient 27.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 108.00
IDA Commitment N/A
IBRD + IDA Commitment 108.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 135.00

Summary Status of World Bank Financing (US$ Millions) as of January 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of January 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Mar 24, 2023 IBRD-94870 Loan Commitment 108,000,000.00
Aug 1, 2024 IBRD-94870 Loan Disb 34,917.55
Jul 15, 2024 IBRD-94870 Int Charges 192.78
Jun 27, 2024 IBRD-94870 Loan Disb 4,747,553.00
Jun 25, 2024 IBRD-94870 Loan Disb 3,711,251.00
May 16, 2024 IBRD-94870 Loan Disb 1,237,862.20
Mar 28, 2024 IBRD-94870 Loan Disb 2,812,657.00
Jul 15, 2024 IBRD-94870 Int Charges 242,080.62
Jul 15, 2024 IBRD-94870 Int Charges 123,190.08
Jul 15, 2024 IBRD-94870 Int Charges 5,355.20
Feb 21, 2024 IBRD-94870 Loan Disb 419,242.66
Sep 5, 2023 IBRD-94870 Loan Disb 1,379,676.50
Sep 5, 2023 IBRD-94870 Loan Disb 151,071.03
Sep 18, 2023 IBRD-94870 Loan Disb 3,324,343.80
Jul 28, 2023 IBRD-94870 Fee Charges 270,000.00
Jul 28, 2023 IBRD-94870 Loan Disb 270,000.00
Nov 17, 2023 IBRD-94870 Loan Disb 477,379.60
Jan 15, 2024 IBRD-94870 Int Charges 112,271.25
Jan 15, 2024 IBRD-94870 Int Charges 110,539.46

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Satisfactory 2024-11-07
Procurement Satisfactory 2024-11-07
Project Management Satisfactory 2024-11-07
Monitoring and Evaluation Satisfactory 2024-11-07
Overall Implementation Progress (IP) Satisfactory 2024-11-07
Financial Management Moderately Satisfactory 2024-11-07

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Adoption of Assam State Water PolicyValueNo state water policy in placeInitial discussions on state water policy have begWater Policy Approved by GoA
    DateJanuary 31, 2023June 1, 2023January 31, 2027
    Comment
  • People with enhanced flood protection in Beki and Buridehing.Value0.000.00100000.00
    DateJanuary 30, 2023June 1, 2023January 31, 2027
    Comment
  • People receiving emergency alerts from State EOCValue0.000.006000000.00
    DateJanuary 30, 2023June 1, 2023January 31, 2027
    Comment
  • People with improved flood forecasting informationValue0.000.004200000.00
    DateJanuary 30, 2023June 1, 2023January 31, 2027
    Comment
  • People with access to new or enhanced flood sheltersValue0.000.0010000.00
    DateJanuary 30, 2023June 1, 2023January 31, 2027
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Riverbank and flood protection embankments improvedValue0.000.0040.00
    DateJanuary 30, 2023June 1, 2023January 31, 2027
    Comment
  • Completion of Assam Brahmaputra State of the Basin Report.ValueNoneDiscussions have started.State of the basin report completed.
    DateJanuary 30, 2023June 1, 2023January 31, 2027
    Comment
  • Flood Shelters constructed.Value0.000.0025.00
    DateJanuary 30, 2023June 1, 2023January 31, 2027
    Comment
  • Upgrading the flood forecasting system in three basinsValueNoneProcurement startedFlood Forecasting System operational
    DateJanuary 30, 2023June 1, 2023January 31, 2027
    Comment
  • Completion of Disaster Risk Financing StudyValueNoneProcurement StartedStudy report completed
    DateJanuary 30, 2023June 1, 2023January 31, 2027
    Comment
  • Upgraded State and District EOCs operational.ValueNoneDiscussion StartedUpgraded state EOC and 10 upgraded District EOCs o
    DateJanuary 30, 2023June 1, 2023January 31, 2027
    Comment
  • Preparation of IFRM PlansValueNoneProcurement started.Works procurement completed
    DateJanuary 30, 2023June 1, 2023January 31, 2027
    Comment
  • Completion of Flash Flood Forecasting StudyValueNoneDiscussions started.Report submitted
    DateJanuary 30, 2023June 1, 2023January 31, 2027
    Comment
  • CQRT teams receiving basic trainingValue0.000.0039.00
    DateJanuary 30, 2023June 1, 2023January 31, 2027
    Comment
  • Collection of hydrological baseline dataValueNoneCollection UnderwayBaseline information utilized.
    DateJanuary 30, 2023June 1, 2023January 31, 2027
    Comment
  • Grievances from PAPs redressed satisfactorily within timelinesValue0.000.0085.00
    DateOctober 20, 2022June 1, 2023January 31, 2027
    Comment
  • Climate risk-informed VDMPs developed in a participatory manner with local communitiesValue0.000.0040.00
    DateJanuary 30, 2023June 1, 2023January 31, 2027
    Comment
  • Flood Embankment Asset Management ProgramValueNoneNot startedReport finalized
    DateJanuary 30, 2023June 1, 2023January 31, 2027
    Comment
  • Flood shelter management committees have 40% female decision making membersValue0.000.0075.00
    DateJanuary 30, 2023June 1, 2023January 31, 2027
    Comment
  • VLCDMC have 40% female decision making membersValue0.000.0075.00
    DateJanuary 17, 2023June 1, 2023January 31, 2027
    Comment