Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 55.00 |
P174595
Active
Jan Nora
Republic of Albania
April 22, 2021
(as of board presentation)
March 16, 2023
December 1, 2023
US$ 55.00 million
Albanian Road Authority
2023
US$ 55.00 million
N/A
December 20, 2023
July 31, 2029
Yes
BANK APPROVED
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 55.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 55.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 55.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 55.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Mar 15, 2024 | IBRD-94790 | Int Charges | 73,610.35 |
Mar 16, 2023 | IBRD-94790 | Loan Commitment | 55,000,000.00 |
Dec 1, 2023 | IBRD-94790 | Fee Charges | 140,571.30 |
Dec 1, 2023 | IBRD-94790 | Loan Disb | 140,571.30 |
Jan 4, 2024 | IBRD-94790 | Loan Disb | 1,833,218.20 |
Mar 15, 2024 | IBRD-94790 | Int Charges | 18,710.18 |
Name | Review | Date |
---|---|---|
Project Management | Moderately Satisfactory | 2025-03-13 |
Progress towards achievement of PDO | Satisfactory | 2025-03-13 |
Financial Management | Satisfactory | 2025-03-13 |
Monitoring and Evaluation | Satisfactory | 2025-03-13 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2025-03-13 |
Procurement | Moderately Satisfactory | 2025-03-13 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Bridges rehabilitated, reconstructed, or constructed following international guidelines on resilience to climate and natural disasters | Value | 0.00 | 0.00 | 30.00 |
Date | March 31, 2023 | December 20, 2023 | March 31, 2031 | |
Comment |
RAMS/BMS and remote sensing data used for a bridge management and maintenance medium-term budget planning | Value | RAMS/BMS and remote sensing data not in use | RAMS/BMS and remote sensing data not in use | RAMS/BMS and remote sensing data used for a trial |
Date | March 31, 2023 | December 20, 2023 | March 30, 2029 | |
Comment |
People with enhanced access to transportation services | Value | 0.00 | 0.00 | 350000.00 |
Date | March 31, 2023 | December 20, 2023 | March 31, 2031 | |
Comment |
Direct daily road users benefited by rehabilitated, reconstructed, or constructed bridges | Value | 0.00 | 0.00 | 200000.00 |
Date | March 31, 2023 | December 20, 2023 | March 31, 2031 | |
Comment |
Pedestrians benefited by safer designs from the rehabilitated or reconstructed bridges | Value | 0.00 | 0.00 | 150000.00 |
Date | March 31, 2023 | December 20, 2023 | March 31, 2031 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Bridge designs completed following international guidelines on resilience to climate and natural hazards | Value | 0.00 | 2.00 | 15.00 |
Date | March 31, 2023 | December 14, 2023 | March 30, 2029 | |
Comment |
Bridges for which designs have been audited for climate resilience before construction | Value | 0.00 | 13.33 | 100.00 |
Date | March 31, 2023 | December 14, 2023 | March 30, 2029 | |
Comment |
The ARA Staff trained for the procurement and implementation of bridge operations | Value | 0.00 | 0.00 | 30.00 |
Date | March 31, 2023 | December 14, 2023 | March 30, 2029 | |
Comment |
Female last-year university students and graduates recruited for a 6-month paid internship program at the MoIE in the areas of engineering/similar male-dominated fields | Value | 0.00 | 0.00 | 15.00 |
Date | March 31, 2023 | December 20, 2023 | March 30, 2029 | |
Comment |
Grievance Redress Mechanism complaints addressed and closed out | Value | 0.00 | 0.00 | 100.00 |
Date | December 20, 2023 | May 31, 2023 | March 30, 2029 | |
Comment |
Service Level Requirements designed | Value | No | No | Yes |
Date | March 31, 2023 | December 20, 2023 | March 30, 2029 | |
Comment |
Bridge designs which have been publicly consulted and surveyed | Value | 0.00 | 0.00 | 100.00 |
Date | March 31, 2023 | May 31, 2023 | March 30, 2029 | |
Comment |
Bridges for which designs have been audited for Road Safety, ensuring road safety considerations for vulnerable users | Value | 0.00 | 0.00 | 100.00 |
Date | March 31, 2023 | December 14, 2023 | March 30, 2029 | |
Comment |
Road condition data inputted into the RAMS/BMS in a reliable and systematic manner. | Value | 0.00 | 0.00 | 1000.00 |
Date | March 31, 2023 | December 14, 2023 | March 30, 2029 | |
Comment |
Females employed permanently in the ARA in roles that are male dominated, e.g. engineers, technical planners in the Road Asset Management System, etc. | Value | 0.00 | 0.00 | 3.00 |
Date | March 31, 2023 | December 20, 2023 | March 30, 2029 | |
Comment |
Bridges for which citizen comments and requests have been incorporated in their designs | Value | 0.00 | 0.00 | 50.00 |
Date | March 31, 2023 | May 31, 2023 | March 30, 2029 | |
Comment |
Data collected for establishing a Disaster Loss Database | Value | No | No | Yes |
Date | March 31, 2023 | December 14, 2023 | March 30, 2029 | |
Comment |