Financier | Commitments |
---|---|
Borrowing Agency | 8.90 |
International Bank for Reconstruction and Development | 80.00 |
P174946
Active
Silvana Kostenbaum
Republic of Argentina
December 16, 2020
(as of board presentation)
March 30, 2021
August 11, 2021
US$ 88.90 million
Secretariat of Innovation, Science and Technology, Chief of Cabinet of Ministers Office
2021
US$ 80.00 million
N/A
Moderate
February 28, 2027
Yes
BANK APPROVED
February 9, 2024
Financier | Commitments |
---|---|
Borrowing Agency | 8.90 |
International Bank for Reconstruction and Development | 80.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 80.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 80.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 88.90 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jul 15, 2024 | IBRD-92240 | Int Charges | 40,488.21 |
Jul 15, 2024 | IBRD-92240 | Int Charges | 108,009.96 |
Jul 15, 2024 | IBRD-92240 | Int Charges | 1,686,500.40 |
Jul 15, 2024 | IBRD-92240 | Int Charges | 3,675.79 |
Mar 30, 2021 | IBRD-92240 | Loan Commitment | 80,000,000.00 |
Sep 29, 2021 | IBRD-92240 | Loan Disb | 3,000,000.00 |
Aug 11, 2021 | IBRD-92240 | Loan Disb | 200,000.00 |
Aug 11, 2021 | IBRD-92240 | Fee Charges | 200,000.00 |
Jan 15, 2022 | IBRD-92240 | Int Charges | 15,598.10 |
Jan 15, 2022 | IBRD-92240 | Int Charges | 58,975.87 |
Jan 15, 2022 | IBRD-92240 | Int Charges | 15,598.10 |
Jul 15, 2022 | IBRD-92240 | Int Charges | 273.97 |
Jul 15, 2022 | IBRD-92240 | Int Charges | 1,481.59 |
Jul 15, 2022 | IBRD-92240 | Int Charges | 39,105.41 |
Jul 15, 2022 | IBRD-92240 | Int Charges | 54,865.82 |
Jul 15, 2022 | IBRD-92240 | Int Charges | 38,831.44 |
Dec 6, 2021 | IBRD-92240 | Loan Disb | 1,000,000.00 |
Oct 7, 2022 | IBRD-92240 | Loan Disb | 2,300,000.00 |
Nov 4, 2022 | IBRD-92240 | Loan Disb | 2,639,800.00 |
Jun 15, 2023 | IBRD-92240 | Loan Disb | 9,966,107.00 |
Jan 15, 2023 | IBRD-92240 | Int Charges | 4,765.41 |
Jan 15, 2023 | IBRD-92240 | Int Charges | 92,651.60 |
Jan 15, 2023 | IBRD-92240 | Int Charges | 162,945.30 |
Mar 2, 2023 | IBRD-92240 | Loan Disb | 1,539,972.00 |
Jul 15, 2023 | IBRD-92240 | Int Charges | 11,789.11 |
Jul 15, 2023 | IBRD-92240 | Int Charges | 84,104.99 |
Jul 15, 2023 | IBRD-92240 | Int Charges | 319,180.38 |
Jun 8, 2023 | IBRD-92240 | Loan Disb | 1,067,220.00 |
Oct 6, 2023 | IBRD-92240 | Loan Disb | 10,500,000.00 |
Nov 27, 2023 | IBRD-92240 | Loan Disb | 10,960,886.00 |
Mar 4, 2024 | IBRD-92240 | Loan Disb | 5,826,014.50 |
Jan 15, 2024 | IBRD-92240 | Int Charges | 62,982.40 |
Jan 15, 2024 | IBRD-92240 | Int Charges | 62,505.47 |
Jan 15, 2024 | IBRD-92240 | Int Charges | 933,796.40 |
Jan 15, 2024 | IBRD-92240 | Int Charges | 2,318.30 |
Jan 15, 2024 | IBRD-92240 | Int Charges | 60,187.17 |
Jul 15, 2024 | IBRD-92240 | Int Charges | 36,812.42 |
Name | Review | Date |
---|---|---|
Monitoring and Evaluation | Satisfactory | 2025-01-29 |
Progress towards achievement of PDO | Satisfactory | 2025-01-29 |
Financial Management | Satisfactory | 2025-01-29 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2025-01-29 |
Procurement | Moderately Satisfactory | 2025-01-29 |
Project Management | Satisfactory | 2025-01-29 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Users registered on the argentina.gob.ar portal with a Citizen Digital profile | Value | 6000000.00 | 20380412.00 | 12000000.00 |
Date | July 1, 2021 | February 7, 2024 | July 1, 2025 | |
Comment |
Digital service centers at the subnational level | Value | 570.00 | 667.00 | 770.00 |
Date | July 1, 2021 | February 7, 2024 | July 1, 2025 | |
Comment |
Government digital procedures with reduced resolution times | Value | 0.00 | 314.00 | 200.00 |
Date | July 1, 2021 | February 7, 2024 | July 1, 2025 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Visitors to digital service centers | Value | 0.00 | 7956999.00 | 3000000.00 |
Date | July 1, 2021 | February 7, 2024 | June 30, 2025 | |
Comment |
Diagnostics or evaluations of the digital government initiatives | Value | 0.00 | 0.00 | 3.00 |
Date | July 1, 2021 | February 7, 2024 | July 1, 2025 | |
Comment |
Active users of the data analytics dashboards for digital platforms and services | Value | 0.00 | 857.00 | 1000.00 |
Date | July 1, 2021 | February 7, 2024 | July 1, 2025 | |
Comment |
Women accessing the Mi Argentina platform | Value | 45.00 | 52.24 | 50.00 |
Date | July 1, 2021 | February 7, 2024 | July 1, 2025 | |
Comment |
Women participating in digital service centers activities | Value | 33.00 | 52.09 | 50.00 |
Date | July 1, 2021 | February 7, 2024 | July 1, 2025 | |
Comment |
New racks for increased physical capacity in ARSAT's National Data Center | Value | 0.00 | 3.00 | 3.00 |
Date | July 1, 2021 | February 7, 2024 | July 1, 2025 | |
Comment |
Women using the remote access platform (TAD - trámites a distancia) | Value | 35.00 | 42.28 | 50.00 |
Date | July 1, 2021 | February 7, 2024 | July 1, 2025 | |
Comment |
Visitors to digital service centers located in vulnerable or remote areas. | Value | 0.00 | 4074812.00 | 500000.00 |
Date | July 1, 2021 | February 7, 2024 | July 30, 2025 | |
Comment |
Institutional units in the National Public Administration using ARSAT’s platform | Value | 27.00 | 43.00 | 50.00 |
Date | June 1, 2021 | February 7, 2024 | July 1, 2025 | |
Comment |
Administrative processes completed by women in the remote access platform (TAD) | Value | 24.50 | 38.16 | 40.00 |
Date | March 1, 2021 | February 7, 2024 | July 31, 2025 | |
Comment |
Citizen-oriented activities in digital service centers. | Value | 0.00 | 203.00 | 50.00 |
Date | July 1, 2021 | February 7, 2024 | July 1, 2025 | |
Comment |
Subnational governments using ARSAT's cloud computing services | Value | 55.00 | 373.00 | 320.00 |
Date | July 1, 2021 | February 7, 2024 | July 1, 2025 | |
Comment |
Services that are specifically targeted to, and consider, women’s specific needs. | Value | 0.00 | 9.00 | 10.00 |
Date | July 1, 2021 | February 7, 2024 | July 1, 2025 | |
Comment |
Knowledge sharing and learning activities of subnational governments conducted | Value | 0.00 | 0.00 | 4.00 |
Date | July 1, 2021 | February 7, 2024 | July 1, 2025 | |
Comment |
Provinces using e-filing digital modules | Value | 8.00 | 9.00 | 14.00 |
Date | July 1, 2021 | February 7, 2024 | July 1, 2025 | |
Comment |
Digital Country Assessment Platform implemented | Value | No | Yes | Yes |
Date | July 1, 2021 | February 7, 2024 | July 1, 2025 | |
Comment |
Subnational governments that have implemented and are operating a digital government system | Value | 0.00 | 19.00 | 20.00 |
Date | July 1, 2021 | February 7, 2024 | July 1, 2025 | |
Comment |
Digital services reenginered using evidence from the Digital Government Observatory | Value | 0.00 | 0.00 | 50.00 |
Date | July 1, 2021 | February 7, 2024 | July 1, 2025 | |
Comment |
Persons trained in gender-focused activities, both implemented as part of the Open Government National Action Plan and in digital service centers | Value | 0.00 | 423544.00 | 500000.00 |
Date | July 1, 2021 | February 7, 2024 | July 1, 2025 | |
Comment |
Portal with open procurement and contracting data following the Open Contracting Data Standard (OCDS) and the Open Contracting for Infrastructure Data Standard (OC4IDS) | Value | No | No | Yes |
Date | July 1, 2021 | February 7, 2024 | July 1, 2025 | |
Comment |
Users who evaluate Mi Argentina portal’s services satisfactorily | Value | 43.00 | 60.00 | 70.00 |
Date | July 1, 2021 | February 7, 2024 | July 1, 2025 | |
Comment |
Innovation Pilot implemented in sector | Value | 0.00 | 2.00 | 3.00 |
Date | July 1, 2021 | February 7, 2024 | July 1, 2025 | |
Comment |
Users who evaluate TAD government services satisfactorily | Value | 40.00 | 40.00 | 70.00 |
Date | July 1, 2021 | February 7, 2024 | July 1, 2025 | |
Comment |