Fiji Social Protection COVID-19 Response and System Development Project

Abstract*

The development objective of Social Protection COVID-19 Response and System Development Project for Fiji is to mitigate the impact of the Coronavirus (COVID-19) crisis on the income of the unemployed and underemployed, and to increase efficiency and adaptability of the social protection system. This project has two components. 1) The first component, Cash transfers to the unemployed and underemployed affected by Coronavirus (COVID-19), aims to support...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

to mitigate the impact of the COVID-19 crisis on the income of the unemployed and underemployed, and to increase efficiency and adaptability of the social protection system of the Recipient.

Key Details

Project Details

  • P175206

  • Active

  • Yuliya Smolyar

  • Republic of Fiji

  • Fiji

  • December 3, 2020

  • (as of board presentation)

    February 9, 2021

  • February 19, 2021

  • US$ 50.00 million

  • Ministry of Economy

  • East Asia and Pacific

  • 2021

  • US$ 50.00 million

  • N/A

  • Moderate

  • July 31, 2025

  • Yes

  • BANK APPROVED

  • April 28, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 50.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 50.00
IBRD + IDA Commitment 50.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 50.00

Summary Status of World Bank Financing (US$ Millions) as of April 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of April 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jun 6, 2022 IDA-68280 Loan Disb 43,557.00
Feb 18, 2022 IDA-68280 Loan Disb 9,516.10
Feb 15, 2022 IDA-68280 Int Charges 21,951.61
Feb 15, 2022 IDA-68280 Int Charges 21,951.61
Feb 15, 2022 IDA-68280 Int Charges 163,518.83
Feb 15, 2022 IDA-68280 Int Charges 163,518.83
Jun 17, 2022 IDA-71060 Loan Disb 37,483,912.00
Apr 26, 2023 IDA-68280 Loan Disb 29,038.01
May 10, 2023 IDA-71060 Loan Disb 138,760.06
Mar 7, 2023 IDA-71060 Loan Disb 15,555.13
May 20, 2022 IDA-71060 Loan Commitment 48,900,000.00
Feb 9, 2021 IDA-68280 Loan Commitment 50,000,000.00
Mar 28, 2024 IDA-71060 Loan Disb 175,039.81
Jun 21, 2024 IDA-71060 Loan Disb 150,156.48
Mar 11, 2024 IDA-71060 Loan Disb 136,905.20
Mar 20, 2024 IDA-68280 Loan Disb 79,132.19
Aug 15, 2024 IDA-68280 Int Charges 2,155.12
Aug 15, 2024 IDA-68280 Int Charges 2,155.12
Apr 12, 2024 IDA-71060 Loan Disb 68,111.19
Aug 15, 2024 IDA-71060 Int Charges 1,664.62
Aug 15, 2024 IDA-71060 Int Charges 1,664.62
Jul 25, 2024 IDA-71060 Loan Disb 118,934.47
Aug 15, 2024 IDA-68280 Int Charges 157,002.30
Aug 15, 2024 IDA-68280 Int Charges 157,002.30
Aug 15, 2024 IDA-71060 Int Charges 144,487.03
Aug 15, 2024 IDA-71060 Int Charges 144,487.03
Oct 6, 2023 IDA-71060 Loan Disb 98,797.58
Oct 13, 2023 IDA-68280 Loan Disb 175,588.19
Feb 13, 2024 IDA-71060 Loan Disb 440,100.00
Feb 7, 2024 IDA-68280 Loan Disb 26,377.40
Feb 27, 2024 IDA-71060 Loan Disb 149,348.98
Aug 30, 2024 IDA-71060 Loan Disb 109,336.15
Jun 28, 2024 IDA-68280 Loan Disb 34,377.31
Jun 17, 2024 IDA-68280 Loan Disb 52,754.80
May 29, 2024 IDA-68280 Loan Disb 79,132.20
Apr 17, 2024 IDA-71060 Loan Disb 95,126.29
Feb 15, 2024 IDA-71060 Int Charges 141,513.20
Feb 15, 2024 IDA-71060 Int Charges 141,513.20
Feb 15, 2024 IDA-71060 Int Charges 243.50
Feb 15, 2024 IDA-71060 Int Charges 243.50
Feb 15, 2024 IDA-68280 Int Charges 234.76
Feb 15, 2024 IDA-68280 Int Charges 234.76
Feb 15, 2024 IDA-68280 Int Charges 158,735.62
Feb 15, 2024 IDA-68280 Int Charges 158,735.62
Apr 30, 2024 IDA-71060 Loan Disb 82,949.10
Oct 13, 2022 IDA-68280 Loan Disb 29,037.99
Jan 24, 2023 IDA-68280 Loan Disb 64,744.26
Nov 15, 2022 IDA-68280 Loan Disb 29,038.00
Dec 20, 2022 IDA-68280 Loan Disb 29,038.00
Sep 6, 2022 IDA-68280 Loan Disb 29,038.00
Nov 29, 2022 IDA-71060 Loan Disb 152,625.98
Feb 15, 2023 IDA-68280 Int Charges 1,337.94
Feb 15, 2023 IDA-68280 Int Charges 1,337.94
Feb 15, 2023 IDA-71060 Int Charges 45,365.65
Feb 15, 2023 IDA-71060 Int Charges 45,365.65
Feb 15, 2023 IDA-71060 Int Charges 140,120.16
Feb 15, 2023 IDA-71060 Int Charges 140,120.16
Feb 15, 2023 IDA-68280 Int Charges 155,859.38
Feb 15, 2023 IDA-68280 Int Charges 155,859.38
Mar 14, 2023 IDA-68280 Loan Disb 221,549.98
Feb 24, 2023 IDA-71060 Loan Disb 61,906.60
Sep 22, 2023 IDA-71060 Loan Disb 133,756.45
Sep 22, 2023 IDA-68280 Loan Disb 179,420.34
Jun 15, 2023 IDA-68280 Loan Disb 30,778.50
Aug 24, 2023 IDA-68280 Loan Disb 21,778.50
Aug 15, 2023 IDA-68280 Int Charges 874.97
Aug 15, 2023 IDA-68280 Int Charges 874.97
Aug 15, 2023 IDA-68280 Int Charges 158,785.86
Aug 15, 2023 IDA-68280 Int Charges 158,785.86
Aug 15, 2023 IDA-71060 Int Charges 912.26
Aug 15, 2023 IDA-71060 Int Charges 912.26
Aug 15, 2023 IDA-71060 Int Charges 141,384.72
Aug 15, 2023 IDA-71060 Int Charges 141,384.72
Nov 30, 2023 IDA-71060 Loan Disb 127,483.70
Jan 10, 2024 IDA-71060 Loan Disb 152,195.20
Jan 18, 2024 IDA-71060 Loan Disb 46,651.60
Dec 15, 2023 IDA-71060 Loan Disb 83,798.20
Aug 11, 2021 IDA-68280 Loan Disb 1,264,074.40
Oct 8, 2021 IDA-68280 Loan Disb 84,464.15
Oct 7, 2021 IDA-68280 Loan Disb 565,010.06
Aug 15, 2021 IDA-68280 Int Charges 5,688.13
Aug 15, 2021 IDA-68280 Int Charges 5,688.13
Jul 20, 2021 IDA-68280 Loan Disb 10,947,069.00
Jun 25, 2021 IDA-68280 Loan Disb 7,544,354.00
Jun 1, 2021 IDA-68280 Loan Disb 3,571,122.20
Aug 2, 2021 IDA-68280 Loan Disb 8,198,630.00
Jul 21, 2021 IDA-68280 Loan Disb 11,763,197.00
Jun 30, 2021 IDA-68280 Loan Disb 666,995.70
May 5, 2021 IDA-68280 Loan Disb 97,939.99
Dec 28, 2022 IDA-68280 Loan Disb 41,412.79
Jul 28, 2022 IDA-68280 Loan Disb 29,037.99
Aug 15, 2022 IDA-68280 Int Charges 538.27
Aug 15, 2022 IDA-68280 Int Charges 538.27
Aug 15, 2022 IDA-68280 Int Charges 155,432.75
Aug 15, 2022 IDA-68280 Int Charges 155,432.75
Aug 12, 2022 IDA-68280 Loan Disb 29,038.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Moderately Unsatisfactory 2024-12-18
Project Management Moderately Satisfactory 2024-12-18
Progress towards achievement of PDO Moderately Satisfactory 2024-12-18
Financial Management Moderately Satisfactory 2024-12-18
Monitoring and Evaluation Moderately Satisfactory 2024-12-18
Overall Implementation Progress (IP) Moderately Satisfactory 2024-12-18

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of unemployed in formal and informal sectors because of COVID-19 crisis who received cash transfers directly paid by the Government of Fiji under the AFValue0.00340671.00340671.00
    DateAugust 1, 2021June 17, 2022July 31, 2022
    Comment
  • Share of female beneficiaries in formal and informal sectorsValue0.0050.000.00
    Date
    Comment
  • Number of beneficiaries in formal sectorValue0.00188630.000.00
    Date
    Comment
  • Share of female beneficiaries in formal sectorValue0.0044.000.00
    Date
    Comment
  • Number of beneficiaries in informal sectorValue0.00152041.000.00
    Date
    Comment
  • Share of female beneficiaries in informal sectorValue0.0059.000.00
    Date
    Comment
  • Number of beneficiaries who received employment opportunities under the Jobs for Nature 2.0Value0.005280.0010000.00
    DateAugust 1, 2021December 8, 2023July 31, 2025
    Comment
  • Share of femaleValue0.000.0035.00
    Date
    Comment
  • Number of unemployed and underemployed who received cash transfers with the government top-ups from FNPFValue0.0075226.0060000.00
    DateMarch 27, 2020August 31, 2021July 31, 2021
    Comment
  • Adaptive Social Protection Strategy and action plans developed and adoptedValueNoNoYes
    DateOctober 30, 2020December 8, 2023July 31, 2024
    Comment
  • Interoperability among social protection databases or information systems have been establishedValueNoNoYes
    DateOctober 30, 2020December 8, 2023July 31, 2024
    Comment
  • Number of female unemployed and underemployed who received cash transfers from FNPFValue0.0031908.0024000.00
    DateMarch 27, 2020August 31, 2021July 31, 2021
    Comment
  • Percentage of beneficiaries in the area affected by TC HaroldValue0.0095.0090.00
    DateMarch 27, 2020May 21, 2021July 31, 2021
    Comment
  • Gap in General Account balances between female and male beneficiariesValue(FJD 32)FJD 0
    Date
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Share of unemployed and underemployed whose application were processed and approved in five business daysValue0.0083.0090.00
    DateMarch 26, 2020July 31, 2021July 31, 2021
    Comment
  • A feasibility study and an implementation roadmap for the unemployment benefits scheme developedValueNoNoYes
    DateNovember 30, 2020December 8, 2023July 31, 2024
    Comment
  • Share of beneficiaries who received employment opportunities under the Jobs for Nature 2.0 are social welfare beneficiariesValue0.0010.5110.00
    DateAugust 1, 2021December 8, 2023July 31, 2025
    Comment
  • Specific operational manual for the Stronger Together Program adopted by the Ministry of EconomyValueNoNoYes
    DateNovember 30, 2020December 8, 2023July 31, 2024
    Comment
  • Share of femaleValue0.000.004.50
    Date
    Comment
  • Number of new and existing SP programs linked to disaster and economic vulnerability dataValue0.000.005.00
    DateNovember 30, 2020December 8, 2023July 31, 2024
    Comment
  • Number of degraded sites restored and rehabilitated using nature-based solutionsValue0.000.00150.00
    DateAugust 1, 2021March 31, 2023July 31, 2025
    Comment
  • Management information system (MIS) to support improved delivery of employment support programs developed at NEC and piloted in selective centersValueInformation system with minimum functions which cosame as baselineMIS has been developed and in operation with defin
    DateNovember 30, 2020December 8, 2023July 31, 2024
    Comment
  • Grievances registered related to wage payment to the beneficiaries of Jobs for Nature 2.0 resolved in a timely mannerValue0.0085.0080.00
    DateAugust 1, 2021December 8, 2023July 31, 2025
    Comment
  • Share of registered jobseekers reporting satisfaction with the employment services received from NECValue0.000.0080.00
    DateNovember 30, 2020December 8, 2023July 31, 2024
    Comment
  • Approval of the design of a GRM for gender-based violenceValueNoNoYes
    DateNovember 30, 2020December 8, 2023July 31, 2024
    Comment
  • Increased share of awareness of GBV services availableValueBaseline to be establishedBaseline to be establishedBaseline+20%
    DateNovember 30, 2020December 8, 2023July 31, 2024
    Comment
  • MaleValuebaseline to be establishedbaseline to be establishedBaseline+20%
    DateNovember 30, 2020December 8, 2023July 31, 2024
    Comment
  • FemaleValueBaseline to be establishedbaseline to be establishedBaseline+20%
    DateNovember 30, 2020December 8, 2023July 31, 2024
    Comment
  • Number of stakeholders who received training throughout the cycle of Jobs for Nature 2.0Value0.000.001440.00
    DateAugust 1, 2021December 8, 2023July 31, 2025
    Comment
  • Share of femaleValue0.000.0050.00
    Date
    Comment
  • Adoption of the standard operating procedure (SOP) developed for an economic inclusion frameworkValueNoNoYes
    DateAugust 1, 2021December 8, 2023July 31, 2025