Financier | Commitments |
---|---|
IDA Credit | 90.00 |
IDA Grant | 240.00 |
P175235
Active
Oceane Keou , Thierry Davy, Francis Ovanda Mbele
Republic of Congo,Central African Republic
Central Africa
March 3, 2022
(as of board presentation)
June 29, 2023
March 18, 2024
US$ 300.00 million
Ministry of the River Economy and Waterways (ROC),Ministry of Transport and Civil Aviation (CAR),Ministry of Equipment and Public Works (CAR),Ministry of Digital Economy, Posts, and Telecommunications (CAR),Ministry of Planning, Statistics and Regional Integration (ROC)
2023
US$ 330.00 million
N/A
High
October 31, 2029
Yes
BANK APPROVED
April 5, 2024
Financier | Commitments |
---|---|
IDA Credit | 90.00 |
IDA Grant | 240.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 330.00 |
IBRD + IDA Commitment | 330.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 300.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jun 29, 2023 | IDA-73820 | Loan Commitment | 90,000,000.00 |
Jun 12, 2024 | IDA-73820 | Loan Disb | 5,420,313.00 |
Apr 23, 2024 | IDA-E2150 | Loan Disb | 9,767,215.00 |
Jun 29, 2023 | IDA-E2150 | Loan Commitment | 240,000,000.00 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2024-12-31 |
Procurement | Satisfactory | 2024-12-31 |
Project Management | Moderately Satisfactory | 2024-12-31 |
Financial Management | Moderately Satisfactory | 2024-12-31 |
Monitoring and Evaluation | Satisfactory | 2024-12-31 |
Overall Implementation Progress (IP) | Satisfactory | 2024-12-31 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Reduced travel time along the Brazzaville-Bangui waterway and the Bossembélé-Bossangoa road sections | Value | 0.00 | 0.00 | 30.00 |
Date | March 15, 2023 | March 29, 2024 | October 31, 2029 | |
Comment |
People provided with all-weather access along the Brazzaville-Bangui waterway and Bossembélé-Bossangoa road sections | Value | 0.00 | 0.00 | 2922000.00 |
Date | March 15, 2023 | March 29, 2024 | October 31, 2029 | |
Comment |
Share of targeted local traders in CAR and ROC demonstrating improved trade and business competency | Value | 0.00 | 0.00 | 75.00 |
Date | March 15, 2023 | March 29, 2024 | October 31, 2029 | |
Comment |
Reduced travel time along the Bossembélé-Bossangoa road section | Value | 260.00 | 0.00 | 0.00 |
Date | ||||
Comment |
People provided with all-weather access along the Bossembélé-Bossangoa road section | Value | 0.00 | 0.00 | 1341000.00 |
Date | March 15, 2023 | March 29, 2024 | October 31, 2029 | |
Comment |
of which are female traders | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Reduced travel time along the Brazzaville-Bangui waterway section | Value | 14.00 | 0.00 | 0.00 |
Date | ||||
Comment |
People provided with all-weather access along the Brazzaville-Bangui waterway section | Value | 0.00 | 0.00 | 1581000.00 |
Date | March 15, 2023 | March 29, 2024 | October 31, 2029 | |
Comment |
Share of targeted local traders in CAR demonstrating improved trade and business competency | Value | 0.00 | 0.00 | 75.00 |
Date | March 15, 2023 | March 29, 2024 | October 31, 2029 | |
Comment |
Increased throughput at selected ports along the Brazzaville-Bangui waterway section | Value | 0.00 | 0.00 | 10.00 |
Date | March 15, 2023 | March 29, 2024 | October 31, 2029 | |
Comment |
Share of targeted local traders in ROC demonstrating improved trade and business competency | Value | 0.00 | 0.00 | 75.00 |
Date | March 15, 2023 | March 29, 2024 | October 31, 2029 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Villages provided with new or rehabilitated socio-economic infrastructure | Value | 0.00 | 0.00 | 10.00 |
Date | March 15, 2023 | September 20, 2023 | October 31, 2029 | |
Comment |
Digital trade data collection system established in CAR and ROC | Value | No | No | Yes |
Date | March 15, 2023 | September 20, 2023 | October 31, 2029 | |
Comment |
Grievances resolved related to the delivery of project activities within the timeframe stipulated in the PIM | Value | 0.00 | 0.00 | 100.00 |
Date | March 15, 2023 | September 20, 2023 | October 31, 2029 | |
Comment |
GIE-SCEVN annual campaigns for maintenance and replacement of river markings and buoys completed | Value | 0.00 | 0.00 | 5.00 |
Date | March 15, 2023 | September 20, 2023 | October 31, 2029 | |
Comment |
Training person-days completed (certification/training programs on navigation) | Value | 0.00 | 0.00 | 12000.00 |
Date | March 15, 2023 | September 20, 2023 | October 31, 2029 | |
Comment |
Ports and quays rehabilitated or upgraded with green, climate-resilient and universal access standards | Value | 0.00 | 0.00 | 18.00 |
Date | March 15, 2023 | September 20, 2023 | October 31, 2029 | |
Comment |
Community feedback on community-level infrastructure works | Value | 0.00 | 0.00 | 80.00 |
Date | March 15, 2023 | September 20, 2023 | October 31, 2029 | |
Comment |
Bossembele-Bossangoa road section upgraded to 2-lane climate-resilient paved road standard | Value | 0.00 | 0.00 | 150.00 |
Date | March 15, 2023 | September 20, 2023 | October 31, 2029 | |
Comment |
Share of project-funded storage facilities leased to or used by women in local markets | Value | 0.00 | 0.00 | 60.00 |
Date | March 15, 2023 | September 20, 2023 | October 31, 2029 | |
Comment |
of which are female beneficiaries | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
All-weather connection for people in Bossangoa along project feeder roads | Value | No | No | Yes |
Date | March 15, 2023 | September 20, 2023 | October 31, 2029 | |
Comment |
Congo Basin Information System (SIBCO), including early warning system, upgraded | Value | No | No | Yes |
Date | March 15, 2023 | September 20, 2023 | October 31, 2029 | |
Comment |
Green and Resilient Ports and Waterways Development Strategies in ROC and CAR endorsed | Value | No | No | Yes |
Date | March 15, 2023 | September 20, 2023 | October 31, 2029 | |
Comment |
Green and Resilient Ports and Waterways Development Strategy in CAR endorsed | Value | No | No | Yes |
Date | March 15, 2023 | September 20, 2023 | October 31, 2029 | |
Comment |
Green and Resilient Ports and Waterways Development Strategy in ROC endorsed | Value | No | No | Yes |
Date | March 15, 2023 | September 20, 2023 | October 31, 2029 | |
Comment |
Financially sustainable asset management strategies for the whole corridor endorsed | Value | No | No | Yes |
Date | March 15, 2023 | September 20, 2023 | October 31, 2029 | |
Comment |
Financially sustainable asset management strategy for road corridors in CAR updated and endorsed | Value | No | No | Yes |
Date | March 15, 2023 | September 20, 2023 | October 31, 2029 | |
Comment |
Financially sustainable asset management strategy for the ports in CAR developed and endorsed | Value | No | No | Yes |
Date | March 15, 2023 | September 20, 2023 | October 31, 2029 | |
Comment |
Financially sustainable asset management strategy for the ports in ROC developed and endorsed | Value | No | No | Yes |
Date | March 15, 2023 | September 20, 2023 | October 31, 2029 | |
Comment |
Financially sustainable strategy for waterways maintenance along the Brazzaville-Bangui waterway corridor developed and endorsed | Value | No | No | Yes |
Date | March 15, 2023 | September 20, 2023 | October 31, 2029 | |
Comment |
Zinga feasibility study completed | Value | No | No | Yes |
Date | March 15, 2023 | September 20, 2023 | October 31, 2029 | |
Comment |
Road and navigation safety awareness campaigns implemented | Value | 0.00 | 0.00 | 8.00 |
Date | March 15, 2023 | September 20, 2023 | October 31, 2029 | |
Comment |
Road safety awareness campaigns implemented | Value | 0.00 | 0.00 | 4.00 |
Date | March 15, 2023 | September 20, 2023 | October 31, 2029 | |
Comment |
Navigation safety awareness campaigns implemented | Value | 0.00 | 0.00 | 4.00 |
Date | March 15, 2023 | September 20, 2023 | October 31, 2029 | |
Comment |