Tajikistan Strengthening Water and Irrigation Management Project

Abstract*

Tajikistan Strengthening Water and Irrigation Management Project will build on the experience of the successful Zarafshon Irrigation Rehabilitation and Management Improvement Project and the preceding World Bank-financed projects in the irrigation sector. The project will upscale support for institutional strengthening and infrastructure modernization. The main project investments will be directed to the lower sub-basin of the Vakhsh river, with a...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The project development objective is to: (i) strengthen capacity for water resources planning and irrigation management in Tajikistan and (ii) improve performance of selected irrigation schemes in the Vakhsh and Zarafshon river basins.

Key Details

Project Details

  • P175356

  • Active

  • Aleix Serrat Capdevila , Farzona Mukhitdinova

  • Ministry of Finance (MoF)

  • Tajikistan

  • April 15, 2021

  • (as of board presentation)

    June 23, 2022

  • February 16, 2023

  • US$ 47.34 million

  • Agency for Land Reclamation and Irrigation (ALRI),FVWRMP PMU under the ALRI,Ministry of Energy and Water Resources (MEWR)

  • Europe and Central Asia

  • 2022

  • US$ 47.34 million

  • N/A

  • Substantial

  • June 25, 2027

  • Yes

  • BANK APPROVED

  • March 15, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
European Commission Development Fund - TF 17.34
IDA Grant 30.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 30.00
IBRD + IDA Commitment 30.00
Lending Instrument
Grant Amount 17.34
Total Project Cost** 47.34

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jul 29, 2024 IDA-E0790 Loan Disb 685,061.10
Mar 13, 2024 IDA-E0790 Loan Disb 149,999.98
Dec 13, 2023 IDA-E0790 Loan Disb 1,014,346.06
Jun 23, 2022 IDA-E0790 Loan Commitment 30,000,000.00
May 12, 2023 IDA-E0790 Loan Disb 1,500,000.00
Apr 17, 2024 IDA-E0790 Loan Disb 872,179.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Moderately Satisfactory 2025-08-11
Procurement Moderately Satisfactory 2025-08-11
Project Management Moderately Satisfactory 2025-08-11
Financial Management Moderately Satisfactory 2025-08-11
Monitoring and Evaluation Moderately Satisfactory 2025-08-11
Overall Implementation Progress (IP) Moderately Satisfactory 2025-08-11

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • National and basin-level water planning institutions established and resourcedValueNoNoYes
    DateSeptember 1, 2022December 15, 2023December 24, 2026
    Comment
  • Area with improved water delivery in targeted large schemesValue0.000.0025000.00
    DateSeptember 1, 2022December 15, 2023December 24, 2026
    Comment
  • ALRI and WUAs strengthened to enable effective management of targeted large schemesValueNoNoYes
    DateSeptember 1, 2022December 15, 2023December 24, 2026
    Comment
  • Energy intensity of water delivered in targeted large schemes (reduction)Value0.000.0015.00
    DateSeptember 1, 2022December 15, 2023December 24, 2026
    Comment
  • Value of production in targeted large schemesValue0.000.0010.00
    DateSeptember 1, 2022December 15, 2023December 24, 2026
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Water resources planning staff trainedValue0.000.0050.00
    DateSeptember 2, 2022December 15, 2023June 26, 2026
    Comment
  • Pump stations in target schemes modernizedValue0.000.0010.00
    DateSeptember 1, 2022December 15, 2023December 24, 2026
    Comment
  • Percentage of grievances redressedValue0.000.0090.00
    DateSeptember 1, 2022December 15, 2023December 24, 2026
    Comment
  • WIS Unit established and WIS populated and improvedValueNoNoYes
    DateSeptember 2, 2022December 15, 2023June 27, 2025
    Comment
  • Selected major hydraulic structures in target schemes repairedValue0.000.0020.00
    DateSeptember 1, 2022December 15, 2023December 24, 2026
    Comment
  • RBO offices rehabilitated and equippedValueNoNoYes
    DateSeptember 2, 2022December 15, 2023October 31, 2024
    Comment
  • Other critical major water infrastructure repairedValueNoNoYes
    DateSeptember 23, 2022December 15, 2023October 31, 2025
    Comment
  • Representation of women in WRMValue0.000.0020.00
    DateSeptember 1, 2022December 15, 2023December 24, 2026
    Comment
  • Community consultations and beneficiary surveys conductedValueNoNoYes
    DateSeptember 23, 2022December 15, 2023December 11, 2026
    Comment
  • New ALRI units established for scheme-based managementValueNoNoYes
    DateSeptember 1, 2022December 15, 2023November 29, 2024
    Comment
  • Selected small/medium schemes rehabilitated for enhanced performanceValue0.000.0015.00
    DateSeptember 1, 2022April 12, 2023December 24, 2026
    Comment
  • Irrigation energy audit and tariff review completeValueNoNoYes
    DateSeptember 1, 2022December 15, 2023June 28, 2024
    Comment
  • Selected vulnerable schemes resilient to climate extremesValue0.000.0015.00
    DateSeptember 1, 2022December 15, 2023December 24, 2026
    Comment
  • IMIS modules developedValueNoNoYes
    DateSeptember 1, 2022December 15, 2023June 28, 2024
    Comment
  • WUA Support Unit established and trainedValueNoNoYes
    DateSeptember 23, 2022December 15, 2023June 28, 2024
    Comment