Adaptive Safety Nets and Economic Inclusion Project

Development Objective

The Project Development Objective (PDO) is to: (i) expand the coverage and shock-responsive capacity of the safety nets system for poor households, and (ii) increase access to income-generation and entrepreneurship support opportunities for youth in urban areas.

Key Details

Project Details

  • P175363

  • Active

  • Hugo Brousset Chaman , Ioana Alexandra Botea

  • The Republic of Cameroon

  • Cameroon

  • June 24, 2021

  • (as of board presentation)

    March 9, 2022

  • November 21, 2022

  • US$ 160.00 million

  • Ministry of Economy, Planning, and Regional Development (MINEPAT)

  • Western and Central Africa

  • 2022

  • US$ 160.00 million

  • N/A

  • February 2, 2024

  • March 30, 2028

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 160.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 160.00
IBRD + IDA Commitment 160.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 160.00

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Mar 21, 2024 IDA-70480 Loan Disb 1,950,303.40
Mar 9, 2022 IDA-70480 Loan Commitment 160,000,000.00
Sep 5, 2023 IDA-70480 Loan Disb 739,236.06
Jul 31, 2023 IDA-70480 Loan Disb 818,261.00
Nov 1, 2023 IDA-70480 Loan Disb 255,068.56
Oct 15, 2023 IDA-70480 Int Charges 42,807.20
Oct 15, 2023 IDA-70480 Int Charges 42,807.20
Oct 15, 2023 IDA-70480 Int Charges 16,788.04
Oct 15, 2023 IDA-70480 Int Charges 6,747.71
Oct 15, 2023 IDA-70480 Int Charges 6,747.71
Oct 15, 2023 IDA-70480 Int Charges 2,789.05
Apr 15, 2024 IDA-70480 Int Charges 20,116.54
May 29, 2024 IDA-70480 Loan Disb 8,876,324.00
Jun 25, 2024 IDA-70480 Loan Disb 4,420,168.00
May 29, 2024 IDA-70480 Loan Disb 444,814.25
Jan 25, 2024 IDA-70480 Loan Disb 848,097.75
Apr 15, 2024 IDA-70480 Int Charges 52,962.31
Apr 15, 2024 IDA-70480 Int Charges 52,962.31
Apr 15, 2024 IDA-70480 Int Charges 917.55
Apr 19, 2024 IDA-70480 Loan Disb 516,232.25
Aug 27, 2024 IDA-70480 Loan Disb 2,005,656.10
Aug 5, 2024 IDA-70480 Loan Disb 511,552.16
Feb 29, 2024 IDA-70480 Loan Disb 322,404.90
Dec 27, 2023 IDA-70480 Loan Disb 363,781.66
Nov 21, 2023 IDA-70480 Loan Disb 263,275.22
Oct 5, 2023 IDA-70480 Loan Disb 179,655.40
Mar 7, 2023 IDA-70480 Loan Disb 2,928,641.20
Mar 7, 2023 IDA-70480 Loan Disb 3,742,152.80
Mar 28, 2023 IDA-70480 Loan Disb 4,461,389.50
Jun 25, 2024 IDA-70480 Loan Disb 351,902.20

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Monitoring and Evaluation Satisfactory 2024-12-20
Procurement Moderately Satisfactory 2024-12-20
Project Management Satisfactory 2024-12-20
Financial Management Moderately Unsatisfactory 2024-12-20
Progress towards achievement of PDO Satisfactory 2024-12-20
Overall Implementation Progress (IP) Moderately Satisfactory 2024-12-20

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Households benefitting from safety nets servicesValue0.000.00150500.00
    DateMarch 31, 2022November 30, 2023March 31, 2028
    Comment
  • Urban youth benefitting from IGA support servicesValue0.000.0065000.00
    DateMarch 31, 2022November 30, 2023March 31, 2028
    Comment
  • of which recipient is a female household memberValue0.000.00103900.00
    DateMarch 31, 2022November 30, 2023March 31, 2028
    Comment
  • of which womenValue0.000.0032500.00
    DateMarch 31, 2022November 30, 2023March 31, 2028
    Comment
  • of which recipient is a displaced household memberValue0.000.0030100.00
    DateMarch 31, 2022November 30, 2023March 31, 2028
    Comment
  • of which displacedValue0.000.0023000.00
    DateMarch 31, 2022November 30, 2023March 31, 2028
    Comment
  • Social registry developed and implementedValueNoNoYes
    DateMarch 31, 2022November 30, 2023March 31, 2028
    Comment
  • Urban youth benefitting from entrepreneurship support servicesValue0.000.002000.00
    DateMarch 31, 2022November 30, 2023June 30, 2027
    Comment
  • Digital payments system developed and implementedValueNoNoYes
    DateMarch 31, 2022November 30, 2023March 31, 2028
    Comment
  • of which womenValue0.000.00600.00
    DateMarch 31, 2022November 30, 2023March 31, 2028
    Comment
  • of which displacedValue0.000.00400.00
    DateMarch 31, 2022November 30, 2023March 31, 2028
    Comment
  • Jobs created by the firms receiving support from the projectValue0.000.006000.00
    DateMarch 31, 2022November 30, 2023March 30, 2028
    Comment
  • of which womenValue0.000.001800.00
    DateMarch 31, 2022November 30, 2023March 31, 2028
    Comment
  • of which displacedValue0.000.001200.00
    DateMarch 31, 2022November 30, 2023March 31, 2028
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Public works beneficiariesValue0.000.0055000.00
    DateMarch 31, 2022November 30, 2023March 31, 2028
    Comment
  • Households benefitting from regular cash transfersValue0.000.0053000.00
    DateMarch 31, 2022November 30, 2023March 31, 2028
    Comment
  • Beneficiaries who received IGA supportValue0.000.0065000.00
    DateMarch 31, 2022November 30, 2023March 31, 2028
    Comment
  • Communal social centers equipped to manage the National Social RegistryValue10.0010.0060.00
    DateMarch 31, 2022November 30, 2023March 31, 2028
    Comment
  • Households benefitting from emergency cash transfersValue0.000.0042500.00
    DateMarch 31, 2022November 30, 2023March 31, 2028
    Comment
  • Beneficiaries receiving payments digitallyValue0.000.0080.00
    DateMarch 30, 2022November 30, 2023March 31, 2028
    Comment
  • Youths (18 to 35) receiving a trainingValue0.000.003000.00
    DateMarch 31, 2022November 30, 2023March 31, 2028
    Comment
  • Of which recipient is a womanValue0.000.0034000.00
    DateMarch 31, 2022November 30, 2023March 31, 2028
    Comment
  • of which FemalesValue0.000.00900.00
    DateMarch 31, 2022November 30, 2023March 31, 2028
    Comment
  • National Social Registry MIS operationalValueNoNoYes
    DateJune 30, 2022November 30, 2023June 30, 2027
    Comment
  • MINAS staff trained to develop, implement and maintain the National Social RegistryValue0.000.00255.00
    DateMarch 31, 2022November 30, 2023March 31, 2028
    Comment
  • of which FemaleValue0.000.0027500.00
    DateMarch 31, 2022November 30, 2023March 31, 2028
    Comment
  • of which recipient is a FemaleValue0.000.0042400.00
    DateJune 30, 2022November 30, 2023June 30, 2027
    Comment
  • Grievances registered and addressed within the project’s GRM timeframeValue0.000.0097.00
    DateMarch 31, 2022November 30, 2023March 31, 2028
    Comment
  • Of which FemaleValue0.000.0032500.00
    DateMarch 31, 2022November 30, 2023March 31, 2028
    Comment
  • of which DisplacedValue0.000.00600.00
    DateMarch 31, 2022November 30, 2023March 31, 2028
    Comment
  • of which DisplacedValue0.000.0011000.00
    DateMarch 31, 2022November 30, 2023March 31, 2028
    Comment
  • Beneficiary satisfied with the programValue0.000.0080.00
    DateMarch 31, 2022November 30, 2023March 31, 2028
    Comment
  • of which recipient is DisplacedValue0.000.0010600.00
    DateMarch 31, 2022November 30, 2023March 31, 2028
    Comment
  • of which DisplacedValue0.000.0023000.00
    DateMarch 31, 2022November 30, 2023March 31, 2028
    Comment
  • of which recipient is displacedValue0.000.008500.00
    DateMarch 31, 2022November 30, 2023March 31, 2028
    Comment
  • Beneficiaries receiving cash transfers on timeValue0.000.0080.00
    DateMarch 31, 2022November 30, 2023March 31, 2028
    Comment
  • Beneficiaries who completed the life and business skills trainingValue0.000.0085.00
    DateMarch 31, 2022November 30, 2023March 31, 2028
    Comment
  • Applications receivedValue0.000.006000.00
    DateMarch 31, 2022November 30, 2023March 31, 2028
    Comment
  • Beneficiaries receiving cash transfers on timeValue0.000.0080.00
    DateMarch 31, 2022November 30, 2023March 31, 2028
    Comment
  • Person days of temporary employment createdValue0.000.003300000.00
    DateMarch 31, 2022November 30, 2023March 31, 2028
    Comment
  • Beneficiaries participating in IGA accompanying measures and completing the activityValue0.000.0080.00
    DateMarch 31, 2022November 30, 2023March 31, 2028
    Comment
  • Beneficiaries who received the productive grantValue0.000.0098.00
    DateMarch 31, 2022November 30, 2023March 31, 2028
    Comment
  • of which femalesValue0.000.001800.00
    DateMarch 31, 2022November 30, 2023March 31, 2028
    Comment
  • Of which femaleValue0.000.001650000.00
    DateMarch 31, 2022November 30, 2023March 31, 2028
    Comment
  • Beneficiaries receiving payment on timeValue0.000.0080.00
    DateMarch 31, 2022November 30, 2023March 31, 2028
    Comment
  • Beneficiaries participating in human capital accompanying measures and completing the activityValue0.000.0080.00
    DateMarch 31, 2022November 30, 2023March 31, 2028
    Comment
  • Among women beneficiariesValue0.000.0098.00
    DateMarch 31, 2022November 30, 2023March 31, 2028
    Comment
  • of which displacedValue0.000.001200.00
    DateMarch 31, 2022November 30, 2023March 31, 2028
    Comment
  • Microprojects chosen through meaningful consultations with targeted communitiesValue0.000.0080.00
    DateMarch 31, 2022November 30, 2023March 31, 2028
    Comment
  • Beneficiaries participating in GBV accompanying measures and completing the activityValue0.000.0080.00
    DateMarch 31, 2022November 30, 2023March 31, 2028
    Comment
  • Beneficiaries running an IGAValue70.0070.0090.00
    DateMarch 31, 2022November 30, 2023March 31, 2028
    Comment
  • Grants disbursedValue0.000.002000.00
    DateMarch 31, 2022November 30, 2023March 31, 2028
    Comment
  • Microprojects contributing to climate change mitigation and adaptationValue0.000.0045.00
    DateMarch 31, 2022November 30, 2023March 31, 2028
    Comment
  • Among women beneficiariesValue50.0050.0090.00
    DateMarch 31, 2022November 30, 2023March 31, 2028
    Comment
  • of which femalesValue0.000.00600.00
    DateMarch 31, 2022November 30, 2023March 31, 2028
    Comment
  • Microprojects providing on-site childcare servicesValue002 per commune
    DateMarch 31, 2022November 30, 2023March 31, 2028
    Comment
  • Women running IGAs in non-traditional sectorsValue5.005.0025.00
    DateMarch 31, 2022November 30, 2023March 31, 2028
    Comment
  • of which displacedValue0.000.00400.00
    DateMarch 31, 2022November 30, 2023March 31, 2028
    Comment
  • Beneficiaries with active IGAs at least 6 months after the end of the programValue0.000.0080.00
    DateMarch 31, 2022November 30, 2023March 31, 2028
    Comment
  • Winners of BPC selected competitivelyValue0.000.002000.00
    DateMarch 31, 2022November 30, 2023March 31, 2028
    Comment
  • New firms supported under the Business Plan Competition (BPC) that are still operating 24 months after receiving assistance (financial and non-financial)Value0.000.0090.00
    DateMarch 31, 2022November 30, 2023March 31, 2028
    Comment
  • Among women beneficiariesValue0.000.0080.00
    DateMarch 31, 2022November 30, 2023March 31, 2028
    Comment
  • New firms established through BPCValue0.000.001000.00
    DateMarch 31, 2022November 30, 2023March 31, 2028
    Comment
  • Of which female ownedValue0.000.00300.00
    DateMarch 31, 2022November 30, 2023March 31, 2028
    Comment
  • Maximum program management expenses as share of total program expensesValue0.000.0015.00
    DateMarch 31, 2022November 30, 2023March 31, 2028
    Comment