Financier | Commitments |
---|---|
IDA Credit | 175.00 |
IDA Grant | 175.00 |
P175382
Active
Malaika Becoulet , Erick Abiassi, Moussa Dieng
BURKINA FASO
December 1, 2020
(as of board presentation)
December 15, 2020
March 31, 2021
US$ 350.00 million
Directorate in charge of Territorial Development
2021
US$ 350.00 million
N/A
High
December 31, 2025
Yes
BANK APPROVED
June 18, 2024
Financier | Commitments |
---|---|
IDA Credit | 175.00 |
IDA Grant | 175.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 350.00 |
IBRD + IDA Commitment | 350.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 350.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Dec 27, 2023 | IDA-D7610 | Loan Disb | 3,455,163.00 |
Jan 17, 2024 | IDA-D7610 | Loan Disb | 628,128.44 |
Jun 11, 2024 | IDA-D7610 | Loan Disb | 254,372.89 |
Jun 20, 2024 | IDA-E1000 | Loan Disb | 832,791.94 |
Jun 11, 2024 | IDA-E1000 | Loan Disb | 1,526,938.40 |
Aug 19, 2024 | IDA-E1000 | Loan Disb | 612,425.70 |
Dec 15, 2020 | IDA-68190 | Loan Commitment | 175,000,000.00 |
Dec 15, 2020 | IDA-D7610 | Loan Commitment | 175,000,000.00 |
Jun 17, 2022 | IDA-71810 | Loan Commitment | 61,500,000.00 |
Jun 17, 2022 | IDA-E1000 | Loan Commitment | 61,500,000.00 |
Sep 12, 2023 | IDA-D7610 | Loan Disb | 632,357.25 |
Jun 9, 2023 | IDA-D7610 | Loan Disb | 700,375.60 |
Jun 9, 2023 | IDA-D7610 | Loan Disb | 1,560,176.50 |
Jun 9, 2023 | IDA-D7610 | Loan Disb | 2,342,446.20 |
Sep 20, 2023 | IDA-D7610 | Loan Disb | 2,231,969.00 |
Feb 22, 2023 | IDA-D7610 | Loan Disb | 3,663,116.80 |
Feb 9, 2023 | IDA-E1000 | Loan Disb | 6,528,480.50 |
Feb 22, 2023 | IDA-E1000 | Loan Disb | 3,550,000.00 |
May 11, 2023 | IDA-E1000 | Loan Disb | 1,514,432.60 |
Mar 31, 2023 | IDA-D7610 | Loan Disb | 1,037,009.40 |
Mar 31, 2023 | IDA-D7610 | Loan Disb | 2,220,491.80 |
May 12, 2023 | IDA-D7610 | Loan Disb | 2,015,985.50 |
Jun 8, 2023 | IDA-E1000 | Loan Disb | 3,000,000.00 |
Aug 14, 2023 | IDA-E1000 | Loan Disb | 3,502,587.80 |
Jun 15, 2023 | IDA-D7610 | Loan Disb | 1,146,249.90 |
Jun 15, 2023 | IDA-D7610 | Loan Disb | 965,517.70 |
Jun 21, 2023 | IDA-D7610 | Loan Disb | 1,323,264.00 |
Aug 24, 2023 | IDA-D7610 | Loan Disb | 2,719,710.80 |
Jul 20, 2023 | IDA-D7610 | Loan Disb | 3,247,379.80 |
Oct 19, 2023 | IDA-D7610 | Loan Disb | 1,550,406.90 |
Jun 26, 2023 | IDA-E1000 | Loan Disb | 1,729,851.90 |
May 18, 2023 | IDA-E1000 | Loan Disb | 18,700,000.00 |
May 23, 2023 | IDA-D7610 | Loan Disb | 2,027,585.40 |
Jun 30, 2023 | IDA-D7610 | Loan Disb | 2,338,703.80 |
Jun 2, 2023 | IDA-D7610 | Loan Disb | 778,524.20 |
Jun 8, 2023 | IDA-D7610 | Loan Disb | 1,402,161.20 |
Jun 8, 2023 | IDA-D7610 | Loan Disb | 739,215.75 |
Dec 27, 2023 | IDA-D7610 | Loan Disb | 810,400.44 |
Dec 28, 2023 | IDA-E1000 | Loan Disb | 1,088,398.90 |
Jan 16, 2024 | IDA-D7610 | Loan Disb | 1,249,506.00 |
Dec 14, 2023 | IDA-D7610 | Loan Disb | 778,189.30 |
Oct 30, 2023 | IDA-E1000 | Loan Disb | 1,997,083.20 |
Nov 30, 2023 | IDA-D7610 | Loan Disb | 1,065,181.10 |
Dec 12, 2023 | IDA-E1000 | Loan Disb | 1,679,693.20 |
Dec 7, 2023 | IDA-D7610 | Loan Disb | 3,258,497.80 |
Sep 28, 2023 | IDA-D7610 | Loan Disb | 1,711,551.00 |
Nov 14, 2023 | IDA-D7610 | Loan Disb | 1,807,487.50 |
Nov 6, 2023 | IDA-D7610 | Loan Disb | 1,876,822.80 |
Oct 20, 2023 | IDA-D7610 | Loan Disb | 698,820.90 |
Oct 23, 2023 | IDA-D7610 | Loan Disb | 1,376,536.00 |
Oct 13, 2023 | IDA-E1000 | Loan Disb | 1,816,719.10 |
Dec 28, 2023 | IDA-D7610 | Loan Disb | 973,923.30 |
Jun 22, 2022 | IDA-D7610 | Loan Disb | 1,626,523.50 |
Jun 22, 2022 | IDA-D7610 | Loan Disb | 1,778,038.50 |
Dec 13, 2021 | IDA-D7610 | Loan Disb | 835,148.50 |
Jun 13, 2022 | IDA-D7610 | Loan Disb | 2,799,053.50 |
Jun 13, 2022 | IDA-D7610 | Loan Disb | 1,736,362.40 |
Jul 21, 2022 | IDA-D7610 | Loan Disb | 1,375,836.90 |
Jun 23, 2022 | IDA-D7610 | Loan Disb | 3,696,673.50 |
Jun 23, 2022 | IDA-D7610 | Loan Disb | 2,430,308.80 |
Jun 23, 2022 | IDA-D7610 | Loan Disb | 2,558,961.00 |
Jul 27, 2022 | IDA-D7610 | Loan Disb | 1,700,139.90 |
Jun 24, 2022 | IDA-D7610 | Loan Disb | 20,000,000.00 |
Jun 24, 2022 | IDA-D7610 | Loan Disb | 4,113,204.20 |
Oct 13, 2021 | IDA-D7610 | Loan Disb | 121,124.30 |
Dec 1, 2021 | IDA-D7610 | Loan Disb | 221,393.56 |
Sep 23, 2021 | IDA-D7610 | Loan Disb | 177,787.78 |
Nov 12, 2021 | IDA-D7610 | Loan Disb | 292,706.80 |
Sep 22, 2021 | IDA-D7610 | Loan Disb | 602,511.90 |
Jun 10, 2021 | IDA-D7610 | Loan Disb | 6,692,320.50 |
Jan 11, 2022 | IDA-D7610 | Loan Disb | 2,241,315.20 |
Dec 29, 2021 | IDA-D7610 | Loan Disb | 1,086,166.80 |
Aug 29, 2022 | IDA-D7610 | Loan Disb | 2,235,659.80 |
May 25, 2022 | IDA-D7610 | Loan Disb | 2,087,972.00 |
May 25, 2022 | IDA-D7610 | Loan Disb | 497,190.47 |
May 25, 2022 | IDA-D7610 | Loan Disb | 3,251,133.80 |
Jun 28, 2022 | IDA-D7610 | Loan Disb | 2,826,298.20 |
May 25, 2022 | IDA-D7610 | Loan Disb | 244,349.40 |
May 25, 2022 | IDA-D7610 | Loan Disb | 564,655.75 |
May 25, 2022 | IDA-D7610 | Loan Disb | 1,977,510.60 |
Jun 22, 2022 | IDA-D7610 | Loan Disb | 825,164.90 |
Apr 18, 2023 | IDA-D7610 | Loan Disb | 1,311,970.80 |
Mar 28, 2023 | IDA-D7610 | Loan Disb | 3,023,615.50 |
Mar 3, 2023 | IDA-D7610 | Loan Disb | 1,167,639.50 |
Feb 2, 2023 | IDA-D7610 | Loan Disb | 825,248.10 |
Jan 31, 2023 | IDA-D7610 | Loan Disb | 228,151.80 |
Jan 31, 2023 | IDA-D7610 | Loan Disb | 1,646,393.40 |
Jan 31, 2023 | IDA-D7610 | Loan Disb | 1,222,720.00 |
Feb 1, 2023 | IDA-D7610 | Loan Disb | 7,612,869.00 |
Feb 16, 2023 | IDA-D7610 | Loan Disb | 1,228,888.50 |
Jan 31, 2023 | IDA-D7610 | Loan Disb | 3,171,345.50 |
Apr 5, 2023 | IDA-E1000 | Loan Disb | 1,697,779.40 |
Apr 6, 2023 | IDA-D7610 | Loan Disb | 1,331,736.00 |
Sep 26, 2022 | IDA-D7610 | Loan Disb | 1,091,704.80 |
Jul 20, 2023 | IDA-D7610 | Loan Disb | 1,155,097.60 |
May 31, 2023 | IDA-D7610 | Loan Disb | 1,095,608.20 |
Aug 11, 2023 | IDA-D7610 | Loan Disb | 1,068,999.90 |
May 7, 2024 | IDA-68190 | Loan Disb | 601,643.70 |
May 7, 2024 | IDA-68190 | Loan Disb | 618,283.50 |
Jun 4, 2024 | IDA-68190 | Loan Disb | 695,021.94 |
Jun 26, 2024 | IDA-68190 | Loan Disb | 519,632.20 |
Jun 4, 2024 | IDA-68190 | Loan Disb | 870,728.20 |
Aug 30, 2024 | IDA-68190 | Loan Disb | 1,592,545.00 |
May 30, 2024 | IDA-68190 | Loan Disb | 888,953.90 |
Jun 25, 2024 | IDA-68190 | Loan Disb | 3,188,727.20 |
May 28, 2024 | IDA-68190 | Loan Disb | 930,494.80 |
Feb 8, 2024 | IDA-68190 | Loan Disb | 46,815.09 |
Feb 8, 2024 | IDA-68190 | Loan Disb | 385,886.28 |
Feb 20, 2024 | IDA-68190 | Loan Disb | 1,129,224.20 |
Feb 26, 2024 | IDA-68190 | Loan Disb | 3,078,121.20 |
Jun 11, 2024 | IDA-68190 | Loan Disb | 1,191,695.20 |
Mar 15, 2024 | IDA-71810 | Int Charges | 87,580.78 |
Mar 15, 2024 | IDA-71810 | Int Charges | 87,580.78 |
Mar 15, 2024 | IDA-68190 | Int Charges | 349.95 |
Mar 15, 2024 | IDA-68190 | Int Charges | 84,839.11 |
Apr 26, 2024 | IDA-68190 | Loan Disb | 2,653,225.00 |
Apr 2, 2024 | IDA-68190 | Loan Disb | 361,781.40 |
Feb 6, 2024 | IDA-68190 | Loan Disb | 2,807,937.00 |
Apr 2, 2024 | IDA-68190 | Loan Disb | 1,147,782.80 |
Aug 1, 2024 | IDA-68190 | Loan Disb | 869,138.60 |
Jun 24, 2024 | IDA-68190 | Loan Disb | -654,311.20 |
Jul 11, 2024 | IDA-68190 | Loan Disb | 1,931,151.40 |
May 10, 2024 | IDA-68190 | Loan Disb | 1,207,085.00 |
Jun 7, 2024 | IDA-68190 | Loan Disb | 698,955.60 |
Jun 7, 2024 | IDA-68190 | Loan Disb | 600,495.90 |
Aug 19, 2024 | IDA-68190 | Loan Disb | 513,097.56 |
May 10, 2024 | IDA-68190 | Loan Disb | 608,160.56 |
Jun 7, 2024 | IDA-68190 | Loan Disb | 1,714,145.50 |
Aug 12, 2021 | IDA-68190 | Loan Disb | 715,626.20 |
Aug 2, 2022 | IDA-68190 | Loan Disb | 42,991.11 |
Dec 30, 2021 | IDA-68190 | Loan Disb | 56,589.22 |
May 25, 2022 | IDA-68190 | Loan Disb | 17,596.62 |
May 25, 2022 | IDA-68190 | Loan Disb | 25,750.03 |
May 25, 2022 | IDA-68190 | Loan Disb | 21,071.50 |
May 25, 2022 | IDA-68190 | Loan Disb | 86,059.90 |
May 25, 2022 | IDA-68190 | Loan Disb | 21,783.09 |
Mar 15, 2022 | IDA-68190 | Int Charges | 461.04 |
Mar 15, 2022 | IDA-68190 | Int Charges | 461.04 |
Mar 15, 2022 | IDA-68190 | Int Charges | 17,789.73 |
Mar 15, 2022 | IDA-68190 | Int Charges | 17,789.73 |
Jun 23, 2022 | IDA-68190 | Loan Disb | 116,890.97 |
Jun 24, 2022 | IDA-68190 | Loan Disb | 2,221,376.00 |
Dec 2, 2021 | IDA-68190 | Loan Disb | 7,299,233.50 |
May 8, 2023 | IDA-68190 | Loan Disb | 1,319,703.80 |
Mar 28, 2023 | IDA-68190 | Loan Disb | 2,205,515.20 |
Mar 28, 2023 | IDA-68190 | Loan Disb | 2,822,239.80 |
Mar 2, 2023 | IDA-71810 | Loan Disb | 22,137,504.00 |
Apr 21, 2023 | IDA-68190 | Loan Disb | 616,493.75 |
Sep 26, 2022 | IDA-68190 | Loan Disb | 70,577.11 |
Sep 15, 2022 | IDA-68190 | Int Charges | 30,667.70 |
Sep 15, 2022 | IDA-68190 | Int Charges | 30,667.70 |
Sep 30, 2022 | IDA-68190 | Loan Disb | 132,261.95 |
Sep 15, 2023 | IDA-71810 | Int Charges | 6,013.06 |
Sep 15, 2023 | IDA-71810 | Int Charges | 6,013.06 |
Sep 15, 2023 | IDA-71810 | Int Charges | 84,663.68 |
Sep 15, 2023 | IDA-71810 | Int Charges | 84,663.68 |
Aug 30, 2023 | IDA-68190 | Loan Disb | 1,119,839.10 |
Jun 1, 2023 | IDA-71810 | Loan Disb | 652,070.25 |
Sep 15, 2023 | IDA-68190 | Int Charges | 182.84 |
Sep 15, 2023 | IDA-68190 | Int Charges | 182.84 |
Sep 15, 2023 | IDA-68190 | Int Charges | 64,768.22 |
Sep 15, 2023 | IDA-68190 | Int Charges | 64,768.22 |
Jul 14, 2023 | IDA-68190 | Loan Disb | 339,859.22 |
Feb 9, 2023 | IDA-68190 | Loan Disb | 244,346.20 |
Mar 15, 2023 | IDA-68190 | Int Charges | 40.02 |
Mar 15, 2023 | IDA-68190 | Int Charges | 40.02 |
Mar 15, 2023 | IDA-68190 | Int Charges | 38,702.47 |
Mar 15, 2023 | IDA-68190 | Int Charges | 38,702.47 |
Mar 14, 2023 | IDA-68190 | Loan Disb | 67,471.41 |
Jun 14, 2023 | IDA-68190 | Loan Disb | 77,027.27 |
Jun 14, 2023 | IDA-68190 | Loan Disb | 349,417.94 |
May 31, 2023 | IDA-68190 | Loan Disb | 522,859.53 |
Nov 30, 2023 | IDA-68190 | Loan Disb | 3,999,591.50 |
Feb 29, 2024 | IDA-68190 | Loan Disb | 1,427,545.10 |
Apr 11, 2024 | IDA-68190 | Loan Disb | 2,405,698.50 |
Mar 14, 2024 | IDA-68190 | Loan Disb | 1,437,517.10 |
Jul 25, 2024 | IDA-68190 | Loan Disb | 2,377,952.80 |
Aug 20, 2024 | IDA-68190 | Loan Disb | 3,339,985.80 |
Mar 15, 2024 | IDA-68190 | Int Charges | 84,839.11 |
May 22, 2024 | IDA-68190 | Loan Disb | 93,363.11 |
May 22, 2024 | IDA-68190 | Loan Disb | 754,661.56 |
May 22, 2024 | IDA-68190 | Loan Disb | 2,626,551.00 |
Mar 21, 2024 | IDA-68190 | Loan Disb | 2,048,549.10 |
Feb 15, 2024 | IDA-68190 | Loan Disb | 2,660,138.20 |
Mar 15, 2024 | IDA-68190 | Int Charges | 349.95 |
Jan 31, 2024 | IDA-68190 | Loan Disb | 1,365,722.80 |
Feb 23, 2024 | IDA-71810 | Loan Disb | 4,055,999.50 |
Name | Review | Date |
---|---|---|
Procurement | Satisfactory | 2024-11-24 |
Overall Implementation Progress (IP) | Satisfactory | 2024-11-24 |
Progress towards achievement of PDO | Satisfactory | 2024-11-24 |
Project Management | Satisfactory | 2024-11-24 |
Financial Management | Satisfactory | 2024-11-24 |
Monitoring and Evaluation | Satisfactory | 2024-11-24 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of beneficiaries with access to communication infrastructures (all-season roads and mobile broadband signal) | Value | 0.00 | 401491.00 | 300000.00 |
Date | December 18, 2020 | March 29, 2024 | December 31, 2025 | |
Comment |
Beneficiaries who have received improved essential social services as a result of the project (number) | Value | 0.00 | 953577.00 | 850000.00 |
Date | October 30, 2020 | March 29, 2024 | December 31, 2025 | |
Comment |
Rate of satisfaction expressed by the beneficiaries for the project investments based on addressed feedback from annual iterative satisfaction surveys | Value | 0.00 | 99.40 | 85.00 |
Date | October 30, 2020 | September 29, 2023 | December 31, 2024 | |
Comment |
Communes integrating feedback from beneficiaries' consultations (including IDP and women) into the key strategic documents (budgetsand development plan) | Value | 0.00 | 100.00 | 100.00 |
Date | October 30, 2020 | September 29, 2023 | January 31, 2025 | |
Comment |
Beneficiaries of emergency food and nutritional assistance in the project area during the lean season (number) | Value | 0.00 | 1454046.00 | 800000.00 |
Date | May 9, 2022 | September 29, 2023 | September 30, 2025 | |
Comment |
Women beneficiaries with improved income as a result of the project (number) | Value | 0.00 | 28976.00 | 300000.00 |
Date | October 30, 2020 | March 29, 2024 | December 31, 2025 | |
Comment |
of which 50 percent are women | Value | 0.00 | 495860.00 | 425000.00 |
Date | October 30, 2020 | March 29, 2024 | December 31, 2025 | |
Comment |
of which 30 percent are IDPs | Value | 0.00 | 285000.00 | 283000.00 |
Date | October 30, 2020 | September 29, 2023 | December 31, 2025 | |
Comment |
of which 30 percent are IDPs | Value | 0.00 | 1398.00 | 90000.00 |
Date | October 30, 2020 | February 28, 2023 | December 31, 2025 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Beneficiary Commune with at least one digital center | Value | 0.00 | 0.00 | 100.00 |
Date | October 30, 2020 | September 15, 2022 | December 31, 2025 | |
Comment |
Schools and Health centers adequately staffed and equipped | Value | 0.00 | 80.00 | 95.00 |
Date | October 30, 2020 | September 29, 2023 | December 31, 2025 | |
Comment |
Grievances received and addressed through the project GRM system | Value | 0.00 | 99.00 | 100.00 |
Date | October 30, 2020 | September 29, 2023 | December 31, 2025 | |
Comment |
Number of young women | Value | 0.00 | 2456.00 | 4000.00 |
Date | October 30, 2020 | September 29, 2023 | December 31, 2025 | |
Comment |
Farmers reached with agricultural assets or services | Value | 0.00 | 231327.00 | 125000.00 |
Date | May 13, 2022 | September 29, 2023 | December 31, 2025 | |
Comment |
People who have received essential health, nutrition, and population (HNP) services | Value | 0.00 | 852444.00 | 200000.00 |
Date | October 30, 2020 | September 29, 2023 | December 31, 2025 | |
Comment |
Farmers reached with agricultural assets or services - Female | Value | 0.00 | 60000.00 | 0.00 |
Date | ||||
Comment |
People who have received essential health, nutrition, and population (HNP) services - Female (RMS requirement) | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Number of children immunized | Value | 0.00 | 0.00 | 0.00 |
Date | October 30, 2020 | February 28, 2023 | December 31, 2025 | |
Comment |
Number of women and children who have received basic nutrition services | Value | 0.00 | 0.00 | 55000.00 |
Date | October 30, 2020 | February 28, 2023 | December 31, 2025 | |
Comment |
Number of deliveries attended by skilled health personnel | Value | 0.00 | 0.00 | 5000.00 |
Date | October 30, 2020 | February 28, 2023 | December 31, 2025 | |
Comment |
Students benefiting from direct interventions to enhance learning | Value | 0.00 | 111637.00 | 100000.00 |
Date | October 30, 2020 | September 29, 2023 | December 31, 2025 | |
Comment |
Students benefiting from direct interventions to enhance learning - Female | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Newly built or rehabilitated social infrastructures (education and health) with new electricity access from renewable energy power supply | Value | 0.00 | 184.00 | 105.00 |
Date | October 30, 2020 | March 29, 2024 | December 31, 2025 | |
Comment |
Communes with an dedicated budget and management committee in place for the infrastructures financed by the project | Value | 0.00 | 0.00 | 100.00 |
Date | October 30, 2020 | March 29, 2024 | December 31, 2025 | |
Comment |
Rural or Inter-Urban Roads Rehabilitated or Improved into climate resilient all-season roads | Value | 0.00 | 401.00 | 1100.00 |
Date | October 30, 2020 | March 29, 2024 | December 31, 2025 | |
Comment |
Number of economic infrastructures constructed or rehabilited by the project | Value | 0.00 | 125.00 | 400.00 |
Date | October 30, 2020 | February 28, 2023 | December 31, 2024 | |
Comment |
Number of beneficiary commune with fonctional Grievance Redress Mecanism and Conflict Management | Value | 0.00 | 30.00 | 15.00 |
Date | October 30, 2020 | March 29, 2024 | December 31, 2024 | |
Comment |
Construction or Curing of Storm Water Drainage Channel in flood prone locations in beneficiary urban communes | Value | 0.00 | 116.90 | 100.00 |
Date | October 30, 2020 | March 29, 2024 | December 31, 2025 | |
Comment |
Beneficairy with increased revenue because of income generating activities | Value | 0.00 | 43500.00 | 400000.00 |
Date | October 30, 2020 | September 29, 2023 | December 31, 2025 | |
Comment |
Simplified Drinking Water Supply System and Community boreholes for Drinking water equipped with Solar Energy | Value | 0.00 | 119.00 | 160.00 |
Date | October 30, 2020 | March 29, 2024 | December 31, 2025 | |
Comment |
Beneficiary participating in trainings in life-skills or livelihood | Value | 0.00 | 10742.00 | 15000.00 |
Date | October 30, 2020 | March 29, 2024 | December 31, 2025 | |
Comment |
Beneficiary employed through labor intensive works | Value | 0.00 | 161100.00 | 300000.00 |
Date | October 30, 2020 | April 11, 2024 | December 31, 2025 | |
Comment |
SGBV response center supported to provide integrated care in beneficiary communes | Value | 0.00 | 91.00 | 100.00 |
Date | October 30, 2020 | September 29, 2023 | December 31, 2025 | |
Comment |
Annual revenue of Beneficiary Communes | Value | 0.00 | 0.00 | 15.00 |
Date | October 30, 2020 | February 28, 2023 | December 31, 2025 | |
Comment |