Skip to Main Navigation

Congo Digital Acceleration Project

Abstract*

The proposed Digital Acceleration Congo project is designed to increase broadband internet access to underserved populations and improve the public sector’s capacity to deliver digitally enabled public services. The project is expected to increase 3G mobile broadband availability for additional 404,000 people, provide 3,000 people with opportunities to acquire certified foundational to advanced digital skills, and give 75,000 people a day access...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The PDO is (i) to increase broadband internet access to underserved populations, and (ii) to improve public sector's capacity to deliver digitally enabled public services.

Key Details

Project Details

  • P175592

  • Active

  • Heriniaina Andrianasy , Amadou Fall

  • The Republic of Congo

  • Congo, Republic of

  • April 30, 2021

  • (as of board presentation)

    June 2, 2022

  • January 12, 2023

  • US$ 100.00 million

  • Ministry of Posts, Telecommunications and Digital Economy

  • Western and Central Africa

  • 2022

  • US$ 100.00 million

  • N/A

  • Substantial

  • December 31, 2027

  • TBD

  • BANK APPROVED

  • January 31, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 100.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 100.00
IDA Commitment N/A
IBRD + IDA Commitment 100.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 100.00

Summary Status of World Bank Financing (US$ Millions) as of April 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of April 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jun 21, 2024 IBRD-93980 Loan Disb 733,157.70
Jun 21, 2024 IBRD-93980 Loan Disb 2,201,918.80
Jun 2, 2022 IBRD-93980 Loan Commitment 100,000,000.00
Feb 15, 2023 IBRD-93980 Loan Disb -2,558,326.50
May 9, 2023 IBRD-93980 Loan Disb 40,328.89
Apr 11, 2023 IBRD-93980 Loan Disb 65,954.40
Apr 14, 2023 IBRD-93980 Loan Disb 236,597.19
Jan 12, 2023 IBRD-93980 Loan Disb 250,000.00
Jan 12, 2023 IBRD-93980 Fee Charges 250,000.00
Mar 11, 2024 IBRD-93980 Int Charges 60,541.40
Mar 11, 2024 IBRD-93980 Int Charges 22,755.46
Feb 15, 2024 IBRD-93980 Loan Disb 1,433,043.80
Aug 28, 2024 IBRD-93980 Int Charges 22,899.20
Aug 28, 2024 IBRD-93980 Int Charges 38,180.26
Aug 15, 2024 IBRD-93980 Loan Disb 11,099,967.00
Aug 31, 2023 IBRD-93980 Int Charges 55,052.33
Aug 28, 2024 IBRD-93980 Int Charges 61,047.37
Feb 15, 2023 IBRD-93980 Loan Disb 2,558,326.50
Aug 31, 2023 IBRD-93980 Int Charges 121,064.00
Jan 12, 2023 IBRD-93980 Loan Disb 516,609.44
Aug 15, 2023 IBRD-93980 Loan Disb 859,489.94
Aug 31, 2023 IBRD-93980 Int Charges 4,103.65
Aug 31, 2023 IBRD-93980 Int Charges 119,756.91
Aug 31, 2023 IBRD-93980 Int Charges 25,176.29
Aug 15, 2023 IBRD-93980 Loan Disb -859,489.94
Feb 8, 2023 IBRD-93980 Loan Disb 2,308,326.50
Dec 22, 2023 IBRD-93980 Loan Disb 121,572.97
Aug 28, 2024 IBRD-93980 Int Charges 1,599.35
Aug 28, 2024 IBRD-93980 Int Charges 112,883.15
Aug 28, 2024 IBRD-93980 Int Charges 101,200.50
Oct 6, 2023 IBRD-93980 Loan Disb 370,356.03
Nov 30, 2023 IBRD-93980 Loan Disb 714,211.70
Feb 7, 2024 IBRD-93980 Loan Disb 226,903.08
Feb 15, 2024 IBRD-93980 Loan Disb -1,433,043.80
Jul 1, 2024 IBRD-93980 Loan Disb 618,032.56
Jul 1, 2024 IBRD-93980 Loan Disb 1,161,193.00
May 31, 2024 IBRD-93980 Loan Disb 548,806.25
May 31, 2024 IBRD-93980 Loan Disb 3,135,726.00
Aug 15, 2024 IBRD-93980 Loan Disb -11,099,967.00
Aug 15, 2024 IBRD-93980 Int Charges 48.10
Apr 5, 2024 IBRD-93980 Loan Disb 736,301.44
Jul 1, 2024 IBRD-93980 Loan Disb 262,243.50
Mar 11, 2024 IBRD-93980 Int Charges 120,869.98
Mar 11, 2024 IBRD-93980 Int Charges 200.58
Mar 11, 2024 IBRD-93980 Int Charges 19,304.98
Apr 8, 2024 IBRD-93980 Loan Disb 701,158.10
May 14, 2024 IBRD-93980 Loan Disb 206,862.02
Jun 12, 2024 IBRD-93980 Loan Disb 794,567.56

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Satisfactory 2024-12-24
Project Management Moderately Satisfactory 2024-12-24
Progress towards achievement of PDO Satisfactory 2024-12-24
Financial Management Unsatisfactory 2024-12-24
Monitoring and Evaluation Moderately Satisfactory 2024-12-24
Overall Implementation Progress (IP) Moderately Satisfactory 2024-12-24

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • New facilitated and digitally enabled public services available online to people citizens and businessesValue0.000.0010.00
    DateDecember 31, 2022September 29, 2023December 31, 2027
    Comment
  • Individuals (Civil servants and government contractors) who earned certifications in foundational, intermediate, and advanced digital skills throughout the project’s activitiesValue0.000.003000.00
    DateDecember 31, 2022September 29, 2023December 31, 2027
    Comment
  • Of which femaleValue0.000.0030.00
    Date
    Comment
  • of which reside in rural areas (percentage)Value0.000.0030.00
    Date
    Comment
  • of which womenValue0.000.0030.00
    Date
    Comment
  • Unique broadband subscribers per 100 inhabitantsValue25.0025.0045.00
    DateDecember 31, 2022September 29, 2023December 31, 2027
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • (Gender informed) Congo’s digital transformation strategy action plans validated and disseminatedValueNoNoYes
    DateDecember 31, 2022September 29, 2023December 31, 2027
    Comment
  • Localities covered in 3G by the projectValue0.000.00212.00
    DateDecember 31, 2021September 29, 2023December 31, 2027
    Comment
  • CR and ID legal and regulatory framework modernizedValueNoNoYes
    DateDecember 31, 2021September 29, 2023December 31, 2027
    Comment
  • Grievances addressed within the stipulated service standards for response times?Value0.000.0090.00
    DateDecember 31, 2021September 29, 2023December 31, 2027
    Comment
  • (Gender informed) Policy framework and regulation to enforce data protection legislation are establishedValueNoNoYes
    DateDecember 31, 2022September 29, 2023December 31, 2027
    Comment
  • Multimedia centers deployed in schools/post offices, according to standards to withstand climate-related shocks and natural disastersValue0.000.00132.00
    DateJanuary 31, 2022September 29, 2023December 31, 2027
    Comment
  • Digital ID roadmap and operational plan draftedValueNoNoYes
    DateDecember 31, 2021September 29, 2023December 31, 2027
    Comment
  • ANSSI is operationalValueNoNoYes
    DateDecember 31, 2022September 29, 2023December 31, 2027
    Comment
  • MDAs connected to fiber by the projectValue0.000.0022.00
    DateDecember 31, 2021September 29, 2023December 31, 2027
    Comment
  • Operationalization of digitalized CR databaseValueNoNoYes
    DateDecember 31, 2022September 29, 2023December 31, 2027
    Comment
  • Institutes and education facilities providing government-approved courses and certificationValue0.000.0020.00
    DateDecember 31, 2022September 29, 2023December 31, 2027
    Comment
  • People provided with new or enhanced access to broadband internetValue0.000.001500000.00
    DateDecember 31, 2022September 29, 2023December 31, 2027
    Comment
  • Average unique daily access to digital services developed under the projectValue0.000.0075000.00
    DateDecember 31, 2022September 29, 2023December 31, 2027
    Comment
  • Share of users satisfied with the eGov one-stop-shop portalValue0.000.0070.00
    DateDecember 31, 2021September 29, 2023December 31, 2027
    Comment
  • of which in rural areasValue0.000.000.00
    Date
    Comment
  • People provided with new or enhanced access to broadband internet – FemaleValue0.000.00120000.00
    Date
    Comment
  • Trained teachers and trainers in the education system throughout the projectValue0.000.00250.00
    DateDecember 31, 2022September 29, 2023December 31, 2027
    Comment
  • Private sector investment mobilized through the projectValue0.000.0012000000.00
    DateDecember 31, 2022September 29, 2023December 31, 2027
    Comment
  • People consulted or involved in the design and delivery of digitally enabled public servicesValue0.000.001000.00
    DateDecember 31, 2021September 29, 2023December 31, 2027
    Comment
  • of which womenValue0.000.0030.00
    Date
    Comment
  • of which percentage of womenValue0.000.0050.00
    Date
    Comment
  • Number of Public Data Centers upgradedValue0.000.002.00
    DateDecember 31, 2022September 29, 2023December 31, 2027
    Comment
  • Graduates from specialized digital skills training programs reporting labor market impacts and/or better education outcomes within 12 months after the completionValue0.000.00450.00
    DateDecember 31, 2022September 29, 2023December 31, 2027
    Comment
  • of which womenValue0.000.0030.00
    Date
    Comment