Abstract*

The development objective of the Greater Kampala Metropolitan Area (GKMA) Urban Development Program Program-for-Results for Uganda is to improve the institutional capacity in the GKMA for metropolitan coordination and management, and to increase access to improved infrastructure and services. Under the GKMA strategy, the Government highlights five strategic objectives and major program areas, which include: (i) competitive economic infrastructure...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To improve the institutional capacity in the Greater Kampala Metropolitan Area (GKMA) for metropolitan coordination and management, and to increase access to improved infrastructure and services

Key Details

Project Details

  • P175660

  • Active

  • Phan Huyen , Aguiratou Savadogo-Tinto, John Stephen Ajalu

  • Republic of Uganda

  • Uganda

  • November 27, 2021

  • (as of board presentation)

    May 31, 2022

  • December 28, 2023

  • US$ 4132.31 million

  • Ministry for Kampala Capital City and Metropolitan Affairs (MoKCCMA)

  • Eastern and Southern Africa

  • 2022

  • US$ 566.00 million

  • N/A

  • February 20, 2024

  • December 31, 2027

  • No

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 512.00
Borrower/Recipient 571.31
IDA Grant 54.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 566.00
IBRD + IDA Commitment 566.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 4132.31

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Mar 7, 2024 IDA-E0390 Loan Disb 1,445,301.60
Jun 24, 2024 IDA-E0390 Loan Disb 9,550,067.00
Jun 25, 2024 IDA-E0390 Loan Disb 1,428,841.10
May 31, 2022 IDA-71200 Loan Commitment 518,000,000.00
May 31, 2022 IDA-E0390 Loan Commitment 48,000,000.00
Jul 1, 2024 IDA-71200 Int Charges 10,342.80
Jun 25, 2024 IDA-71200 Loan Disb 29,728,196.00
Jun 24, 2024 IDA-71200 Loan Disb 4,286,784.00
Jun 24, 2024 IDA-71200 Loan Disb 1,428,928.00
Jul 1, 2024 IDA-71200 Int Charges 10,342.80
Apr 4, 2024 IDA-71200 Loan Disb 5,758,724.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Satisfactory 2025-03-09
Monitoring and Evaluation Satisfactory 2025-03-09
Overall Implementation Progress (IP) Satisfactory 2025-03-09

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • GKMA sub-national entities with strengthened institutional performance for service delivery, including climate resilience project designsValue0.000.0090.00
    DateJanuary 12, 2022February 20, 2024December 31, 2027
    Comment
  • Implementation of climate-resilient annual infrastructure investment planValue0.000.0095.00
    DateJanuary 12, 2022February 20, 2024December 31, 2027
    Comment
  • MoKMA and IMC with improved coordination and management capacityValue0.000.0095.00
    DateJanuary 12, 2022February 20, 2024December 31, 2027
    Comment
  • People provided with improved access to infrastructure under the ProgramValue0.000.001740.00
    DateJanuary 12, 2022February 20, 2024December 31, 2027
    Comment
  • Number of female direct beneficiariesValue0.000.000.00
    Date
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Infrastructure/investment completed with the Program supportValue00.00TBD, as planned in the capital investment plans
    DateJanuary 12, 2022February 20, 2024December 31, 2027
    Comment
  • The number of GKMA sub-national entities with climate and disaster-informed integrated neighborhood plans covering at least 30% of LG’s administrative boundaryValue0.000.009.00
    DateJanuary 12, 2022February 20, 2024December 31, 2027
    Comment
  • The number of GKMA sub-national entities with more than 5 percent increase in OSRValue0.000.009.00
    DateJanuary 12, 2022February 20, 2024December 31, 2027
    Comment
  • Rehabilitated Roads (km)Value00.00TBD
    DateJanuary 12, 2022February 20, 2024June 30, 2027
    Comment
  • GKMA sub-national entities that have prepared an ISG plan that includes urban resilience and climate change/disaster risk managementValue0.000.009.00
    DateJanuary 12, 2022February 20, 2024December 31, 2027
    Comment
  • Pedestrian walkways/NMT (km)Value00.00TBD
    DateJanuary 12, 2022February 20, 2024June 30, 2027
    Comment
  • GKMA sub-national entities that have substantively filled key staff positions and demonstrated basic capacities in fiduciary, E&S standards, and climate change/disaster risk managementValue0.000.009.00
    DateJanuary 12, 2022February 20, 2024December 31, 2027
    Comment
  • Signalized junctions (number)Value00.00TBD
    DateJanuary 12, 2022February 20, 2024June 30, 2027
    Comment
  • GKMA sub-national entities with strengthened, coordinated, climate -resilient, and integrated metropolitan planning and investmentsValue0.000.0030.00
    DateJanuary 12, 2022February 20, 2024December 31, 2027
    Comment
  • Stormwater drains (km)Value00.00TBD
    DateJanuary 12, 2022February 20, 2024June 30, 2027
    Comment
  • GKMA sub-national entities utilizing tax simplification and e-governance across the GKMAValue3.003.009.00
    DateJanuary 12, 2022February 20, 2024December 31, 2027
    Comment
  • Local economic infrastructure (number)Value00.00TBD
    DateJanuary 12, 2022February 20, 2024June 30, 2027
    Comment
  • Quarterly monitoring report template, updated to collect gender disaggregated data for MDG and ISG beneficiaries, is being usedValueNoNoYes
    DateJanuary 12, 2022February 20, 2024December 31, 2027
    Comment
  • Green parks created (square meter)Value00.00TBD
    DateJanuary 12, 2022February 20, 2024June 30, 2027
    Comment
  • Trees planted (number)Value00.00TBD
    DateJanuary 12, 2022February 20, 2024June 30, 2027
    Comment
  • GKMA sub-national entities with strengthened capacity on climate change mitigation and adaptationValue0.000.0030.00
    DateJanuary 12, 2022February 20, 2024December 31, 2027
    Comment
  • Value for Money (VfM) audits in the infrastructure investments deliveredValue0.000.0090.00
    DateJanuary 12, 2022February 20, 2024December 31, 2027
    Comment
  • Operation and Maintenance (O&M) of Infrastructure ProjectsValue0.000.0090.00
    DateJanuary 12, 2022February 20, 2024December 31, 2027
    Comment
  • Public satisfaction in the GKMA with completed infrastructure and services provided under the ProgramValueTBDTo be determined50%
    DateJanuary 12, 2022February 20, 2024December 31, 2027
    Comment
  • Number of clients in the GKMA serviced via the SMS platformValue0.000.005000000.00
    DateJanuary 12, 2022February 20, 2024December 31, 2027
    Comment