Financier | Commitments |
---|---|
IDA Credit | 15.00 |
P175720
Active
Jared Mercadante , Joanna Moody
Grenada
Grenada
February 22, 2021
(as of board presentation)
May 17, 2022
June 17, 2022
US$ 15.00 million
Ministry of Infrastructure and Physical Development, Public Utilities, Civil Aviation and Transport
2022
US$ 15.00 million
N/A
January 23, 2024
May 31, 2027
Yes
BANK APPROVED
Financier | Commitments |
---|---|
IDA Credit | 15.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 15.00 |
IBRD + IDA Commitment | 15.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 15.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Mar 8, 2024 | IDA-71070 | Loan Disb | 253,276.55 |
Dec 15, 2023 | IDA-71070 | Int Charges | 2,850.23 |
Dec 15, 2023 | IDA-71070 | Int Charges | 2,850.23 |
Aug 17, 2023 | IDA-71070 | Loan Disb | 87,935.95 |
Jun 5, 2023 | IDA-71070 | Loan Disb | 384,250.00 |
Dec 15, 2023 | IDA-71070 | Int Charges | 137.69 |
Jun 15, 2024 | IDA-71070 | Int Charges | 4,537.33 |
Nov 21, 2023 | IDA-71070 | Loan Disb | 94,786.92 |
Jun 15, 2024 | IDA-71070 | Int Charges | 81.52 |
Jun 15, 2024 | IDA-71070 | Int Charges | 81.52 |
Jun 15, 2024 | IDA-71070 | Int Charges | 4,537.33 |
May 17, 2022 | IDA-71070 | Loan Commitment | 15,000,000.00 |
Dec 15, 2023 | IDA-71070 | Int Charges | 137.69 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Moderately Satisfactory | 2025-02-21 |
Financial Management | Moderately Satisfactory | 2025-02-21 |
Monitoring and Evaluation | Moderately Satisfactory | 2025-02-21 |
Procurement | Moderately Satisfactory | 2025-02-21 |
Project Management | Satisfactory | 2025-02-21 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2025-02-21 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Persons with access to more disaster resilient critical infrastructure | Value | 0.00 | 0.00 | 50000.00 |
Date | December 6, 2021 | October 9, 2023 | March 17, 2027 | |
Comment |
Risk informed strategies and designs available to the government for investment planning towards strengthening infrastructure resilience | Value | 0.00 | 0.00 | 7.00 |
Date | January 24, 2022 | October 9, 2023 | May 19, 2027 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Bridge made disaster resilient | Value | 0.00 | 0.00 | 55.00 |
Date | December 6, 2021 | October 9, 2023 | March 17, 2027 | |
Comment |
Studies and assessments developed to inform disaster resilient designs and strategies | Value | 0.00 | 0.00 | 7.00 |
Date | December 7, 2021 | October 9, 2023 | March 17, 2027 | |
Comment |
Coastline protected against erosion | Value | 0.00 | 0.00 | 500.00 |
Date | December 6, 2021 | October 9, 2023 | March 17, 2027 | |
Comment |
Women believe they are better prepared to respond to natural disaster after participating in outreach, training and advocacy activities | Value | 0.00 | 0.00 | 75.00 |
Date | February 14, 2022 | October 9, 2023 | May 17, 2027 | |
Comment |
Project beneficiaries reporting satisfaction that the project’s stakeholder engagement and communications strategy met their information needs. | Value | 0.00 | 0.00 | 80.00 |
Date | December 6, 2021 | October 9, 2023 | March 17, 2027 | |
Comment |
Women facilitators hired and trained to undertake outreach, training and advocacy activities | Value | 0.00 | 0.00 | 20.00 |
Date | March 16, 2022 | October 9, 2023 | May 17, 2027 | |
Comment |
of which the female beneficiaries report satisfaction that the project’s stakeholder engagement and communications strategy met their information needs | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Increased capacity and knowledge of shelter coordinators to become decision-makers to better respond to the specific needs of women, girls, the elderly and the disabled | Value | 0.00 | 0.00 | 100.00 |
Date | March 16, 2022 | October 9, 2023 | May 17, 2027 | |
Comment |