Skip to Main Navigation

KP- Spending Effectively for Enhanced Development

Abstract*

Component 1: Strengthening capacity for transparent management of public finances (US$5 million) The TA will finance the following: (i) development and mainstreaming of an integrated MTFF; (ii) preparation and mainstreaming of budget ceilings consistent with the MTFF, including considerations of climate resilience; (iii) development of rules for public investment management of education and health assets; (iv) upgrade of existing e-systems for inventory...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To improve the availability and management of public resources for delivery of primary, middle and high school education and primary health care services.

Key Details

Project Details

  • P175727

  • Active

  • Akmal Minallah

  • Islamic Republic of Pakistan

  • Pakistan

  • February 15, 2021

  • (as of board presentation)

    April 22, 2021

  • May 6, 2021

  • US$ 2719.00 million

  • Finance Department, Government of Khyber Pakhtunkhwa

  • South Asia

  • 2021

  • US$ 400.00 million

  • N/A

  • Moderate

  • June 30, 2026

  • No

  • BANK APPROVED

  • May 22, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 400.00
Borrower/Recipient 319.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 400.00
IBRD + IDA Commitment 400.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 2719.00

Summary Status of World Bank Financing (US$ Millions) as of April 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of April 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Feb 15, 2022 IDA-68720 Int Charges 344,898.38
Feb 15, 2022 IDA-68720 Int Charges 344,898.38
Feb 15, 2022 IDA-68720 Int Charges 582,795.06
Feb 15, 2022 IDA-68720 Int Charges 6,504.52
Feb 15, 2023 IDA-68720 Int Charges 909,287.25
Apr 22, 2021 IDA-68720 Loan Commitment 400,000,000.00
Aug 15, 2023 IDA-68720 Int Charges 669,253.20
Aug 15, 2023 IDA-68720 Int Charges 669,253.20
Aug 15, 2023 IDA-68720 Int Charges 70,014.15
Aug 15, 2023 IDA-68720 Int Charges 1,065,003.10
Feb 15, 2022 IDA-68720 Int Charges 6,504.52
Jun 17, 2022 IDA-68720 Loan Disb 27,839,754.00
Jun 17, 2022 IDA-68720 Loan Disb 32,479,712.00
Jun 9, 2022 IDA-68720 Loan Disb 659,898.00
Aug 15, 2021 IDA-68720 Int Charges 184,086.81
Aug 15, 2021 IDA-68720 Int Charges 184,086.81
Aug 15, 2021 IDA-68720 Int Charges 306,811.30
May 12, 2021 IDA-68720 Loan Disb 96,355,096.00
Dec 27, 2022 IDA-68720 Loan Disb 23,123,344.00
Aug 15, 2022 IDA-68720 Int Charges 2,711.25
Aug 15, 2022 IDA-68720 Int Charges 404,187.12
Aug 15, 2022 IDA-68720 Int Charges 404,187.12
Aug 15, 2022 IDA-68720 Int Charges 489,134.12
Feb 15, 2024 IDA-68720 Int Charges 713,498.75
Feb 15, 2024 IDA-68720 Int Charges 1,189,164.60
Feb 15, 2024 IDA-68720 Int Charges 50,058.33
Jun 28, 2024 IDA-68720 Loan Disb 10,969,936.00
Feb 15, 2024 IDA-68720 Int Charges 713,498.75
Jun 26, 2024 IDA-68720 Loan Disb 27,404,614.00
Jun 5, 2024 IDA-68720 Loan Disb 6,908,647.50
Aug 15, 2024 IDA-68720 Int Charges 1,150,302.40
Aug 15, 2024 IDA-68720 Int Charges 745,063.94
Aug 15, 2024 IDA-68720 Int Charges 745,063.94
Aug 15, 2024 IDA-68720 Int Charges 26,526.96
Aug 15, 2024 IDA-68720 Int Charges 26,526.96
Jun 23, 2023 IDA-68720 Loan Disb 18,534,120.00
Feb 15, 2023 IDA-68720 Int Charges 587,739.44
Feb 15, 2023 IDA-68720 Int Charges 587,739.44
Feb 15, 2023 IDA-68720 Int Charges 186,885.31

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Monitoring and Evaluation Satisfactory 2024-12-19
Overall Implementation Progress (IP) Moderately Satisfactory 2024-12-19
Progress towards achievement of PDO Satisfactory 2024-12-19

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Increased facility level responsibility for budgeting and spending in primary and middle schools and primary healthcare facilitiesValueLimited facility level budget responsibility for pThis activity is on track. for the first three qua(a) At least 75% of primary health care facilities
    DateMarch 5, 2021April 30, 2024April 30, 2026
    Comment
  • of which girls' schoolsValue0.0050.0055.00
    Date
    Comment
  • of which, in NMDsValue0.0060.0040.00
    Date
    Comment
  • PHC facilities having all the essential medicines and commoditiesValue60.0070.0085.00
    DateMarch 5, 2021April 30, 2024April 30, 2026
    Comment
  • of which, Maternal and Neonatal ClinicsValue50.0067.0080.00
    DateMarch 31, 2021April 30, 2024April 30, 2026
    Comment
  • Districts that meet agreed KPIs for education and health service deliveryValueEducation and health service delivery District Key1. DOH, in collaboration with the World Bank, prepAdditional 5 districts meeting agreed KPI for deli
    DateJanuary 29, 2021April 30, 2024April 25, 2025
    Comment
  • of which, NMDsValue0.000.003.00
    Date
    Comment
  • PHC facilities with filled medical staff positions according to approved staffing normsValue10.0068.0060.00
    DateMarch 31, 2021April 30, 2024April 30, 2026
    Comment
  • Primary, Middle and High schools and PHC facilities have functioning basic infrastructureValueSeveral service delivery centers missing basic faca) Target achieved for the year but most of the sc(a) Additional 10% (45% in total) of primary, midd
    DateMarch 5, 2021April 30, 2024April 30, 2026
    Comment
  • Primary, middle, and high schools with filled teaching staff positions according to approved staffing normsValue0.0045.0045.00
    DateMarch 31, 2021April 30, 2024April 30, 2026
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Multi-year budgeting implemented integrating development and current expenditureValueDevelopment and recurrent budgets not integrated aDue to interim government, this activity was not cThree-year indicative budgeting ceiling announced
    DateNovember 30, 2020April 30, 2024April 30, 2026
    Comment
  • Automated budgeting and expenditure reporting systemsValueIFMIS coverage currently restricted only to FinancConsulting firm hired and As-Is analysis is carrieFD deployed the automated billing process in at le
    DateDecember 18, 2020April 30, 2024April 30, 2026
    Comment
  • Districts with completed audits within 90 days after the end of financial yearValue5.000.0030.00
    DateDecember 18, 2020April 30, 2024April 30, 2026
    Comment
  • Repairs and maintenance expenditure ( % of development expenditure )Value7.504.0012.00
    DateDecember 18, 2020April 30, 2024April 30, 2026
    Comment
  • of which, accounts for DESEValue5.000.0015.00
    Date
    Comment
  • of which, accounts for DoHValue0.000.0010.00
    Date
    Comment
  • of which for educationValue<37 percentAt least 5%
    Date
    Comment
  • Invoices paid directly into vendor bank accountsValue0.000.0055.00
    DateMarch 31, 2021April 30, 2024April 30, 2026
    Comment
  • of which, for healthValue<37 percentAt least 5%
    Date
    Comment
  • Proportion of approved development budget for continuing projects in elementary and secondary education released within 90 days after budget approvalValue25.0045.0065.00
    DateJanuary 29, 2021April 30, 2024April 30, 2026
    Comment
  • of which, for education related expensesValue0.000.0010.00
    Date
    Comment
  • A costed medium term expenditure plan for primary, middle, and high school education and primary health careValueKP does not have a costed MTEP for primary educatiMTEP was developed with the support of departmentsBudget releases for non-salary recurrent budget li
    DateMarch 5, 2021April 30, 2024April 30, 2026
    Comment
  • of which, for DOHValue0.000.0010.00
    Date
    Comment
  • Reduction in pension expenditureValuePension costs rising as a proportion of total reveProgress on achieving three parametric reformsFD has implemented six parametric reforms
    DateMarch 5, 2021April 30, 2024April 30, 2026
    Comment
  • Increased recurrent expenditure for repairs and maintenance of public investment assetsValueRepairs and maintenance budget low and climate conR&M budget increased by 1%(a) FD has increased its repairs and maintenance r
    DateMarch 5, 2021April 30, 2024April 30, 2026
    Comment
  • Citizens surveyed on budget priorities and receiving budget informationValue100000.00150000.00700000.00
    DateFebruary 1, 2021April 30, 2024April 30, 2026
    Comment
  • Availability of essential supplies in schools and hospitals and increased transparencyValueDelays in availability of essential medicine and sa) According to IMU data 70% PHC facilities having(a) On average at least 80% of primary health care
    DateMarch 5, 2021April 30, 2024April 30, 2026
    Comment