Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 280.00 |
Borrowing Agency | 120.00 |
P175728
Active
Poonam Ahluwalia Khanijo , Carmen Yee-Batista
India
February 3, 2021
(as of board presentation)
November 22, 2022
May 15, 2024
US$ 400.00 million
Urban Development and Urban Housing Department,Gujarat Urban Development Mission,Ahmedabad Municipal Corporation
2023
US$ 280.00 million
N/A
March 28, 2024
December 31, 2028
Yes
BANK APPROVED
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 280.00 |
Borrowing Agency | 120.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 280.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 280.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 400.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jul 15, 2024 | IBRD-94490 | Int Charges | 131,675.56 |
Aug 12, 2024 | IBRD-94490 | Loan Disb | 196,325.16 |
Nov 22, 2022 | IBRD-94490 | Loan Commitment | 280,000,000.00 |
May 15, 2024 | IBRD-94490 | Loan Disb | 700,000.00 |
May 15, 2024 | IBRD-94490 | Fee Charges | 700,000.00 |
Name | Review | Date |
---|---|---|
Financial Management | Satisfactory | 2025-02-25 |
Monitoring and Evaluation | Satisfactory | 2025-02-25 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2025-02-25 |
Progress towards achievement of PDO | Moderately Satisfactory | 2025-02-25 |
Procurement | Moderately Satisfactory | 2025-02-25 |
Project Management | Moderately Satisfactory | 2025-02-25 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Improved performance of AMC's property tax systems | Value | properties are not geo-tagged in GIS for tax admin | Same as baseline | At least 900,000 active properties have been geo-c |
Date | April 1, 2022 | October 31, 2023 | November 30, 2028 | |
Comment |
People with access to improved, climate-resilient wastewater services (Corporate Results Indicator [CRI], Climate indicator) | Value | 0.00 | 0.00 | 1500000.00 |
Date | April 1, 2022 | October 31, 2023 | November 30, 2028 | |
Comment |
Improved performance of AMC's wastewater management systems | Value | Fragmented capital planning, O&M planning and reve | Same as baseline | Certified accounts of wastewater operations of the |
Date | April 1, 2022 | October 31, 2023 | November 30, 2028 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
User Charges for wastewater introduced | Value | 0 | 0 | AMC has completed at least two billing cycles of w |
Date | April 1, 2022 | March 20, 2024 | November 28, 2028 | |
Comment |
Environmental compliance for wastewater treatment systems achieved | Value | Wastewater discharge from AMC's treatment faciliti | Same as baseline | At least 90 percent of wastewater effluent samples |
Date | April 1, 2022 | March 20, 2024 | November 30, 2028 | |
Comment |
GUDM’s project and fiduciary management system operationalized | Value | 0 | 0 | IT based project lifecycle management system opera |
Date | April 1, 2022 | March 20, 2024 | November 30, 2028 | |
Comment |
IFMS system upgraded for better budgeting and accounting systems | Value | 0 | 0 | IFMS system generates complete Balance Sheet / Ann |
Date | April 1, 2022 | March 20, 2024 | November 30, 2028 | |
Comment |
Wastewater pollution and quality monitoring system strengthened | Value | There is no wastewater quality and pollution monit | Same as baseline | AMC has disclosed at least two consecutive quarter |
Date | April 1, 2022 | March 20, 2024 | November 30, 2028 | |
Comment |
Project implementation arrangement fully operationalized and staffed at AMC and GUDM | Value | Project implementation arrangement to be operation | PIU is staffed and fully operational | Project implementation arrangement has been fully |
Date | April 1, 2022 | March 20, 2024 | November 30, 2028 | |
Comment |
Disclosure of financial performance of AMC improved | Value | External audits are not done annually and reports | Same as baseline | AMC has disclosed in its website audited annual ac |
Date | April 1, 2022 | March 20, 2024 | November 30, 2028 | |
Comment |
Performance orientation introduced in wastewater services | Value | AMC's wastewater management contracts do not inclu | Same as baseline | At least 4 consecutive quarterly performance revie |
Date | April 1, 2022 | March 20, 2024 | November 30, 2028 | |
Comment |
AMC's wastewater assets digitized in GIS | Value | Wastewater assets are not available in digital for | Same as baseline | At least [1700] of wastewater pipelines, [6000] ma |
Date | April 1, 2022 | March 20, 2024 | November 30, 2028 | |
Comment |
Additional quantity (MLD) of wastewater treated as per National Green Tribunal (NGT) norms | Value | 0.00 | 0.00 | 650.00 |
Date | April 1, 2022 | March 20, 2024 | November 30, 2028 | |
Comment |
Percentage of consumers satisfied with waste water and storm water management services | Value | 0.00 | 0.00 | 75.00 |
Date | April 1, 2022 | March 20, 2024 | November 30, 2028 | |
Comment |
Percentage of informal women workers skilled and provided access to technical job roles in AMC's wastewater services | Value | 0.00 | 0.00 | 15.00 |
Date | April 1, 2022 | March 20, 2024 | November 30, 2028 | |
Comment |