Gujarat Resilient Cities Partnership: Ahmedabad City Resilience Project

Abstract*

GRCP will support AMC in addressing key institutional, financial, and service delivery constraints to strengthen the resilience and sustainability in Ahmedabad. The project will provide a combination of technical and financial assistance to AMC in pivoting towards an integrated service delivery approach – one that is resilient, green, sustainable, and inclusive. In line with the three pillars of the urban sector partnership framework - the institutions...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To strengthen institutional, financial and service delivery performance in Ahmedabad

Key Details

Project Details

  • P175728

  • Active

  • Poonam Ahluwalia Khanijo , Carmen Yee-Batista

  • India

  • India

  • February 3, 2021

  • (as of board presentation)

    November 22, 2022

  • May 15, 2024

  • US$ 400.00 million

  • Urban Development and Urban Housing Department,Gujarat Urban Development Mission,Ahmedabad Municipal Corporation

  • South Asia

  • 2023

  • US$ 280.00 million

  • N/A

  • March 28, 2024

  • December 31, 2028

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 280.00
Borrowing Agency 120.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 280.00
IDA Commitment N/A
IBRD + IDA Commitment 280.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 400.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jul 15, 2024 IBRD-94490 Int Charges 131,675.56
Aug 12, 2024 IBRD-94490 Loan Disb 196,325.16
Nov 22, 2022 IBRD-94490 Loan Commitment 280,000,000.00
May 15, 2024 IBRD-94490 Loan Disb 700,000.00
May 15, 2024 IBRD-94490 Fee Charges 700,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Financial Management Satisfactory 2025-02-25
Monitoring and Evaluation Satisfactory 2025-02-25
Overall Implementation Progress (IP) Moderately Satisfactory 2025-02-25
Progress towards achievement of PDO Moderately Satisfactory 2025-02-25
Procurement Moderately Satisfactory 2025-02-25
Project Management Moderately Satisfactory 2025-02-25

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Improved performance of AMC's property tax systemsValueproperties are not geo-tagged in GIS for tax adminSame as baselineAt least 900,000 active properties have been geo-c
    DateApril 1, 2022October 31, 2023November 30, 2028
    Comment
  • People with access to improved, climate-resilient wastewater services (Corporate Results Indicator [CRI], Climate indicator)Value0.000.001500000.00
    DateApril 1, 2022October 31, 2023November 30, 2028
    Comment
  • Improved performance of AMC's wastewater management systemsValueFragmented capital planning, O&M planning and reveSame as baselineCertified accounts of wastewater operations of the
    DateApril 1, 2022October 31, 2023November 30, 2028
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • User Charges for wastewater introducedValue00AMC has completed at least two billing cycles of w
    DateApril 1, 2022March 20, 2024November 28, 2028
    Comment
  • Environmental compliance for wastewater treatment systems achievedValueWastewater discharge from AMC's treatment facilitiSame as baselineAt least 90 percent of wastewater effluent samples
    DateApril 1, 2022March 20, 2024November 30, 2028
    Comment
  • GUDM’s project and fiduciary management system operationalizedValue00IT based project lifecycle management system opera
    DateApril 1, 2022March 20, 2024November 30, 2028
    Comment
  • IFMS system upgraded for better budgeting and accounting systemsValue00IFMS system generates complete Balance Sheet / Ann
    DateApril 1, 2022March 20, 2024November 30, 2028
    Comment
  • Wastewater pollution and quality monitoring system strengthenedValueThere is no wastewater quality and pollution monitSame as baselineAMC has disclosed at least two consecutive quarter
    DateApril 1, 2022March 20, 2024November 30, 2028
    Comment
  • Project implementation arrangement fully operationalized and staffed at AMC and GUDMValueProject implementation arrangement to be operationPIU is staffed and fully operationalProject implementation arrangement has been fully
    DateApril 1, 2022March 20, 2024November 30, 2028
    Comment
  • Disclosure of financial performance of AMC improvedValueExternal audits are not done annually and reports Same as baselineAMC has disclosed in its website audited annual ac
    DateApril 1, 2022March 20, 2024November 30, 2028
    Comment
  • Performance orientation introduced in wastewater servicesValueAMC's wastewater management contracts do not incluSame as baselineAt least 4 consecutive quarterly performance revie
    DateApril 1, 2022March 20, 2024November 30, 2028
    Comment
  • AMC's wastewater assets digitized in GISValueWastewater assets are not available in digital forSame as baselineAt least [1700] of wastewater pipelines, [6000] ma
    DateApril 1, 2022March 20, 2024November 30, 2028
    Comment
  • Additional quantity (MLD) of wastewater treated as per National Green Tribunal (NGT) normsValue0.000.00650.00
    DateApril 1, 2022March 20, 2024November 30, 2028
    Comment
  • Percentage of consumers satisfied with waste water and storm water management servicesValue0.000.0075.00
    DateApril 1, 2022March 20, 2024November 30, 2028
    Comment
  • Percentage of informal women workers skilled and provided access to technical job roles in AMC's wastewater servicesValue0.000.0015.00
    DateApril 1, 2022March 20, 2024November 30, 2028
    Comment