Financier | Commitments |
---|---|
IDA Grant | 50.00 |
P175791
Active
Zaruhi Tokhmakhyan , Naif Abu-Lohom, Abdulhakim Al-Aghbari
United Nations Office for Project Services
Yemen, Republic of
May 2, 2021
(as of board presentation)
June 7, 2021
July 11, 2021
US$ 50.00 million
UNITED NATIONS OFFICE FOR PROJECT SERVICES (UNOPS)
2021
US$ 50.00 million
N/A
Substantial
June 30, 2026
TBD
BANK APPROVED
May 12, 2024
Financier | Commitments |
---|---|
IDA Grant | 50.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 50.00 |
IBRD + IDA Commitment | 50.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 50.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Mar 28, 2024 | IDA-D8450 | Loan Disb | 1,122,466.00 |
Dec 22, 2023 | IDA-E2140 | Loan Disb | 8,855,015.00 |
Sep 14, 2023 | IDA-D9570 | Loan Disb | 44,449,940.00 |
Feb 15, 2023 | IDA-D9570 | Loan Disb | 34,835,556.00 |
Jun 7, 2021 | IDA-D8450 | Loan Commitment | 50,000,000.00 |
Oct 21, 2022 | IDA-D8450 | Loan Disb | 18,071,932.00 |
Aug 3, 2021 | IDA-D8450 | Loan Disb | 28,066,520.00 |
Dec 20, 2021 | IDA-D9570 | Loan Commitment | 120,000,000.00 |
Jun 21, 2023 | IDA-E2140 | Loan Commitment | 19,500,000.00 |
Apr 13, 2022 | IDA-D9570 | Loan Disb | 16,401,277.00 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2024-12-03 |
Monitoring and Evaluation | Satisfactory | 2024-12-03 |
Overall Implementation Progress (IP) | Satisfactory | 2024-12-03 |
Procurement | Satisfactory | 2024-12-03 |
Project Management | Satisfactory | 2024-12-03 |
Financial Management | Moderately Satisfactory | 2024-12-03 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
People provided with restored access to rehabilitated water supply services | Value | 0.00 | 363768.00 | 1000000.00 |
Date | June 8, 2021 | February 21, 2024 | June 30, 2026 | |
Comment |
Of which are women | Value | 0.00 | 159212.00 | 480000.00 |
Date | June 8, 2021 | February 21, 2024 | June 30, 2026 | |
Comment |
Which benefit from climate resilient infrastructure approaches | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
People provided with restored access to rehabilitated sanitation services | Value | 0.00 | 220838.00 | 1300000.00 |
Date | June 8, 2021 | February 21, 2024 | June 30, 2026 | |
Comment |
Of which are women | Value | 0.00 | 102633.00 | 630500.00 |
Date | June 30, 2021 | February 21, 2024 | June 30, 2026 | |
Comment |
Which benefit from climate resilient infrastructure approaches | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
People benefiting from restored electricity supply to health facilities | Value | 0.00 | 240798.00 | 650000.00 |
Date | June 8, 2021 | February 21, 2024 | June 30, 2026 | |
Comment |
Of which are women | Value | 0.00 | 127623.00 | 318000.00 |
Date | June 8, 2021 | February 21, 2024 | June 30, 2026 | |
Comment |
People benefiting from improved urban roads | Value | 0.00 | 540350.00 | 1600000.00 |
Date | June 8, 2021 | February 21, 2024 | June 30, 2026 | |
Comment |
Of which are women | Value | 0.00 | 264772.00 | 784000.00 |
Date | June 8, 2021 | February 21, 2024 | June 30, 2026 | |
Comment |
People benefiting from reduced flood risk | Value | 0.00 | 160463.00 | 350000.00 |
Date | June 8, 2021 | February 21, 2024 | June 30, 2026 | |
Comment |
Of which are women | Value | 0.00 | 78765.00 | 168000.00 |
Date | June 8, 2021 | February 21, 2024 | June 30, 2026 | |
Comment |
Subprojects that adopt climate resilient infrastructure design approaches | Value | 0.00 | 60.00 | 60.00 |
Date | June 8, 2021 | February 21, 2024 | June 30, 2026 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Tertiary municipal services activities implemented. | Value | 0.00 | 88.00 | 170.00 |
Date | December 11, 2020 | February 21, 2024 | June 30, 2026 | |
Comment |
Number of managers and staff trained among local partners, local consultants and contractors. | Value | 0.00 | 1743.00 | 1800.00 |
Date | June 30, 2021 | February 21, 2024 | June 30, 2026 | |
Comment |
Increased understanding among employers who participated in the training, of the importance of gender diversity in their workforce and women’s economic empowerment. | Value | 0.00 | 64.00 | 75.00 |
Date | June 30, 2021 | February 21, 2024 | June 30, 2026 | |
Comment |
Urban roads rehabilitated | Value | 0.00 | 198.00 | 230.00 |
Date | June 30, 2021 | February 21, 2024 | June 30, 2026 | |
Comment |
Energy generation supported through the Project | Value | 0.00 | 14245.00 | 62000.00 |
Date | June 30, 2021 | February 21, 2024 | June 30, 2026 | |
Comment |
COVID-19 awareness building/training sessions in project locations. | Value | 0.00 | 15.00 | 15.00 |
Date | June 8, 2021 | February 21, 2024 | June 30, 2026 | |
Comment |
Critical urban facilities using solar power generation | Value | 0.00 | 32.00 | 124.00 |
Date | June 30, 2021 | February 21, 2024 | June 30, 2026 | |
Comment |
Share of trained unregistered business owners who complete a formal business registration - for female owned businesses | Value | 0.00 | 60.00 | 60.00 |
Date | June 30, 2021 | February 21, 2024 | June 30, 2026 | |
Comment |
Beneficiaries that participated in consultative forums to inform sub-project selection. | Value | 0.00 | 7768.00 | 5000.00 |
Date | June 30, 2021 | February 21, 2024 | June 30, 2026 | |
Comment |
Number of newly deployed waste bins | Value | 0.00 | 0.00 | 1500.00 |
Date | June 16, 2023 | June 16, 2023 | June 30, 2026 | |
Comment |
Increase in CCIF Revenues | Value | 0.00 | 0.00 | 25.00 |
Date | June 16, 2023 | June 16, 2023 | June 30, 2026 | |
Comment |
of which are women | Value | 0.00 | 40.00 | 35.00 |
Date | June 30, 2021 | February 21, 2024 | June 30, 2026 | |
Comment |
Percentage of beneficiaries that participated in consultative forums who reported that their feedback informed sub-project selection. | Value | 0.00 | 0.00 | 65.00 |
Date | June 30, 2021 | February 21, 2024 | June 30, 2026 | |
Comment |
Increase in frequency of waste collection | Value | 0.00 | 0.00 | 50.00 |
Date | June 16, 2023 | June 16, 2023 | June 30, 2026 | |
Comment |
Increase in the number of female staff in management positions in CCIFs | Value | 0.00 | 0.00 | 15.00 |
Date | June 16, 2023 | June 16, 2023 | June 30, 2026 | |
Comment |
women's responses | Value | 0.00 | 0.00 | 65.00 |
Date | June 30, 2021 | February 21, 2024 | June 30, 2026 | |
Comment |
Percentage of grievances that are addressed in 28 days | Value | 0.00 | 87.00 | 90.00 |
Date | March 26, 2021 | February 21, 2024 | June 30, 2026 | |
Comment |
Percentage of project financing executed by local contractors or suppliers | Value | 0.00 | 60.00 | 60.00 |
Date | June 30, 2021 | February 21, 2024 | June 30, 2026 | |
Comment |
Person-days of temporary employment created under the Project. | Value | 0.00 | 1015131.00 | 1590000.00 |
Date | March 26, 2021 | February 21, 2024 | June 30, 2026 | |
Comment |
Participating contractor and consulting firms must have a minimum of 10% of staff who are women | Value | No | Yes | Yes |
Date | June 7, 2021 | February 21, 2024 | June 30, 2026 | |
Comment |
Value of tender slots allocated for Women Owned Businesses (WOB) only | Value | 0.00 | 1132825.00 | 1500000.00 |
Date | December 17, 2021 | February 21, 2024 | June 30, 2026 | |
Comment |
Share of private sector participants that benefited from climate change training that reported they had a greater understanding of the need for climate adaptation and mitigation in Yemeni cities | Value | 0.00 | 0.00 | 50.00 |
Date | December 16, 2021 | February 21, 2024 | June 30, 2026 | |
Comment |
Number of SWM equipment made operational to CCIFs | Value | 0.00 | 0.00 | 200.00 |
Date | June 16, 2023 | June 16, 2023 | June 30, 2026 | |
Comment |