Skip to Main Navigation

Resilience, Entrepreneurship and Livelihood Improvement Project

Abstract*

The proposed Resilience, Entrepreneurship and Livelihood Improvement Project (RELI) aims to improve livelihoods of the poor and extreme poor, enhance their resilience and support rural entrepreneurship in project areas in Bangladesh. The recent disruptions created by the COVID-19 pandemic and recent climate-induced events such as cyclone Amphan have compounded the vulnerability of poor and extreme poor rural communities in Bangladesh. The proposed...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

Improve livelihoods of the poor and extreme poor, enhance their resilience and support rural entrepreneurship in project areas

Key Details

Project Details

  • P175820

  • Active

  • Samina Yasmin , Arshia Gupta

  • People’s Republic of Bangladesh

  • Bangladesh

  • December 10, 2020

  • (as of board presentation)

    May 20, 2021

  • October 5, 2021

  • US$ 341.00 million

  • Social Development Foundation

  • South Asia

  • 2021

  • US$ 300.00 million

  • N/A

  • February 21, 2024

  • May 28, 2026

  • TBD

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Local Beneficiaries 1.00
IDA Credit 300.00
Borrower/Recipient 40.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 300.00
IBRD + IDA Commitment 300.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 341.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Aug 31, 2023 IDA-68760 Loan Disb 5,074,088.50
Nov 15, 2023 IDA-68760 Int Charges 19,324.36
Nov 15, 2023 IDA-68760 Int Charges 328,395.10
Nov 15, 2023 IDA-68760 Int Charges 328,395.10
Nov 15, 2023 IDA-68760 Int Charges 530,110.44
Dec 26, 2023 IDA-68760 Loan Disb 6,881,510.00
Oct 19, 2023 IDA-68760 Loan Disb 2,452,001.80
May 25, 2023 IDA-68760 Loan Disb 3,857,153.20
May 23, 2024 IDA-68760 Loan Disb 3,795,857.00
Oct 16, 2023 IDA-68760 Loan Disb 2,011,768.60
Oct 26, 2023 IDA-68760 Loan Disb 4,927,567.00
Dec 12, 2023 IDA-68760 Loan Disb 4,146,169.80
Feb 29, 2024 IDA-68760 Loan Disb 6,593,990.00
Apr 22, 2024 IDA-68760 Loan Disb 5,507,379.00
May 15, 2024 IDA-68760 Int Charges 17,175.41
May 15, 2024 IDA-68760 Int Charges 442,485.72
May 15, 2024 IDA-68760 Int Charges 442,485.72
Feb 8, 2024 IDA-68760 Loan Disb 4,877,025.00
May 15, 2024 IDA-68760 Int Charges 726,550.75
Jun 27, 2024 IDA-68760 Loan Disb 2,798,579.00
Jun 6, 2024 IDA-68760 Loan Disb 1,824,115.60
May 15, 2022 IDA-68760 Int Charges 51,086.49
May 15, 2022 IDA-68760 Int Charges 51,086.49
Apr 2, 2024 IDA-68760 Loan Disb 4,688,464.00
May 15, 2022 IDA-68760 Int Charges 85,144.14
Jun 30, 2022 IDA-68760 Loan Disb 9,050,975.00
Sep 29, 2022 IDA-68760 Loan Disb 10,048,329.00
Dec 22, 2022 IDA-68760 Loan Disb 6,782,891.50
Nov 15, 2022 IDA-68760 Int Charges 4,971.08
Nov 15, 2022 IDA-68760 Int Charges 4,971.08
Nov 15, 2022 IDA-68760 Int Charges 114,644.00
Nov 15, 2022 IDA-68760 Int Charges 114,644.00
Nov 15, 2022 IDA-68760 Int Charges 161,548.40
Nov 17, 2022 IDA-68760 Loan Disb 7,698,357.00
Jan 24, 2022 IDA-68760 Loan Disb 23,255,814.00
May 20, 2021 IDA-68760 Loan Commitment 300,000,000.00
May 15, 2023 IDA-68760 Int Charges 38,576.89
May 15, 2023 IDA-68760 Int Charges 231,082.06
May 15, 2023 IDA-68760 Int Charges 231,082.06
May 15, 2023 IDA-68760 Int Charges 365,574.78
Feb 27, 2023 IDA-68760 Loan Disb 2,945,611.50
Mar 22, 2023 IDA-68760 Loan Disb 1,536,488.50
Apr 6, 2023 IDA-68760 Loan Disb 2,878,641.00
May 2, 2023 IDA-68760 Loan Disb 4,681,043.00
Sep 15, 2022 IDA-68760 Loan Disb 1,993,003.10
Jun 15, 2023 IDA-68760 Loan Disb 5,552,163.00
Aug 21, 2023 IDA-68760 Loan Disb 3,079,873.00
Jan 26, 2023 IDA-68760 Loan Disb 790,122.25
Feb 9, 2023 IDA-68760 Loan Disb 2,117,805.00
Jul 5, 2023 IDA-68760 Loan Disb 2,385,666.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Project Management Satisfactory 2025-03-16
Overall Implementation Progress (IP) Moderately Satisfactory 2025-03-16
Procurement Moderately Satisfactory 2025-03-16
Financial Management Moderately Satisfactory 2025-03-16
Progress towards achievement of PDO Satisfactory 2025-03-16
Monitoring and Evaluation Satisfactory 2025-03-16

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of beneficiaries with an income increase of at least 30% from Income Generating Activities and increased employmentValue0.000.00163072.00
    DateMay 28, 2021December 29, 2023May 28, 2026
    Comment
  • Direct project beneficiariesValue0.00822043.00744600.00
    DateMay 28, 2021December 29, 2023May 28, 2026
    Comment
  • Number of producers and rural entrepreneurs with increased income of at least 40%Value0.000.006500.00
    DateMay 28, 2021December 29, 2023May 28, 2026
    Comment
  • Share of beneficiaries with improved resilienceValue0.000.0030.00
    DateMay 28, 2021December 29, 2023May 28, 2026
    Comment
  • Of which female beneficiariesValue0.000.0090.00
    Date
    Comment
  • Of which female beneficiariesValue0.000.0090.00
    Date
    Comment
  • Of which female producers and rural entrepreneursValue0.000.000.00
    Date
    Comment
  • Of which female beneficiariesValue0.000.000.00
    Date
    Comment
  • Share of project beneficiaries in RELI villages changing poverty statusValue0.000.0025.00
    DateMay 28, 2021December 29, 2023May 28, 2026
    Comment
  • Share of beneficiaries who are satisfied with project activitiesValue0.000.0080.00
    DateMay 28, 2021December 29, 2023May 28, 2026
    Comment
  • Of which female beneficiariesValue0.000.000.00
    Date
    Comment
  • Female beneficiaries who are satisfied with project activitiesValue0.000.000.00
    Date
    Comment
  • Youth beneficiaries who are satisfied with project activitiesValue0.000.000.00
    Date
    Comment
  • Beneficiaries who are IPs and from other disadvantaged groups who are satisfied with project activitiesValue0.000.000.00
    Date
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Share of grievances redressed within the stipulated timeValue0.00100.0080.00
    DateMay 28, 2021December 29, 2023May 28, 2026
    Comment
  • Share of vulnerable people accessing one-time grant in RELI villagesValue0.00100.0095.00
    DateMay 28, 2021December 29, 2023May 28, 2026
    Comment
  • Number of producer groups registeredValue0.00102.00400.00
    DateMay 28, 2021December 29, 2023May 28, 2026
    Comment
  • Follow-up measures undertaken from recommendations of the social audit and community monitoring reportsValue0.0095.0080.00
    DateMay 28, 2021December 29, 2023May 28, 2026
    Comment
  • Climate-resilient infrastructure sub-projects completed with community participation, according to agreed design and quality standardsValue0.002149.005120.00
    DateMay 28, 2021December 29, 2023May 28, 2026
    Comment
  • Number of youth and returning migrants who received skill development trainingValue0.009422.0020000.00
    DateMay 28, 2021December 29, 2023May 28, 2026
    Comment
  • Number of beneficiaries with improved access to climate-resilient community infrastructureValue0.00241893.00640000.00
    DateMay 28, 2021December 29, 2023May 28, 2026
    Comment
  • Number of self and wage-employed youths and returning migrantsValue0.007223.0016000.00
    DateMay 28, 2021December 29, 2023May 28, 2026
    Comment
  • Number of students accessing higher education institutionValue0.00640.00640.00
    DateMay 28, 2021December 29, 2023May 28, 2026
    Comment
  • Of which female beneficiariesValue0.000.0090.00
    Date
    Comment
  • Number of beneficiaries with increased capacity on nutrition and healthValue0.000.00391680.00
    DateMay 28, 2021December 29, 2023May 28, 2026
    Comment
  • Of which female beneficiariesValue0.000.0090.00
    Date
    Comment
  • Number of beneficiaries who received training on climate risk, adaptation and resilience buildingValue0.00230464.00489600.00
    DateMay 28, 2021December 29, 2023May 28, 2026
    Comment
  • Of which female beneficiariesValue0.000.000.00
    Date
    Comment
  • Representatives in community-based decision making & management functions from poor and extreme poor beneficiariesValue0.00100.0090.00
    DateMay 28, 2021December 29, 2023May 28, 2026
    Comment
  • RELI Community Societies formed and providing services to member villagesValue0.000.00136.00
    DateMay 28, 2021December 29, 2023May 28, 2026
    Comment