Financier | Commitments |
---|---|
Special Financing | 25.00 |
Partnership for Intrastructure Development MDTF | 26.00 |
P176025
Active
Iyad Rammal , Marcus Wishart
Palestine Liberation Organization for the Benefit of the Palestinian Authority
June 16, 2022
(as of board presentation)
February 28, 2023
August 14, 2023
US$ 51.00 million
Palestinian Water Authority (PWA)
2023
US$ 51.00 million
N/A
Substantial
November 30, 2028
BANK APPROVED
November 7, 2023
Financier | Commitments |
---|---|
Special Financing | 25.00 |
Partnership for Intrastructure Development MDTF | 26.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 51.00 |
Total Project Cost** | 51.00 |
Name | Review | Date |
---|---|---|
Project Management | Satisfactory | 2024-09-30 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2024-09-30 |
Progress towards achievement of PDO | Satisfactory | 2024-09-30 |
Financial Management | Satisfactory | 2024-09-30 |
Monitoring and Evaluation | Satisfactory | 2024-09-30 |
Procurement | Moderately Satisfactory | 2024-09-30 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Increase bulk water availability through Salem and Al Jalameh connection points | Value | 0.00 | 0.00 | 7000000.00 |
Date | March 31, 2023 | October 16, 2023 | November 30, 2026 | |
Comment |
Number of regional water utilities established through clustering of service providers in West Bank; and their performance monitored against the KPIs | Value | 0.00 | 0.00 | 2.00 |
Date | March 31, 2022 | October 16, 2023 | November 30, 2028 | |
Comment |
Number of households benefitting from 24/7 water supply through individual connections | Value | 0.00 | 0.00 | 1500.00 |
Date | March 30, 2023 | October 16, 2023 | March 30, 2027 | |
Comment |
Performance of PWA staff for sector management improved | Value | No | No | Yes |
Date | March 30, 2023 | October 16, 2023 | November 30, 2028 | |
Comment |
Percentage of water samples compliant with WHO standards in project area | Value | 0.00 | 0.00 | 95.00 |
Date | March 31, 2023 | October 16, 2023 | November 30, 2028 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Length of the Jenin bulk water supply pipeline constructed | Value | 0.00 | 0.00 | 26.00 |
Date | March 31, 2023 | October 16, 2023 | November 30, 2026 | |
Comment |
Target RWUs established, staffed, and equipped with financial and operational systems | Value | 0.00 | 0.00 | 4.00 |
Date | March 30, 2023 | October 16, 2023 | November 30, 2028 | |
Comment |
Number of people benefitting from training on project management under the project (Number) | Value | 0.00 | 0.00 | 100.00 |
Date | March 30, 2023 | October 16, 2023 | November 30, 2028 | |
Comment |
Water storage capacity in the project area increased | Value | 0.00 | 0.00 | 5000.00 |
Date | March 30, 2023 | October 16, 2023 | November 30, 2026 | |
Comment |
National public awareness campaign conducted | Value | No | No | Yes |
Date | March 30, 2022 | October 16, 2023 | November 30, 2028 | |
Comment |
Number of female professionals benefitting from training under the project (Number) | Value | 0.00 | 0.00 | 50.00 |
Date | March 30, 2023 | October 16, 2023 | November 30, 2028 | |
Comment |
Length of water distribution network in villages of the North-East Jenin constructed | Value | 0.00 | 0.00 | 100.00 |
Date | March 31, 2023 | October 16, 2023 | March 31, 2027 | |
Comment |
Number of junior professionals hired as interns (Number) | Value | 0.00 | 0.00 | 25.00 |
Date | March 30, 2023 | October 16, 2023 | November 30, 2028 | |
Comment |
Number of regular stakeholders meetings for the project | Value | 0.00 | 0.00 | 10.00 |
Date | March 30, 2023 | October 16, 2023 | November 30, 2028 | |
Comment |
New metered piped water supply connections in Jenin area installed | Value | 0.00 | 0.00 | 5000.00 |
Date | March 30, 2023 | October 16, 2023 | November 30, 2028 | |
Comment |
Percentage of grievances responded to in the stipulated time | Value | 0.00 | 0.00 | 80.00 |
Date | March 30, 2023 | October 16, 2023 | November 30, 2028 | |
Comment |
Number of female interns reached through the internship program supported through the project | Value | 0.00 | 0.00 | 10.00 |
Date | March 30, 2023 | October 16, 2023 | November 30, 2028 | |
Comment |
Daily volume of wastewater treated through the Hebron Wastewater Treatment Plant | Value | 0.00 | 0.00 | 15000.00 |
Date | March 31, 2023 | October 16, 2023 | November 30, 2028 | |
Comment |
of which female recruited as staff by PWA | Value | 0.00 | 0.00 | 7.00 |
Date | February 28, 2023 | October 16, 2023 | November 30, 2028 | |
Comment |