Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 200.00 |
Borrower/Recipient | 50.00 |
P176032
Active
Surbhi Goyal , Pyush Dogra
India
August 11, 2021
(as of board presentation)
June 27, 2023
November 29, 2023
US$ 250.00 million
HPPCL (Himachal Pradesh Power Corporation Limited),HPSEBL (Himachal Pradesh State Electricity Board Limited),Directorate of Energy,HPPTCL (Himachal Pradesh Power Transmission Corporation Limited),HPSLDC (Himachal Pradesh State Load Despatch Centre),HimUrja
2023
US$ 200.00 million
N/A
March 5, 2024
March 31, 2028
BANK APPROVED
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 200.00 |
Borrower/Recipient | 50.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 200.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 200.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 250.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jun 15, 2024 | IBRD-95660 | Int Charges | 1,417.74 |
Nov 29, 2023 | IBRD-95660 | Fee Charges | 500,000.00 |
Jun 15, 2024 | IBRD-95660 | Int Charges | 204,663.45 |
Feb 13, 2024 | IBRD-95660 | Loan Disb | 19,156,668.00 |
Jun 27, 2023 | IBRD-95660 | Loan Commitment | 200,000,000.00 |
Jun 15, 2024 | IBRD-95660 | Int Charges | 433,406.00 |
Nov 29, 2023 | IBRD-95660 | Loan Disb | 500,000.00 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Government order issued for state level adoption of basin wide E&S protocols | Value | No | No | Yes |
Date | August 1, 2022 | March 15, 2024 | March 31, 2028 | |
Comment |
Increase in renewable energy generated | Value | 0.00 | 0.00 | 182353.00 |
Date | August 1, 2022 | March 15, 2024 | March 31, 2028 | |
Comment |
Cumulative GHG emission reduction | Value | 0.00 | 0.00 | 189300.00 |
Date | August 1, 2022 | March 15, 2024 | March 31, 2028 | |
Comment |
Availability of green power to the identified offtaker(s) through the bundled Renewable Energy product | Value | No | No | Yes |
Date | August 1, 2022 | March 15, 2024 | March 31, 2028 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Pilot for Demand Response System Launched | Value | No | No | Yes |
Date | August 1, 2022 | March 15, 2024 | March 31, 2028 | |
Comment |
Improved Redundancy through availability of (n-1) supply at the major EHV substations | Value | 0.00 | 0.00 | 3.00 |
Date | August 1, 2022 | March 15, 2024 | March 31, 2028 | |
Comment |
Adopt web-based Monitoring and Evaluation (M&E) systems to monitor E&S risk management | Value | No | No | Yes |
Date | August 1, 2022 | March 15, 2024 | March 31, 2028 | |
Comment |
Single Energy Trading Desk Operational | Value | No | No | Yes |
Date | August 1, 2022 | March 15, 2024 | March 31, 2028 | |
Comment |
Transformation Capacity Added | Value | 0.00 | 0.00 | 440000.00 |
Date | August 1, 2022 | March 15, 2024 | March 31, 2028 | |
Comment |
Percentage share of women in technical and managerial positions among annual new sector recruits | Value | 7.00 | 7.00 | 10.00 |
Date | August 1, 2022 | March 15, 2024 | March 31, 2028 | |
Comment |
Transmission System Added | Value | 0.00 | 0.00 | 90.00 |
Date | August 1, 2022 | March 15, 2024 | March 31, 2028 | |
Comment |
Number of women professionals trained as apprentices, with reporting on subsequent sector job applications and sector technical employment outcomes one year post-apprenticeship | Value | 0.00 | 0.00 | 150.00 |
Date | August 1, 2022 | March 15, 2024 | March 31, 2028 | |
Comment |
Average percent reduction of outages (in KVA of installed distribution transformers) during fault in the selected towns | Value | 0.00 | 0.00 | 65.00 |
Date | August 1, 2022 | March 15, 2024 | March 31, 2028 | |
Comment |
Citizen's Feedback Survey conducted by HPSEBL, HPPCL, HPPTCL, and HimUrja | Value | No | No | Yes |
Date | August 1, 2022 | March 15, 2024 | March 31, 2028 | |
Comment |
Capacity Added in Distribution Substations | Value | 0.00 | 0.00 | 179000.00 |
Date | August 1, 2022 | March 15, 2024 | March 31, 2028 | |
Comment |
Percent of the grievances to be resolved within 45 days from their receipt by HPSEBL, HPPCL, HPPTCL, HimUrja, and DoE | Value | 0.00 | 0.00 | 80.00 |
Date | August 1, 2022 | March 15, 2024 | March 31, 2028 | |
Comment |
Capacity Added in Distribution Transformers | Value | 0.00 | 0.00 | 160000.00 |
Date | August 1, 2022 | March 15, 2024 | March 31, 2028 | |
Comment |
Cumulative allocated budget for training utilized annually | Value | 0.00 | 100.00 | 100.00 |
Date | August 1, 2022 | March 15, 2024 | March 31, 2028 | |
Comment |
Distribution Network (33 kV, 11 kV and 400 Volts network added) added | Value | 0.00 | 0.00 | 1301.00 |
Date | August 1, 2022 | March 15, 2024 | March 31, 2028 | |
Comment |
Percentage of total tenders valued more than INR 10 million have used standard bidding document(s) | Value | 0.00 | 100.00 | 80.00 |
Date | August 1, 2022 | March 15, 2024 | March 31, 2028 | |
Comment |