Air Quality Improvement Project

Abstract*

The development objectives of the Air Quality Improvement Project for Bosnia and Herzegovina (BiH) are to strengthen air quality monitoring and management and reduce air pollutant emissions from the residential heating and transport sectors in the Federation of BiH (FBiH). The project comprises of four components. The first component, strengthening air quality monitoring and management objective is to help further develop and strengthen air quality...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Project Development Objectives (PDOs) are to strengthen air quality monitoring and management and reduce air pollutant emissions from the residential heating and transport sectors in the Federation of Bosnia and Herzegovina.

Key Details

Project Details

  • P176040

  • Active

  • Yuriy Myroshnychenko , Wenyu Jia, Esma Kreso Beslagic

  • Bosnia and Herzegovina

  • Bosnia and Herzegovina

  • December 15, 2021

  • (as of board presentation)

    May 30, 2023

  • May 15, 2024

  • US$ 50.00 million

  • FBiH Ministry of Environment and Tourism,Tuzla Canton,Environmental Protection Fund of the Federation of Bosnia and Herzegovina,Herzegovina-Neretva Canton,Zenica-Doboj Canton,Sarajevo Canton

  • Europe and Central Asia

  • 2023

  • US$ 50.00 million

  • N/A

  • October 2, 2023

  • June 30, 2029

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 50.00
Local Beneficiaries 20.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 50.00
IDA Commitment N/A
IBRD + IDA Commitment 50.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 50.00

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
May 15, 2024 IBRD-95180 Fee Charges 124,758.13
May 30, 2023 IBRD-95180 Loan Commitment 50,000,000.00
Aug 15, 2024 IBRD-95180 Int Charges 1,579.28
Aug 15, 2024 IBRD-95180 Loan Disb 126,896.01
Aug 15, 2024 IBRD-95180 Loan Disb -126,896.01
May 15, 2024 IBRD-95180 Loan Disb 124,758.13
Aug 15, 2024 IBRD-95180 Int Charges 71,689.32

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Satisfactory 2024-12-10
Monitoring and Evaluation Satisfactory 2024-12-10
Overall Implementation Progress (IP) Moderately Satisfactory 2024-12-10
Procurement Satisfactory 2024-12-10
Project Management Satisfactory 2024-12-10
Financial Management Satisfactory 2024-12-10

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Projected lifetime reduction in local fine particulate matter (PM2.5) emissionsValue0.000.0019000.00
    DateMarch 31, 2024September 18, 2023June 30, 2029
    Comment
  • Air Quality Centers established in the participating cantonsValue1.001.004.00
    DateMarch 31, 2024September 18, 2023June 30, 2029
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Private sector capital mobilized through household contributions (including own funds and commercial loans)Value0.000.0020000000.00
    DateMarch 31, 2024September 18, 2023June 30, 2029
    Comment
  • Total length of built bicycle infrastructureValue26.0026.0041.00
    DateMarch 31, 2024September 18, 2023June 30, 2029
    Comment
  • Females that cycle on a regular basis to work and report time and/or money savings as a result of cyclingValue0.000.0030.00
    DateMarch 31, 2024September 18, 2023June 30, 2029
    Comment
  • Projected energy or fuel savingsValue0.000.00750000000.00
    DateMarch 31, 2024September 18, 2023June 30, 2029
    Comment
  • Level of satisfaction among the public for Sarajevo as a cycling cityValue25.0025.0045.00
    DateMarch 31, 2024September 18, 2023June 30, 2029
    Comment
  • Projected lifetime reduction in greenhouse gas (GHG) emissionsValue0.000.00600000.00
    DateMarch 31, 2024September 18, 2023June 30, 2029
    Comment
  • Institutional Air Quality response mechanism established and operationalValueNoNoYes
    DateMarch 31, 2024September 18, 2023June 30, 2029
    Comment
  • Level of satisfaction among bus riders using the demonstration corridorValue33.0033.0060.00
    DateMarch 31, 2024September 18, 2023June 30, 2029
    Comment
  • Projected lifetime energy savingsValue0.000.00750000000.00
    DateMarch 31, 2024September 18, 2023June 30, 2029
    Comment
  • GHG accounting mechanism established and made operational under the FBiH Hydrometeorological InstituteValueNoNoYes
    DateMarch 31, 2024September 18, 2023June 30, 2029
    Comment
  • Number of households that have implemented sustainable heating and/or energy efficiency investments with a grant provided under theprojectValue0.000.0025000.00
    DateMarch 31, 2024September 18, 2023June 30, 2029
    Comment
  • Share of beneficiaries that are female-headed householdsValue0.000.000.00
    Date
    Comment