Financier | Commitments |
---|---|
IDA Credit | 143.00 |
Borrower/Recipient | 42.90 |
P176060
Active
Irina Voitekhovitch , Bahodir Amonov
Republic of Uzbekistan
December 28, 2021
(as of board presentation)
June 24, 2022
October 4, 2023
US$ 185.90 million
Extra-budgetary Intersectoral Energy Savings Fund,Ministry of Energy
2022
US$ 143.00 million
N/A
Moderate
December 29, 2028
TBD
BANK APPROVED
January 24, 2024
Financier | Commitments |
---|---|
IDA Credit | 143.00 |
Borrower/Recipient | 42.90 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 143.00 |
IBRD + IDA Commitment | 143.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 185.90 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Aug 15, 2024 | IDA-71720 | Int Charges | 1,872.00 |
Aug 15, 2024 | IDA-71720 | Int Charges | 2,590.89 |
Feb 23, 2024 | IDA-71720 | Loan Disb | 150,000.00 |
Feb 22, 2024 | IDA-71720 | Loan Disb | 200,000.00 |
Jun 21, 2024 | IDA-71720 | Loan Disb | 200,000.00 |
Jun 24, 2022 | IDA-71720 | Loan Commitment | 143,000,000.00 |
Aug 15, 2024 | IDA-71720 | Int Charges | 2,590.89 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Moderately Satisfactory | 2024-12-24 |
Project Management | Moderately Satisfactory | 2024-12-24 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2024-12-24 |
Procurement | Moderately Satisfactory | 2024-12-24 |
Financial Management | Satisfactory | 2024-12-24 |
Monitoring and Evaluation | Satisfactory | 2024-12-24 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Projected energy or fuel savings | Value | 0.00 | 0.00 | 34153000000.00 |
Date | January 13, 2023 | August 31, 2023 | December 29, 2028 | |
Comment |
Projected lifetime energy savings | Value | 0.00 | 0.00 | 4440000000.00 |
Date | January 13, 2023 | August 31, 2023 | December 29, 2028 | |
Comment |
Projected lifetime fuel savings | Value | 0.00 | 0.00 | 29713000000.00 |
Date | January 13, 2023 | August 31, 2023 | December 29, 2028 | |
Comment |
Projected electricity generation savings | Value | 0.00 | 0.00 | 5496000000.00 |
Date | January 13, 2023 | August 31, 2023 | December 29, 2028 | |
Comment |
Renewable energy generation capacity constructed under the project | Value | 0.00 | 0.00 | 25.00 |
Date | January 13, 2023 | August 31, 2023 | December 29, 2028 | |
Comment |
Clean energy secondary legislation (for energy audits, building energy efficiency performance, and energy service contracts) adopted under the Project | Value | None | None | (i) Secondary legislation for energy audits for th |
Date | January 13, 2023 | August 31, 2023 | December 29, 2028 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Net greenhouse gas (GHG) emissions | Value | 0.00 | 0.00 | 3509000.00 |
Date | January 13, 2023 | August 31, 2023 | December 29, 2028 | |
Comment |
Percentage of beneficiaries who report that the project has established effective citizen engagement processes | Value | 0.00 | 0.00 | 80.00 |
Date | January 13, 2023 | August 31, 2023 | December 29, 2028 | |
Comment |
Number of public buildings renovated with EE or renewable energy investments under the project | Value | 0.00 | 0.00 | 800.00 |
Date | January 13, 2023 | August 31, 2023 | December 29, 2028 | |
Comment |
Percentage increase in the number of women in technical and managerial jobs at companies directly benefitting from project | Value | 0.00 | 0.00 | 10.00 |
Date | January 13, 2023 | August 31, 2023 | December 29, 2028 | |
Comment |
Number of public building renovations financed using repayments under the ESAs | Value | 0.00 | 0.00 | 50.00 |
Date | January 13, 2023 | August 31, 2023 | December 29, 2028 | |
Comment |
Number of banks receiving support to provide clean energy financing for the buildings sector | Value | 0.00 | 0.00 | 3.00 |
Date | January 13, 2023 | August 31, 2023 | December 29, 2028 | |
Comment |
Private capital mobilized for clean energy investments in the buildings sector | Value | 0.00 | 0.00 | 10000000.00 |
Date | January 13, 2023 | August 31, 2023 | December 29, 2028 | |
Comment |
Full functionality of the Intersectoral Energy Savings Fund (Fund) with adequate staff as evidenced by a signed document transferring implementation responsibility from the PMC to the Fund | Value | Limited capacity | Limited capacity | Full functionality of the Fund with adequate staff |
Date | January 13, 2023 | August 31, 2023 | December 29, 2028 | |
Comment |
Annual average of the monthly solar output deviation at a selected facility | Value | 0.00 | 0.00 | 10.00 |
Date | January 13, 2023 | August 31, 2023 | December 29, 2028 | |
Comment |
Percentage of participants in capacity building activities who are women | Value | 0.00 | 0.00 | 30.00 |
Date | January 13, 2023 | August 31, 2023 | December 29, 2028 | |
Comment |