Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 40.00 |
P176105
Active
Helena Rovner , Antonella Novali
Oriental Republic of Uruguay
July 28, 2021
(as of board presentation)
January 19, 2022
November 7, 2022
US$ 40.00 million
Administracion Nacional de Educacion Publica
2022
US$ 40.00 million
N/A
Moderate
June 30, 2027
Yes
BANK APPROVED
February 6, 2024
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 40.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 40.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 40.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 40.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Aug 15, 2024 | IBRD-93310 | Int Charges | 622.28 |
Apr 11, 2024 | IBRD-93310 | Loan Disb | 1,327,949.10 |
Aug 15, 2024 | IBRD-93310 | Int Charges | 281,619.72 |
Aug 15, 2024 | IBRD-93310 | Int Charges | 38,975.10 |
Aug 15, 2024 | IBRD-93310 | Int Charges | 16,543.80 |
Dec 21, 2023 | IBRD-93310 | Loan Disb | 250,000.00 |
Dec 19, 2023 | IBRD-93310 | Loan Disb | 1,328,382.00 |
Aug 15, 2023 | IBRD-93310 | Int Charges | 124,716.72 |
Nov 17, 2022 | IBRD-93310 | Fee Charges | 100,000.00 |
Feb 15, 2024 | IBRD-93310 | Int Charges | 1,338.46 |
Feb 15, 2024 | IBRD-93310 | Int Charges | 42,076.10 |
Feb 15, 2024 | IBRD-93310 | Int Charges | 197,963.31 |
Aug 16, 2024 | IBRD-93310 | Loan Disb | 939,085.00 |
Jan 19, 2022 | IBRD-93310 | Loan Commitment | 40,000,000.00 |
Dec 16, 2022 | IBRD-93310 | Loan Disb | 4,000,000.00 |
Feb 15, 2023 | IBRD-93310 | Int Charges | 11,589.04 |
Aug 15, 2023 | IBRD-93310 | Int Charges | 1,287.68 |
Jun 1, 2023 | IBRD-93310 | Loan Disb | 1,052,574.90 |
Aug 24, 2023 | IBRD-93310 | Loan Disb | 1,098,299.40 |
Aug 15, 2023 | IBRD-93310 | Int Charges | 33,156.55 |
Aug 15, 2023 | IBRD-93310 | Int Charges | 44,089.42 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2024-11-29 |
Project Management | Satisfactory | 2024-11-29 |
Financial Management | Satisfactory | 2024-11-29 |
Monitoring and Evaluation | Satisfactory | 2024-11-29 |
Overall Implementation Progress (IP) | Satisfactory | 2024-11-29 |
Procurement | Satisfactory | 2024-11-29 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Percentage of schools implementing the new curriculum | Value | 0.00 | 0.00 | 65.00 |
Date | December 31, 2020 | December 6, 2023 | December 31, 2026 | |
Comment |
Percentage of ELT schools with an improved school governance index | Value | 0.00 | 0.00 | 50.00 |
Date | December 31, 2020 | December 6, 2023 | December 31, 2026 | |
Comment |
Repetition rate in quintile 1 and 2 primary schools | Value | 6.20 | 4.20 | 5.20 |
Date | December 31, 2020 | December 6, 2023 | December 31, 2026 | |
Comment |
Number of schools converted to Expanded Learning Time Schools | Value | 0.00 | 0.00 | 35.00 |
Date | December 31, 2020 | December 6, 2023 | December 31, 2026 | |
Comment |
Percentage of vulnerable schools implementing the new curriculum | Value | 0.00 | 0.00 | 65.00 |
Date | December 31, 2020 | December 6, 2023 | December 31, 2026 | |
Comment |
Repetition rate in quintile 1 and 2 primary schools, female | Value | 5.40 | 4.20 | 4.40 |
Date | December 31, 2020 | December 6, 2023 | December 31, 2026 | |
Comment |
Repetition rate in quintile 1 and 2 primary schools, male | Value | 7.00 | 4.10 | 6.00 |
Date | December 31, 2020 | December 6, 2023 | December 31, 2026 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Development of guidelines for the design of school infrastructure | Value | Guidelines not yet developed | Preparation of guidelines underway | Pilot implementation of guidelines |
Date | December 31, 2020 | December 6, 2023 | December 31, 2026 | |
Comment |
Number of members of school management teams trained | Value | 0.00 | 2208.00 | 5000.00 |
Date | December 31, 2020 | December 6, 2023 | December 31, 2026 | |
Comment |
Teachers recruited or trained | Value | 0.00 | 28209.00 | 45000.00 |
Date | December 31, 2020 | December 6, 2023 | December 31, 2026 | |
Comment |
Impact evaluations completed under the Project | Value | Impact evaluation not yet designed | Impact evaluation not yet designed | Results report of at least 1 impact evaluation |
Date | December 31, 2020 | December 6, 2023 | December 31, 2026 | |
Comment |
Number of schools that receive infrastructure works under the Project | Value | 0.00 | 50.00 | 175.00 |
Date | December 31, 2020 | December 6, 2023 | December 31, 2026 | |
Comment |
Development of a Monitoring Survey for teachers and directors | Value | Survey not yet designed | Survey designed, piloted, and undergoing first imp | Survey implemented and data reported |
Date | December 31, 2020 | December 6, 2023 | December 31, 2025 | |
Comment |
Number of female members of school management teams trained | Value | 0.00 | 1879.00 | 3845.00 |
Date | December 31, 2020 | December 6, 2023 | December 31, 2026 | |
Comment |
Number of teachers recruited | Value | 0.00 | 0.00 | 0.00 |
Date | December 31, 2020 | December 6, 2023 | December 31, 2026 | |
Comment |
Number of students enrolled in Expanded Learning Time schools | Value | 0.00 | 0.00 | 39375.00 |
Date | December 31, 2020 | December 6, 2023 | December 31, 2026 | |
Comment |
Percentage of schools that carry out activities to promote better management practices | Value | 0.00 | 0.00 | 50.00 |
Date | December 31, 2020 | December 6, 2023 | December 31, 2026 | |
Comment |
Teachers recruited or trained - Female (RMS requirement) | Value | 0.00 | 0.00 | 9288.00 |
Date | ||||
Comment |
Percentage of schools that develop an institutional management plan | Value | 0.00 | 0.00 | 70.00 |
Date | December 31, 2020 | December 6, 2023 | December 31, 2026 | |
Comment |
Number of teachers trained | Value | 0.00 | 28209.00 | 45000.00 |
Date | December 31, 2020 | December 6, 2023 | December 31, 2026 | |
Comment |
Percentage of female students enrolled in Expanded Learning Time schools | Value | 0.00 | 0.00 | 18900.00 |
Date | December 31, 2020 | December 6, 2023 | December 31, 2026 | |
Comment |
Percentage of schools that develop pedagogical innovations | Value | 0.00 | 0.00 | 25.00 |
Date | December 31, 2020 | December 6, 2023 | December 31, 2026 | |
Comment |
Percentage of vulnerable schools that develop pedagogical innovations | Value | 0.00 | 0.00 | 25.00 |
Date | December 31, 2020 | December 6, 2023 | December 31, 2026 | |
Comment |
Gender Gap: Percentage of female students that choose STEM-related tracks | Value | 37.00 | 37.00 | 40.00 |
Date | December 31, 2020 | December 6, 2023 | December 31, 2026 | |
Comment |
Citizen Engagement: Percentage of teachers and directors who consider that the in-service training received is useful for implementing the new curriculum | Value | 0.00 | 0.00 | 65.00 |
Date | December 31, 2020 | December 6, 2023 | December 31, 2026 | |
Comment |
Passing rate in secondary schools with expanded learning time | Value | 81.10 | 81.10 | 83.10 |
Date | December 31, 2020 | December 6, 2023 | December 31, 2026 | |
Comment |
Passing rate in secondary schools with expanded learning time, female | Value | 84.40 | 84.40 | 87.20 |
Date | December 31, 2020 | December 6, 2023 | December 31, 2026 | |
Comment |