Financier | Commitments |
---|---|
IDA Grant | 100.00 |
P176157
Active
Xavier Chavana , Suranga Kahandawa, Lizardo Narvaez Marulanda
Republic of Mozambique / Ministry of Economy and Finance
March 13, 2021
(as of board presentation)
April 27, 2021
July 1, 2021
US$ 100.00 million
Ministry of Economy and Finance
2021
US$ 100.00 million
N/A
May 28, 2024
April 30, 2026
TBD
BANK APPROVED
Financier | Commitments |
---|---|
IDA Grant | 100.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 100.00 |
IBRD + IDA Commitment | 100.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 100.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Feb 3, 2022 | IDA-D8090 | Loan Disb | 29,550,000.00 |
Mar 30, 2022 | IDA-D8090 | Loan Disb | 1,500,000.00 |
Oct 13, 2021 | IDA-D8090 | Loan Disb | 19,700,000.00 |
Dec 20, 2021 | IDA-D9530 | Loan Commitment | 100,000,000.00 |
Oct 5, 2023 | IDA-D9530 | Loan Disb | 89,100,000.00 |
Apr 27, 2021 | IDA-D8090 | Loan Commitment | 100,000,000.00 |
Nov 9, 2022 | IDA-D8090 | Loan Disb | 43,998,684.00 |
Name | Review | Date |
---|---|---|
Overall Implementation Progress (IP) | Satisfactory | 2024-11-11 |
Progress towards achievement of PDO | Satisfactory | 2024-11-11 |
Project Management | Satisfactory | 2024-11-11 |
Financial Management | Satisfactory | 2024-11-11 |
Procurement | Satisfactory | 2024-11-11 |
Monitoring and Evaluation | Moderately Satisfactory | 2024-11-11 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Percentage of beneficiaries satisfied with project activities towards increased resilience and social cohesion | Value | 0.00 | 0.00 | 75.00 |
Date | January 18, 2021 | February 14, 2024 | April 30, 2026 | |
Comment |
Number of beneficiaries with access to basic services and climate resilient public infrastructure. | Value | 0.00 | 95680.00 | 680000.00 |
Date | January 18, 2021 | February 14, 2024 | April 30, 2026 | |
Comment |
Number of beneficiaries with improved access to livelihoods support | Value | 0.00 | 90681.00 | 85000.00 |
Date | January 18, 2021 | February 14, 2024 | April 30, 2026 | |
Comment |
Percentage of female beneficiaries satisfied with project activities towards increased resilience and social cohesion | Value | 0.00 | 0.00 | 65.00 |
Date | ||||
Comment |
Percentage of which are women | Value | 0.00 | 0.00 | 60.00 |
Date | ||||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of climate resilient water sources rehabilitated or constructed | Value | 0.00 | 42.00 | 45.00 |
Date | January 18, 2021 | February 14, 2024 | April 30, 2026 | |
Comment |
Number of government officials trained in crisis recovery management skills | Value | 0.00 | 468.00 | 250.00 |
Date | January 18, 2021 | February 14, 2024 | April 30, 2026 | |
Comment |
Number of IDPs and host communities members provided with civil registration documents | Value | 0.00 | 133102.00 | 610000.00 |
Date | January 18, 2021 | February 14, 2024 | April 30, 2026 | |
Comment |
Number of IDPs and members of host communities benefiting from cash-for-work programs | Value | 0.00 | 13740.00 | 29000.00 |
Date | January 18, 2021 | February 14, 2024 | April 30, 2026 | |
Comment |
Number of improved latrines build | Value | 0.00 | 6893.00 | 13000.00 |
Date | January 18, 2021 | February 14, 2024 | April 30, 2026 | |
Comment |
Of which women and youth | Value | 0 | 4672 | 15,500 |
Date | January 18, 2021 | February 14, 2024 | April 30, 2026 | |
Comment |
Beneficiaries that report that their project-related grievances or proposals were addressed | Value | 0.00 | 90.00 | 75.00 |
Date | January 18, 2021 | February 14, 2024 | April 30, 2026 | |
Comment |
Number of community-based peacebuilding committees created and trained | Value | 0.00 | 38.00 | 55.00 |
Date | January 30, 2021 | February 14, 2024 | April 30, 2026 | |
Comment |
Number of climate resilient classrooms rehabilitated or constructed and equipped. | Value | 0.00 | 0.00 | 750.00 |
Date | January 18, 2021 | February 14, 2024 | April 30, 2026 | |
Comment |
Percentage of which led by women | Value | 0.00 | 0.00 | 40.00 |
Date | ||||
Comment |
Number of households benefiting from agricultural inputs | Value | 0.00 | 68962.00 | 79000.00 |
Date | January 18, 2021 | February 14, 2024 | April 30, 2026 | |
Comment |
Number of climate resilient health units constructed, rehabilitated / expanded and equipped | Value | 0.00 | 0.00 | 29.00 |
Date | January 18, 2021 | February 14, 2024 | April 30, 2026 | |
Comment |
Of which female-headed households | Value | 0 | 17,110 | 28,500 |
Date | January 18, 2021 | February 14, 2024 | April 30, 2026 | |
Comment |
Number of beneficiaries integrating community-based peacebuilding committees | Value | 0.00 | 1614.00 | 1100.00 |
Date | January 18, 2021 | February 14, 2024 | April 30, 2026 | |
Comment |
Number of toilets constructed | Value | 0.00 | 0.00 | 520.00 |
Date | January 18, 2021 | February 14, 2024 | April 30, 2026 | |
Comment |
Number of IDPs and host community members that complete vocational training courses | Value | 0.00 | 7979.00 | 16000.00 |
Date | January 18, 2021 | February 14, 2024 | April 30, 2026 | |
Comment |
Percentage of cases of violence, GBV and sexual abuse addressed through the Referral Pathway Mechanism | Value | 0.00 | 100.00 | 100.00 |
Date | January 18, 2021 | February 14, 2024 | April 30, 2026 | |
Comment |
Percentage of which completed by women and youth | Value | 0.00 | 0.00 | 50.00 |
Date | ||||
Comment |
Number of trauma victims who have received psychosocial service/support from community programs | Value | 0.00 | 34503.00 | 11000.00 |
Date | January 18, 2021 | February 14, 2024 | April 30, 2026 | |
Comment |
Number of climate resilient community infrastructure and amenities constructed | Value | 0.00 | 0.00 | 85.00 |
Date | January 18, 2021 | February 14, 2024 | December 31, 2025 | |
Comment |
Completion rate of literacy training completed by girls and women | Value | 0.00 | 85.00 | 80.00 |
Date | January 18, 2021 | February 14, 2024 | April 30, 2026 | |
Comment |
Percentage of relocation sites equipped with climate resilient women's friendly spaces | Value | 0.00 | 0.00 | 100.00 |
Date | January 18, 2021 | February 14, 2024 | April 30, 2026 | |
Comment |
Number of climate resilient public administration infrastructures constructed and rehabilitated | Value | 0.00 | 0.00 | 73.00 |
Date | October 22, 2021 | February 14, 2024 | April 30, 2026 | |
Comment |
Number of climate resilient power supply systems restored and equipped | Value | 0.00 | 0.00 | 23.00 |
Date | October 22, 2021 | February 14, 2024 | April 30, 2026 | |
Comment |
Number of public officials benefitting from recovered, rehabilitated, or reconstructed climate resilient public infrastructure | Value | 0.00 | 60.00 | 1200.00 |
Date | October 28, 2021 | February 14, 2024 | April 30, 2026 | |
Comment |