Uruguay Agro-Ecological and Climate Resilient Systems Project

Abstract*

The development objective of the Agro-ecological and Climate Resilient Systems Project for Uruguay is to: (i) strengthen agricultural public systems and rural producers to increase climate change adaptation and mitigation actions and promote agro-ecological production; and (ii) respond effectively in case of an eligible crisis or emergency. The project comprises of four components. The first component, strengthening decision support systems for climate...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

(i) strengthen agricultural public systems and rural producers to increase climate change adaptation and mitigation actions and promote Agro-ecological production; and (ii) respond effectively in case of an Eligible Crisis or Emergency.

Key Details

Project Details

  • P176232

  • Active

  • Edward Bresnyan , Pablo Valdivia Zelaya

  • Oriental Republic of Uruguay

  • Uruguay

  • May 11, 2021

  • (as of board presentation)

    November 30, 2021

  • June 17, 2022

  • US$ 52.50 million

  • Ministry of Livestock, Agriculture and Fisheries (MGAP)

  • Latin America and Caribbean

  • 2022

  • US$ 36.50 million

  • N/A

  • Moderate

  • November 30, 2026

  • Yes

  • BANK APPROVED

  • December 15, 2023

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 35.50
IBRD Fund for Innovative GPG Solutions 1.00
Local Beneficiaries 6.00
Borrower/Recipient 11.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 35.50
IDA Commitment N/A
IBRD + IDA Commitment 35.50
Lending Instrument
Grant Amount 1.00
Total Project Cost** 52.50

Summary Status of World Bank Financing (US$ Millions) as of April 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of April 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Aug 1, 2024 IBRD-93050 Loan Disb 938,956.30
Feb 20, 2024 IBRD-93050 Loan Disb 1,517,788.10
Jul 22, 2022 IBRD-93050 Loan Disb 1,304,311.90
Jun 24, 2022 IBRD-93050 Fee Charges 88,750.00
Jun 28, 2022 IBRD-93050 Loan Disb 5,000,000.00
Dec 5, 2022 IBRD-93050 Loan Disb 798,196.00
Feb 15, 2023 IBRD-93050 Int Charges 19,935.45
Feb 15, 2023 IBRD-93050 Int Charges 36,400.92
Feb 15, 2023 IBRD-93050 Int Charges 151,663.30
Jul 13, 2023 IBRD-93050 Loan Disb 2,175,116.50
Feb 15, 2023 IBRD-93050 Int Charges 18,809.57
Aug 15, 2023 IBRD-93050 Int Charges 7,391.24
Aug 15, 2023 IBRD-93050 Int Charges 34,713.46
Aug 15, 2023 IBRD-93050 Int Charges 199,194.77
Oct 11, 2023 IBRD-93050 Loan Disb 1,455,039.00
Aug 15, 2024 IBRD-93050 Int Charges 1,858.31
Aug 15, 2024 IBRD-93050 Int Charges 28,865.17
Aug 15, 2024 IBRD-93050 Int Charges 397,636.88
Feb 15, 2024 IBRD-93050 Int Charges 491.64
Feb 15, 2024 IBRD-93050 Int Charges 13,254.39
Feb 15, 2024 IBRD-93050 Int Charges 31,760.84
Feb 15, 2024 IBRD-93050 Int Charges 333,792.90
Nov 30, 2021 IBRD-93050 Loan Commitment 35,500,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Satisfactory 2024-12-07
Financial Management Satisfactory 2024-12-07
Monitoring and Evaluation Satisfactory 2024-12-07
Procurement Satisfactory 2024-12-07
Project Management Satisfactory 2024-12-07
Overall Implementation Progress (IP) Satisfactory 2024-12-07

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of producers using climate change information and data services and tools provided by the projectValue0.0012264.0012000.00
    DateJanuary 10, 2022October 12, 2023November 9, 2026
    Comment
  • Land area under sustainable landscape management practicesValue400000.001331714.001500000.00
    DateJanuary 10, 2022October 12, 2023November 9, 2026
    Comment
  • Farmers adopting improved agricultural technologyValue0.00471.002020.00
    DateJanuary 10, 2022October 12, 2023November 9, 2026
    Comment
  • Women accessing climate change information and data services and tools provided by the projectValue0.003406.004200.00
    DateJanuary 10, 2022October 12, 2023November 2, 2026
    Comment
  • Men accessing climate change information and data services and tools provided by the projectValue0.008858.007800.00
    DateJanuary 10, 2022October 12, 2023November 9, 2026
    Comment
  • Farmers adopting improved agricultural technology - FemaleValue0.000.000.00
    Date
    Comment
  • Collaboration across technical entities in the agriculture sector improvedValue0.007.005.00
    DateJanuary 10, 2022October 12, 2023November 9, 2026
    Comment
  • Farmers adopting improved agricultural technology - maleValue0.000.000.00
    Date
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Area with information for management of climate risks for agriculture risk insuranceValue50134.00221909.00300000.00
    DateJanuary 10, 2022October 12, 2023November 9, 2026
    Comment
  • Number of Producers supported with Subprojects for an agroecological transitionValue0.00176.00700.00
    DateJanuary 10, 2022October 12, 2023November 9, 2026
    Comment
  • Beneficiaries reporting satisfaction with design and implementation of subprojectsValue0.0096.0085.00
    DateJanuary 9, 2023October 12, 2023November 9, 2026
    Comment
  • Area monitored by the Agricultural Monitoring System (DMA)Value303000.00993523.001150000.00
    DateJanuary 10, 2022October 12, 2023November 9, 2026
    Comment
  • Women reporting satisfaction with project supported subprojectsValue0.0097.0085.00
    DateJanuary 10, 2022October 12, 2023November 9, 2026
    Comment
  • Women supported with Subprojects for an agroecological transitionValue0.0082.00210.00
    DateJanuary 10, 2022October 12, 2023November 9, 2026
    Comment
  • Area of the country with cartography 1:40.000Value45.0064.0075.00
    DateJanuary 10, 2022October 12, 2023November 9, 2026
    Comment
  • Men reporting satisfaction with project-supported subprojectsValue0.0095.0085.00
    DateJanuary 10, 2022October 12, 2023November 9, 2026
    Comment
  • Men supported with Subprojects for an agroecological transitionValue0.0094.00490.00
    DateJanuary 10, 2022October 12, 2023November 9, 2026
    Comment
  • All beneficiaries of project investmentsValue0.0012735.0017400.00
    DateJanuary 10, 2022October 12, 2023November 9, 2026
    Comment
  • Number of Subprojects supporting effluent management technologies in priority watershedsValue370.00375.00570.00
    DateJanuary 10, 2022October 12, 2023November 9, 2026
    Comment
  • Number of beneficiaries capacitated in the use of Ministry information systemsValue0.00418.00500.00
    DateJanuary 10, 2022October 12, 2023November 9, 2026
    Comment
  • Public goods generated through agroecological transitionsValue0.000.004.00
    DateJanuary 10, 2022October 12, 2023November 9, 2026
    Comment
  • Beneficiaries of project investments - womenValue0.003510.006900.00
    DateJanuary 10, 2022October 12, 2023November 9, 2026
    Comment
  • Female beneficiaries capacitated in the use of Ministry SystemsValue0.00144.00250.00
    DateJanuary 10, 2022October 12, 2023November 9, 2026
    Comment
  • Producers with knowledge and skills of agroecological transitionsValue0.000.003300.00
    DateJanuary 10, 2022October 12, 2023November 9, 2026
    Comment
  • Beneficiaries of project investments - menValue0.009225.0010500.00
    DateJanuary 10, 2022October 12, 2023November 9, 2026
    Comment
  • Male beneficiaries capacitated in the use of Ministry SystemsValue0.00274.00250.00
    DateJanuary 10, 2022October 12, 2023November 9, 2026
    Comment
  • Number of women receiving tablets and digital literacy technical assistanceValue0.000.002000.00
    DateJanuary 10, 2022October 12, 2023November 9, 2026
    Comment
  • Producers with knowledge and skills of agroecological transitions - womenValue0.000.001650.00
    DateJanuary 10, 2022October 12, 2023November 9, 2026
    Comment
  • Domestic dogs registered in national traceability system (Number)Value0.00141844.00500000.00
    DateJanuary 10, 2022October 12, 2023November 9, 2026
    Comment
  • Producers with knowledge and skills of agroecological transitions - menValue0.000.001650.00
    DateJanuary 10, 2022October 12, 2023November 9, 2026
    Comment
  • Number of digital products developed for management of natural resources and climate risksValue0.002.004.00
    DateJanuary 10, 2022October 12, 2023November 9, 2026
    Comment
  • National Plan for Agroecology in execution and implementation arrangements establishedValueNoYesYes
    DateJanuary 10, 2022October 12, 2023November 9, 2026
    Comment
  • Grievances received that are addressedValue0.00100.00100.00
    DateJanuary 10, 2022October 12, 2023November 9, 2026
    Comment