Skip to Main Navigation

Chattogram Water Supply Improvement Project

Abstract*

The project (Phase I of the Bangladesh Water Security and WSS MPA) will support the Government of Bangladesh in achieving the SDG Goal 6 and advance the utility reform agenda ensuring long-term sustainability of Water Supply and Sanitation (WSS) service provision in Chattogram. The MPA will comprise four phases spanning over nine years (2024-2033) to support 15 cities with an estimated 20 million beneficiaries. The program framework includes three...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Project Development Objectives (PDOs) are to (i) increase access to safely managed water supply in Chattogram; and (ii) improve operational performance and financial sustainability of Chattogram Water Supply and Sewerage Authority (CWASA).

Key Details

Project Details

  • P176429

  • Active

  • Arif Ahamed , Harsh Goyal

  • People's Republic of Bangladesh

  • Bangladesh

  • August 13, 2021

  • (as of board presentation)

    December 19, 2024

  • N/A

  • US$ 397.00 million

  • Chattogram Water Supply and Sewerage Authority

  • South Asia

  • 2025

  • US$ 280.00 million

  • N/A

  • June 10, 2023

  • December 31, 2030

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 140.00
Borrower/Recipient 53.00
IDA Shorter Maturity Loan (SML) 140.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 280.00
IBRD + IDA Commitment 280.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 397.00

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

No data available.