Financier | Commitments |
---|---|
IDA Grant | 19.49 |
P176478
Active
Rebecca Gilsdorf , Christian Severin, Shona Fitzgerald
Republic of Kiribati
August 18, 2021
(as of board presentation)
May 25, 2022
September 6, 2022
US$ 19.49 million
Ministry of Infrastructure and Sustainable Energy
2022
US$ 19.49 million
N/A
Substantial
May 31, 2028
Yes
BANK APPROVED
February 25, 2024
Financier | Commitments |
---|---|
IDA Grant | 19.49 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 19.49 |
IBRD + IDA Commitment | 19.49 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 19.49 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jun 21, 2024 | IDA-E0240 | Loan Disb | 127,653.41 |
May 25, 2022 | IDA-E0240 | Loan Commitment | 19,490,000.00 |
Oct 27, 2022 | IDA-E0240 | Loan Disb | 415,442.90 |
Mar 28, 2024 | IDA-E0240 | Loan Disb | 100,683.13 |
Sep 21, 2023 | IDA-E0240 | Loan Disb | 53,375.54 |
Feb 22, 2023 | IDA-E0240 | Loan Disb | 4,204.47 |
Dec 20, 2023 | IDA-E0240 | Loan Disb | 127,186.75 |
Oct 17, 2022 | IDA-E0240 | Loan Disb | 314,000.00 |
Name | Review | Date |
---|---|---|
Financial Management | Satisfactory | 2024-12-16 |
Project Management | Moderately Unsatisfactory | 2024-12-16 |
Monitoring and Evaluation | Moderately Satisfactory | 2024-12-16 |
Progress towards achievement of PDO | Moderately Satisfactory | 2024-12-16 |
Overall Implementation Progress (IP) | Moderately Unsatisfactory | 2024-12-16 |
Procurement | Moderately Unsatisfactory | 2024-12-16 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
People provided with access to improved sanitation services | Value | 0.00 | 0.00 | 20100.00 |
Date | May 25, 2022 | January 15, 2024 | May 31, 2028 | |
Comment |
PUB's cost recovery rate from sewerage tariffs | Value | 0.00 | 0.00 | 22.00 |
Date | May 25, 2022 | January 15, 2024 | May 31, 2028 | |
Comment |
People provided with access to improved sanitation services - Female (RMS requirement) | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Number of villages certified Open Defecation Free | Value | 0.00 | 0.00 | 4.00 |
Date | May 25, 2022 | January 15, 2024 | May 31, 2028 | |
Comment |
Improved septage management: volume of fecal sludge from onsite sanitation facilities properly collected and disposed | Value | 0.00 | 0.00 | 297.00 |
Date | May 25, 2022 | January 15, 2024 | May 31, 2028 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
New household sewer connections constructed under the project that reduce greenhouse gases emitted into the atmosphere | Value | 0.00 | 0.00 | 1831.00 |
Date | May 25, 2022 | January 15, 2024 | May 31, 2028 | |
Comment |
Bill collection efficiency of PUB | Value | 0.00 | 0.00 | 68.00 |
Date | May 25, 2022 | January 15, 2024 | May 31, 2028 | |
Comment |
Citizen in the project areas satisfied with the sanitation service delivery | Value | 0.00 | 0.00 | 70.00 |
Date | May 25, 2022 | January 15, 2024 | May 31, 2028 | |
Comment |
Households with access to improved onsite sanitation | Value | 0.00 | 0.00 | 1282.00 |
Date | May 25, 2022 | January 15, 2024 | May 31, 2028 | |
Comment |
Septic tanks emptied as per standard operating procedures | Value | 0.00 | 0.00 | 80.00 |
Date | May 25, 2022 | January 15, 2024 | May 31, 2028 | |
Comment |
People trained to improved hygiene and behavior and sanitation practices under the project | Value | 0.00 | 0.00 | 8293.00 |
Date | May 25, 2022 | January 15, 2024 | May 31, 2028 | |
Comment |
Annual Communication Workshops are organized | Value | No | No | Yes |
Date | May 25, 2022 | January 15, 2024 | May 31, 2028 | |
Comment |
Share of female staff in MISE’s Water & Sanitation Engineering Unit and PUB's Water Engineering Department | Value | 17.00 | 17.00 | 25.00 |
Date | May 25, 2022 | January 15, 2024 | May 31, 2028 | |
Comment |
A monitoring system is operational for Water Quality Monitoring | Value | No | No | Annual Review |
Date | May 25, 2022 | January 15, 2024 | May 31, 2028 | |
Comment |
Annual training plan agreed and implemented for training of MISE and PUB staff | Value | No | No | Yes |
Date | May 25, 2022 | January 15, 2024 | May 31, 2028 | |
Comment |