Financier | Commitments |
---|---|
IDA Credit | 140.00 |
P176543
Closed
Siddhartha Raja
Nepal
December 17, 2021
(as of board presentation)
June 16, 2022
March 15, 2023
US$ 180.00 million
National Information Technology Center,Nepal Telecommunications Authority,Ministry of Communications and IT,Department of Information Technology
2022
US$ 140.00 million
N/A
February 27, 2024
May 31, 2024
Yes
BANK APPROVED
Financier | Commitments |
---|---|
IDA Credit | 140.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 140.00 |
IBRD + IDA Commitment | 140.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 180.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Mar 25, 2024 | IDA-71440 | Loan Cancel | 138,128,560.00 |
Jun 16, 2022 | IDA-71440 | Loan Commitment | 140,000,000.00 |
Name | Review | Date |
---|---|---|
Project Management | Unsatisfactory | 2024-03-05 |
Progress towards achievement of PDO | Unsatisfactory | 2024-03-05 |
Procurement | Unsatisfactory | 2024-03-05 |
Financial Management | Unsatisfactory | 2024-03-05 |
Monitoring and Evaluation | Unsatisfactory | 2024-03-05 |
Overall Implementation Progress (IP) | Unsatisfactory | 2024-03-05 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
People provided with access to broadband services | Value | 0.00 | 0.00 | 1000000.00 |
Date | March 18, 2022 | February 27, 2024 | December 31, 2027 | |
Comment |
New digital government services available to the public, under the Project | Value | 0.00 | 0.00 | 20.00 |
Date | March 18, 2022 | February 27, 2024 | December 31, 2027 | |
Comment |
Beneficiaries of the digital skills development program who report being employed or in higher education | Value | 0.00 | 0.00 | 80.00 |
Date | March 18, 2022 | February 27, 2024 | December 31, 2027 | |
Comment |
Share among female inhabitants of Project areas | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Among female beneficiaries | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Share among inhabitants of rural municipalities | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Among beneficiaries who are persons with disabilities | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Participants in skills development securing new income or employment opportunities after completing the digital skills training supported by the Project | Value | 0.00 | 0.00 | 80.00 |
Date | July 1, 2022 | February 27, 2024 | December 31, 2027 | |
Comment |
Installed IT equipment that is certified as energy efficient | Value | 0.00 | 0.00 | 90.00 |
Date | March 18, 2022 | February 27, 2024 | December 31, 2027 | |
Comment |
Reduction in price of international IP transit services | Value | 0.00 | 0.00 | 33.00 |
Date | March 18, 2022 | February 27, 2024 | December 31, 2027 | |
Comment |
Digital government functions and services using data centers supported by the Project | Value | 0.00 | 0.00 | 40.00 |
Date | March 18, 2022 | February 27, 2024 | December 31, 2027 | |
Comment |
Share of whom are female | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Citizen engagement: Skills program participants expressing satisfaction with the activities under Subcomponent 2.2 | Value | 0.00 | 0.00 | 80.00 |
Date | March 18, 2022 | February 27, 2024 | December 31, 2027 | |
Comment |
Citizen engagement: People accessing new e-services supported through the Project and reporting satisfaction | Value | 0.00 | 0.00 | 80.00 |
Date | March 18, 2022 | February 27, 2024 | December 31, 2027 | |
Comment |
Participants establishing a startup after completing entrepreneurship activities supported by the project | Value | 0.00 | 0.00 | 80.00 |
Date | July 1, 2022 | February 27, 2024 | December 31, 2027 | |
Comment |
Of which, share among females | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Share of whom are female | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Citizen engagement: Startups reporting satisfaction with incubation and acceleration services received under Subcomponent 2.3 | Value | 0.00 | 0.00 | 80.00 |
Date | March 18, 2022 | February 27, 2024 | December 31, 2027 | |
Comment |
Share among female owned or managed startups | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
PCM indicator: Private capital attracted into rural broadband under Subcomponent 1.1 | Value | 0.00 | 0.00 | 40000000.00 |
Date | March 18, 2022 | February 27, 2024 | December 31, 2027 | |
Comment |
People trained through digital literacy programs | Value | 0.00 | 0.00 | 10.00 |
Date | March 18, 2022 | February 27, 2024 | December 31, 2027 | |
Comment |
Digital signatures issued in Nepal | Value | 5.00 | 6.70 | 20.00 |
Date | March 18, 2022 | February 27, 2024 | December 31, 2027 | |
Comment |
Citizen engagement: Grievances registered that receive an adequate response within 30 days | Value | 0.00 | 0.00 | 80.00 |
Date | March 18, 2022 | February 27, 2024 | December 31, 2027 | |
Comment |
Citizen engagement: Beneficiaries satisfied with access to and quality of broadband services | Value | 0.00 | 0.00 | 80.00 |
Date | March 18, 2022 | February 27, 2024 | December 31, 2027 | |
Comment |
Cybersecurity Center established and operational with staff in place and procedures published in a format that is readily availableto the public and industry | Value | No | No | Yes |
Date | March 18, 2022 | February 27, 2024 | December 31, 2027 | |
Comment |
Share of whom are female | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Installed telecommunications equipment that is certified as energy efficient | Value | 0.00 | 0.00 | 90.00 |
Date | March 18, 2022 | February 27, 2024 | December 31, 2027 | |
Comment |