Second Solomon Islands Roads and Aviation Project

Abstract*

The development objective of Second Solomon Islands Roads and Aviation Project is to improve the climate resilience and safety of the recipient's road and aviation sectors, and in case of an eligible crisis or emergency, respond promptly and effectively to it. This project has four components. 1) The first component, Climate Resilience and Safety Investments in the Aviation Sector, has the following sub-components: (i) Honiara Airport Infrastructure...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To improve the climate resilience and safety of the Recipient's road and aviation sectors, and in case of an Eligible Crisis or Emergency, respond promptly and effectively to it.

Key Details

Project Details

  • P176548

  • Active

  • Naoki Kakuta , Keelye Hanmer

  • Solomon Islands

  • Solomon Islands

  • (as of board presentation)

    June 1, 2022

  • US$ 89.21 million

  • Ministry of Infrastructure Development,Ministry of Communication and Aviation

  • June 27, 2024

  • June 30, 2029

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 67.69
IDA Grant 21.52

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 89.21
IBRD + IDA Commitment 89.21
Lending Instrument
Grant Amount N/A
Total Project Cost** 89.21

Summary Status of World Bank Financing (US$ Millions) as of December 31, 2024

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of December 31, 2024

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Oct 1, 2023 IDA-71100 Int Charges 26,506.68
Jan 10, 2024 IDA-71100 Loan Disb 761,213.40
Nov 10, 2023 IDA-71100 Loan Disb 4,475,062.50
Dec 1, 2023 IDA-71100 Loan Disb 42,588.44
Apr 30, 2024 IDA-71100 Loan Disb 2,723,781.00
Mar 21, 2024 IDA-71100 Loan Disb 223,886.30
Jan 31, 2024 IDA-71100 Loan Disb 3,743,043.50
May 7, 2024 IDA-71100 Loan Disb 398,244.62
Mar 14, 2024 IDA-E0340 Loan Disb 310,931.10
Jun 14, 2024 IDA-E0340 Loan Disb 223,886.30
Mar 14, 2024 IDA-E0340 Loan Disb 163,167.81
May 7, 2024 IDA-E0340 Loan Disb 90,183.30
Jul 22, 2024 IDA-E0340 Loan Disb 136,979.48
Jun 1, 2022 IDA-E0340 Loan Commitment 21,520,000.00
Jun 1, 2022 IDA-71100 Loan Commitment 67,690,000.00
Dec 19, 2022 IDA-E0340 Loan Disb 1,471,200.00
Jun 9, 2023 IDA-E0340 Loan Disb 1,331,490.20
Jul 14, 2023 IDA-E0340 Loan Disb 113,564.26
May 12, 2023 IDA-E0340 Loan Disb 68,594.02
Jun 28, 2023 IDA-E0340 Loan Disb 223,886.30
Sep 15, 2023 IDA-E0340 Loan Disb 127,570.02
Dec 13, 2023 IDA-E0340 Loan Disb 313,440.80
Dec 1, 2023 IDA-E0340 Loan Disb 96,157.80
Sep 28, 2023 IDA-E0340 Loan Disb 72,691.94
Apr 2, 2024 IDA-71100 Int Charges 47,352.70
Apr 2, 2024 IDA-71100 Int Charges 47,352.70
Aug 7, 2024 IDA-71100 Loan Disb 2,775,704.00
Jul 22, 2024 IDA-71100 Loan Disb 116,206.97
Feb 26, 2024 IDA-71100 Loan Disb 25,384.45
Apr 1, 2023 IDA-71100 Int Charges 5,047.63
Apr 1, 2023 IDA-71100 Int Charges 5,047.63
Jan 25, 2023 IDA-71100 Loan Disb 3,666,000.00
Jul 14, 2023 IDA-71100 Loan Disb 285,832.88
Mar 28, 2023 IDA-71100 Loan Disb 3,454,273.00
Apr 1, 2024 IDA-71100 Int Charges 502.05
Apr 1, 2024 IDA-71100 Int Charges 502.05
Apr 11, 2024 IDA-71100 Loan Disb 2,799,694.80
Oct 1, 2023 IDA-71100 Int Charges 188.09
Oct 1, 2023 IDA-71100 Int Charges 188.09
Oct 1, 2023 IDA-71100 Int Charges 26,506.68
Aug 20, 2024 IDA-71100 Loan Disb 2,388,287.00
Oct 3, 2023 IDA-71100 Loan Disb 333,019.16

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Monitoring and Evaluation Satisfactory 2024-11-20
Overall Implementation Progress (IP) Satisfactory 2024-11-20
Progress towards achievement of PDO Satisfactory 2024-11-20
Procurement Satisfactory 2024-11-20
Financial Management Satisfactory 2024-11-20
Project Management Satisfactory 2024-11-20

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Bridges with climate resilience and safety measures constructed and in useValue0.000.004.00
    DateJanuary 31, 2022December 31, 2023June 30, 2029
    Comment
  • Roads with climate resilience and safety measures constructed and in useValue0.000.009.90
    DateJanuary 31, 2022December 31, 2023June 30, 2029
    Comment
  • Airport or airfield runway with climate resilience and safety measures constructed and in useValue0.000.002.00
    DateJanuary 31, 2022December 31, 2023June 30, 2029
    Comment
  • Modernization of air traffic and aviation safety managementValueNo ADS-B or VSATNo ADS-B or VSATADS-B and VSAT fully operational
    DateJanuary 31, 2022December 31, 2023June 30, 2029
    Comment
  • Enhanced climate resilience and operational safety at regional airports under preventative and corrective airport maintenance program for airport equipment and facilitiesValueNoNoYes
    DateJanuary 31, 2022December 31, 2023June 30, 2029
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Honiara Airport rescue fire service vehicle station constructed and code of conduct establishedValueNoNoYes
    DateJanuary 31, 2022December 31, 2023June 30, 2029
    Comment
  • Consultancy for detailed design and supervision of building and civil works providedValueNo contract with the consulting firm in placeThe Design Reports for most of all the key infrastSupervision of building and civil works completed
    DateJanuary 31, 2022December 31, 2023June 30, 2029
    Comment
  • Honiara Airport Automated Weather Observation System (AWOS) installed and operationalValueNoNoYes
    DateJanuary 31, 2022December 31, 2023June 30, 2029
    Comment
  • National Airports Development Plan preparedValueNoNoYes
    DateJanuary 31, 2022December 31, 2023June 30, 2029
    Comment
  • Honiara and Munda Airports air traffic control (ATC) towers constructed and operationalValue0.000.002.00
    DateJanuary 31, 2022December 31, 2023June 30, 2029
    Comment
  • Successful implementation of agreed training plan for MCA and Solomon AirlinesValueNo trainingTraining plan preparedTraining plan completed
    DateJanuary 31, 2022February 15, 2024June 30, 2029
    Comment
  • People with enhanced access to transportation servicesValue0.000.00120000.00
    DateJanuary 31, 2022December 31, 2023June 30, 2029
    Comment
  • Regional Airport Asset Maintenance Contract in placeValueNoNoYes
    DateJanuary 31, 2022December 31, 2023June 30, 2029
    Comment
  • Women employed in technical or management positions within MCAValue20.0033.0040.00
    DateJanuary 31, 2022December 31, 2023June 30, 2029
    Comment
  • People with enhanced access to transportation services - Roads/HighwaysValue0.000.00120000.00
    DateJanuary 31, 2022December 31, 2023June 30, 2029
    Comment
  • Road safety audits completedValue0.001.002.00
    DateJanuary 31, 2022December 31, 2023June 30, 2029
    Comment
  • Roads rehabilitated, which are equipped with gender responsive road safety infrastructureValue0.000.00100.00
    DateJanuary 31, 2022December 31, 2023June 30, 2029
    Comment
  • Road network criticality and vulnerability assessments and sustainable road financing strategy completed and in useValueRoad network criticality and vulnerability assessmRoad network criticality and vulnerability assessmRoad network criticality and vulnerability assessm
    DateJanuary 31, 2022December 31, 2023June 30, 2029
    Comment
  • Grievance registered related to delivery of project benefits that are addressedValue0.000.0075.00
    DateJanuary 31, 2022December 31, 2023June 30, 2029
    Comment
  • Road upgraded using participatory design approachesValue0.000.009.90
    DateJanuary 31, 2022December 31, 2023June 30, 2029
    Comment