Financier | Commitments |
---|---|
IDA Grant | 592.00 |
IDA Grant | 592.00 |
P176570
Active
Avril Kaplan , Arsala Deane, Naif Abu-Lohom
United Nations Children's Fund,United Nations Office for Project Services,World Health Organization,United Nations Children's Fund,United Nations Office for Project Services,World Health Organization
Yemen, Republic of
May 31, 2021
(as of board presentation)
June 30, 2021
September 27, 2021
US$ 150.00 million
United Nations Children's Fund,United Nations Office for Project Services,World Health Organization,United Nations Children's Fund,United Nations Office for Project Services,World Health Organization
2021
US$ 592.00 million
N/A
Substantial
December 31, 2026
No
BANK APPROVED
June 11, 2024
Financier | Commitments |
---|---|
IDA Grant | 592.00 |
IDA Grant | 592.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 592.00 |
IBRD + IDA Commitment | 592.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 150.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jun 30, 2021 | IDA-D8820 | Loan Commitment | 45,460,000.00 |
Jul 25, 2022 | IDA-E1170 | Loan Commitment | 45,460,000.00 |
Jul 25, 2022 | IDA-E1180 | Loan Commitment | 30,000,000.00 |
Jul 25, 2022 | IDA-E1190 | Loan Commitment | 74,540,000.00 |
Sep 22, 2023 | IDA-E2330 | Loan Commitment | 24,000,000.00 |
Sep 22, 2023 | IDA-E2340 | Loan Commitment | 48,000,000.00 |
Sep 22, 2023 | IDA-E2350 | Loan Commitment | 78,000,000.00 |
Dec 30, 2021 | IDA-D8800 | Loan Disb | 44,032,500.00 |
Aug 26, 2022 | IDA-D8820 | Loan Disb | 1,391.25 |
Aug 23, 2022 | IDA-D8810 | Loan Disb | 5,024,220.00 |
Feb 15, 2022 | IDA-D8820 | Loan Disb | 15,000,000.00 |
May 24, 2022 | IDA-D8820 | Loan Disb | 8,435,573.00 |
May 4, 2022 | IDA-D8820 | Loan Disb | 10,000,000.00 |
Nov 9, 2021 | IDA-D8810 | Loan Disb | 10,436,203.00 |
Nov 1, 2021 | IDA-D8820 | Loan Disb | 10,000,000.00 |
Oct 24, 2022 | IDA-E1180 | Loan Disb | 8,904,014.00 |
Sep 13, 2022 | IDA-E1170 | Loan Disb | 25,000,000.00 |
Oct 7, 2022 | IDA-E1190 | Loan Disb | 32,896,304.00 |
Sep 20, 2022 | IDA-D8800 | Loan Disb | 26,062,284.00 |
Jun 8, 2023 | IDA-E1190 | Loan Disb | 39,224.75 |
Mar 8, 2023 | IDA-D8800 | Loan Disb | 18,727.54 |
Feb 17, 2023 | IDA-E1170 | Loan Disb | 19,390,910.00 |
Mar 10, 2023 | IDA-E1190 | Loan Disb | 39,311,500.00 |
Mar 2, 2023 | IDA-D8810 | Loan Disb | 6,135,460.00 |
Aug 22, 2023 | IDA-D8810 | Loan Disb | 6,135,500.00 |
Aug 22, 2023 | IDA-E1180 | Loan Disb | 19,690,682.00 |
Dec 22, 2023 | IDA-E2330 | Loan Disb | 15,330,520.00 |
Nov 9, 2023 | IDA-E2350 | Loan Disb | 67,256,944.00 |
Oct 26, 2023 | IDA-E2340 | Loan Disb | 30,000,000.00 |
Mar 20, 2024 | IDA-E2340 | Loan Disb | 17,099,850.00 |
Mar 13, 2024 | IDA-E2350 | Loan Disb | 9,356,880.00 |
Apr 22, 2024 | IDA-D8810 | Loan Disb | 424,592.00 |
Apr 22, 2024 | IDA-E1180 | Loan Disb | 699,270.00 |
Jun 30, 2021 | IDA-D8800 | Loan Commitment | 74,540,000.00 |
Jun 30, 2021 | IDA-D8810 | Loan Commitment | 30,000,000.00 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2025-03-07 |
Project Management | Satisfactory | 2025-03-07 |
Monitoring and Evaluation | Satisfactory | 2025-03-07 |
Overall Implementation Progress (IP) | Satisfactory | 2025-03-07 |
Progress towards achievement of PDO | Satisfactory | 2025-03-07 |
Monitoring and Evaluation | Satisfactory | 2025-03-07 |
Project Management | Satisfactory | 2025-03-07 |
Procurement | Satisfactory | 2025-03-07 |
Financial Management | Moderately Satisfactory | 2025-03-07 |
Overall Implementation Progress (IP) | Satisfactory | 2025-03-07 |
Progress towards achievement of PDO | Satisfactory | 2025-03-07 |
Project Management | Satisfactory | 2025-03-07 |
Monitoring and Evaluation | Satisfactory | 2025-03-07 |
Overall Implementation Progress (IP) | Satisfactory | 2025-03-07 |
Progress towards achievement of PDO | Satisfactory | 2025-03-07 |
Monitoring and Evaluation | Satisfactory | 2025-03-07 |
Project Management | Satisfactory | 2025-03-07 |
Procurement | Satisfactory | 2025-03-07 |
Financial Management | Moderately Satisfactory | 2025-03-07 |
Overall Implementation Progress (IP) | Satisfactory | 2025-03-07 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Beneficiaries of health, nutrition and/or population services provided through the project | Value | 0.00 | 14103735.00 | 18944654.00 |
Date | April 30, 2021 | March 29, 2024 | June 30, 2025 | |
Comment |
People provided with access to improved water and sanitation services in selected urban and rural areas | Value | 0.00 | 963006.00 | 2000000.00 |
Date | April 30, 2021 | April 29, 2024 | June 30, 2025 | |
Comment |
Beneficiaries of health, nutrition, and/or population services provided through the project, of which female | Value | 0.00 | 7468348.00 | 9997652.00 |
Date | April 30, 2021 | March 29, 2024 | June 30, 2025 | |
Comment |
People provided with access to improved water and sanitation services in selected urban and rural areas - female | Value | 0.00 | 0.00 | 48.00 |
Date | ||||
Comment |
Beneficiaries of health, nutrition, and/or population services provided through the project - of which children under 5 | Value | 0.00 | 5636888.00 | 7420982.00 |
Date | April 30, 2021 | March 29, 2024 | June 30, 2025 | |
Comment |
Percentage of beneficiaries of health, nutrition, and/or population services provided through the project - IDPs | Value | 0.00 | 0.00 | 10.00 |
Date | ||||
Comment |
Beneficiaries of health, nutrition and/or population services provided through the project | Value | 0.00 | 14103735.00 | 18944654.00 |
Date | April 30, 2021 | March 29, 2024 | June 30, 2025 | |
Comment |
People provided with access to improved water and sanitation services in selected urban and rural areas | Value | 0.00 | 963006.00 | 2000000.00 |
Date | April 30, 2021 | April 29, 2024 | June 30, 2025 | |
Comment |
Beneficiaries of health, nutrition, and/or population services provided through the project, of which female | Value | 0.00 | 7468348.00 | 9997652.00 |
Date | April 30, 2021 | March 29, 2024 | June 30, 2025 | |
Comment |
People provided with access to improved water and sanitation services in selected urban and rural areas - female | Value | 0.00 | 0.00 | 48.00 |
Date | ||||
Comment |
Beneficiaries of health, nutrition, and/or population services provided through the project - of which children under 5 | Value | 0.00 | 5636888.00 | 7420982.00 |
Date | April 30, 2021 | March 29, 2024 | June 30, 2025 | |
Comment |
Percentage of beneficiaries of health, nutrition, and/or population services provided through the project - IDPs | Value | 0.00 | 0.00 | 10.00 |
Date | ||||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Local NGOs involved in service provision | Value | 0.00 | 10.00 | 12.00 |
Date | April 30, 2021 | March 29, 2024 | June 30, 2025 | |
Comment |
Number of outreach rounds conducted | Value | 0.00 | 45994.00 | 61736.00 |
Date | April 30, 2021 | March 29, 2024 | June 30, 2025 | |
Comment |
Beneficiaries satisfied with services provided | Value | 0.00 | 96.00 | 85.00 |
Date | April 30, 2021 | March 29, 2024 | June 30, 2025 | |
Comment |
Health facilities provided with equipment and medical/non-medical supplies | Value | 0.00 | 2616.00 | 2610.00 |
Date | April 30, 2021 | March 29, 2024 | June 30, 2025 | |
Comment |
Pregnant women receiving antenatal care during a visit to a health provider | Value | 0.00 | 832962.00 | 932242.00 |
Date | April 30, 2021 | March 29, 2024 | June 30, 2025 | |
Comment |
An action plan to follow up on the findings from TPM surveys is prepared and monitored | Value | No | No | Yes |
Date | ||||
Comment |
Health personnel receiving training | Value | 0.00 | 14810.00 | 15603.00 |
Date | April 30, 2021 | March 29, 2024 | June 30, 2025 | |
Comment |
Number of people receiving mental health and psychosocial support | Value | 0.00 | 205256.00 | 241077.00 |
Date | April 30, 2021 | March 29, 2024 | June 30, 2025 | |
Comment |
Number of facility-based nutrition sentinel sites | Value | 0.00 | 340.00 | 340.00 |
Date | April 30, 2021 | March 29, 2024 | June 30, 2025 | |
Comment |
Women receiving breastfeeding and complementary feeding counselling | Value | 0.00 | 1255046.00 | 1519360.00 |
Date | March 31, 2021 | March 29, 2024 | June 30, 2025 | |
Comment |
People receiving essential drugs for non-communicable diseases | Value | 0.00 | 158196.00 | 196365.00 |
Date | April 30, 2021 | March 29, 2024 | June 30, 2025 | |
Comment |
Training on good hygiene and sanitation practices to prevent the spread of diseases exacerbated by climate change | Value | No | Yes | Yes |
Date | April 30, 2021 | March 29, 2024 | June 30, 2025 | |
Comment |
Percentage of WASH focus groups attendees who were satisfied with the participatory approach in the planning process of the project | Value | 0.00 | 80.00 | 80.00 |
Date | April 30, 2021 | April 29, 2024 | June 30, 2025 | |
Comment |
New electronic integrated disease early warning system (eIDEWS) data collection sites established | Value | 1991.00 | 2379.00 | 2379.00 |
Date | April 30, 2021 | March 29, 2024 | June 30, 2025 | |
Comment |
Percentage of WASH focus groups attendees who were satisfied with the participatory approach in the planning process of the project- of which female | Value | 0.00 | 40.00 | 40.00 |
Date | April 30, 2021 | April 29, 2024 | June 30, 2025 | |
Comment |
People who have received essential health, nutrition, and population (HNP) services | Value | 0.00 | 8318318.00 | 10727911.00 |
Date | April 30, 2021 | March 29, 2024 | June 30, 2025 | |
Comment |
Number of people trained from government institutions to improving local WASH capacity at the institutional level | Value | 0.00 | 278.00 | 300.00 |
Date | April 30, 2021 | April 29, 2024 | June 30, 2025 | |
Comment |
People who have received essential health, nutrition, and population (HNP) services - Female (RMS requirement) | Value | 0.00 | 0.00 | 1800000.00 |
Date | ||||
Comment |
Schools with improved WASH facilities | Value | 0.00 | 0.00 | 30.00 |
Date | April 30, 2021 | April 29, 2024 | June 30, 2025 | |
Comment |
Number of children immunized | Value | 0.00 | 1491555.00 | 1651905.00 |
Date | April 30, 2021 | March 29, 2024 | June 30, 2025 | |
Comment |
Health care establishments with improved WASH facilities | Value | 0.00 | 0.00 | 20.00 |
Date | April 30, 2021 | April 29, 2024 | June 30, 2025 | |
Comment |
Number of women and children who have received basic nutrition services | Value | 0.00 | 6292879.00 | 8350095.00 |
Date | April 30, 2021 | March 29, 2024 | June 30, 2025 | |
Comment |
IDPs benefiting from emergency WASH response (rural and urban) | Value | 0.00 | 3146.00 | 7500.00 |
Date | April 30, 2021 | April 29, 2024 | June 30, 2025 | |
Comment |
Number of deliveries attended by skilled health personnel | Value | 0.00 | 533884.00 | 724565.00 |
Date | April 30, 2021 | March 29, 2024 | June 30, 2025 | |
Comment |
People who have access to water monitored for quality using critical parameters related to cholera and water borne diseases | Value | 0.00 | 121938.00 | 200000.00 |
Date | April 30, 2021 | April 29, 2024 | June 30, 2025 | |
Comment |
Water and sanitation facilities using solar power generation | Value | 0.00 | 7.00 | 30.00 |
Date | May 20, 2022 | April 29, 2024 | June 30, 2025 | |
Comment |
Percentage of severe acute malnutrition cases cured | Value | 90.00 | 90.00 | 90.00 |
Date | July 28, 2023 | March 29, 2024 | June 30, 2025 | |
Comment |
Energy generation supported through the Project | Value | 0.00 | 2840.00 | 5000.00 |
Date | June 20, 2022 | April 29, 2024 | June 30, 2025 | |
Comment |
People provided with restored access to rehabilitated water supply services | Value | 0.00 | 542865.00 | 1025000.00 |
Date | April 30, 2021 | April 29, 2024 | June 30, 2025 | |
Comment |
People provided with restored access to rehabilitated water supply services - female | Value | 0.00 | 240062.00 | 0.00 |
Date | ||||
Comment |
People provided with restored access to rehabilitated water supply services - rural | Value | 0.00 | 99410.00 | 150000.00 |
Date | April 30, 2021 | April 29, 2024 | June 30, 2025 | |
Comment |
People provided with restored access to rehabilitated water supply services - urban | Value | 0.00 | 443455.00 | 875000.00 |
Date | April 30, 2021 | April 29, 2024 | June 30, 2025 | |
Comment |
People provided with restored access to rehabilitated sanitation services | Value | 0.00 | 420141.00 | 975000.00 |
Date | April 30, 2021 | April 29, 2024 | June 30, 2025 | |
Comment |
People provided with restored access to rehabilitated sanitation services - female | Value | 0.00 | 187329.00 | 0.00 |
Date | ||||
Comment |
People provided with restored access to rehabilitated sanitation services - rural | Value | 0.00 | 60360.00 | 75000.00 |
Date | April 30, 2021 | April 29, 2024 | June 30, 2025 | |
Comment |
People provided with restored access to rehabilitated sanitation services - urban | Value | 0.00 | 359781.00 | 900000.00 |
Date | April 30, 2021 | April 29, 2024 | June 30, 2025 | |
Comment |
Local NGOs involved in service provision | Value | 0.00 | 10.00 | 12.00 |
Date | April 30, 2021 | March 29, 2024 | June 30, 2025 | |
Comment |
Number of outreach rounds conducted | Value | 0.00 | 45994.00 | 61736.00 |
Date | April 30, 2021 | March 29, 2024 | June 30, 2025 | |
Comment |
Beneficiaries satisfied with services provided | Value | 0.00 | 96.00 | 85.00 |
Date | April 30, 2021 | March 29, 2024 | June 30, 2025 | |
Comment |
Health facilities provided with equipment and medical/non-medical supplies | Value | 0.00 | 2616.00 | 2610.00 |
Date | April 30, 2021 | March 29, 2024 | June 30, 2025 | |
Comment |
Pregnant women receiving antenatal care during a visit to a health provider | Value | 0.00 | 832962.00 | 932242.00 |
Date | April 30, 2021 | March 29, 2024 | June 30, 2025 | |
Comment |
An action plan to follow up on the findings from TPM surveys is prepared and monitored | Value | No | No | Yes |
Date | ||||
Comment |
Health personnel receiving training | Value | 0.00 | 14810.00 | 15603.00 |
Date | April 30, 2021 | March 29, 2024 | June 30, 2025 | |
Comment |
Number of people receiving mental health and psychosocial support | Value | 0.00 | 205256.00 | 241077.00 |
Date | April 30, 2021 | March 29, 2024 | June 30, 2025 | |
Comment |
Number of facility-based nutrition sentinel sites | Value | 0.00 | 340.00 | 340.00 |
Date | April 30, 2021 | March 29, 2024 | June 30, 2025 | |
Comment |
Women receiving breastfeeding and complementary feeding counselling | Value | 0.00 | 1255046.00 | 1519360.00 |
Date | March 31, 2021 | March 29, 2024 | June 30, 2025 | |
Comment |
People receiving essential drugs for non-communicable diseases | Value | 0.00 | 158196.00 | 196365.00 |
Date | April 30, 2021 | March 29, 2024 | June 30, 2025 | |
Comment |
Training on good hygiene and sanitation practices to prevent the spread of diseases exacerbated by climate change | Value | No | Yes | Yes |
Date | April 30, 2021 | March 29, 2024 | June 30, 2025 | |
Comment |
Percentage of WASH focus groups attendees who were satisfied with the participatory approach in the planning process of the project | Value | 0.00 | 80.00 | 80.00 |
Date | April 30, 2021 | April 29, 2024 | June 30, 2025 | |
Comment |
New electronic integrated disease early warning system (eIDEWS) data collection sites established | Value | 1991.00 | 2379.00 | 2379.00 |
Date | April 30, 2021 | March 29, 2024 | June 30, 2025 | |
Comment |
Percentage of WASH focus groups attendees who were satisfied with the participatory approach in the planning process of the project- of which female | Value | 0.00 | 40.00 | 40.00 |
Date | April 30, 2021 | April 29, 2024 | June 30, 2025 | |
Comment |
People who have received essential health, nutrition, and population (HNP) services | Value | 0.00 | 8318318.00 | 10727911.00 |
Date | April 30, 2021 | March 29, 2024 | June 30, 2025 | |
Comment |
Number of people trained from government institutions to improving local WASH capacity at the institutional level | Value | 0.00 | 278.00 | 300.00 |
Date | April 30, 2021 | April 29, 2024 | June 30, 2025 | |
Comment |
People who have received essential health, nutrition, and population (HNP) services - Female (RMS requirement) | Value | 0.00 | 0.00 | 1800000.00 |
Date | ||||
Comment |
Schools with improved WASH facilities | Value | 0.00 | 0.00 | 30.00 |
Date | April 30, 2021 | April 29, 2024 | June 30, 2025 | |
Comment |
Number of children immunized | Value | 0.00 | 1491555.00 | 1651905.00 |
Date | April 30, 2021 | March 29, 2024 | June 30, 2025 | |
Comment |
Health care establishments with improved WASH facilities | Value | 0.00 | 0.00 | 20.00 |
Date | April 30, 2021 | April 29, 2024 | June 30, 2025 | |
Comment |
Number of women and children who have received basic nutrition services | Value | 0.00 | 6292879.00 | 8350095.00 |
Date | April 30, 2021 | March 29, 2024 | June 30, 2025 | |
Comment |
IDPs benefiting from emergency WASH response (rural and urban) | Value | 0.00 | 3146.00 | 7500.00 |
Date | April 30, 2021 | April 29, 2024 | June 30, 2025 | |
Comment |
Number of deliveries attended by skilled health personnel | Value | 0.00 | 533884.00 | 724565.00 |
Date | April 30, 2021 | March 29, 2024 | June 30, 2025 | |
Comment |
People who have access to water monitored for quality using critical parameters related to cholera and water borne diseases | Value | 0.00 | 121938.00 | 200000.00 |
Date | April 30, 2021 | April 29, 2024 | June 30, 2025 | |
Comment |
Water and sanitation facilities using solar power generation | Value | 0.00 | 7.00 | 30.00 |
Date | May 20, 2022 | April 29, 2024 | June 30, 2025 | |
Comment |
Percentage of severe acute malnutrition cases cured | Value | 90.00 | 90.00 | 90.00 |
Date | July 28, 2023 | March 29, 2024 | June 30, 2025 | |
Comment |
Energy generation supported through the Project | Value | 0.00 | 2840.00 | 5000.00 |
Date | June 20, 2022 | April 29, 2024 | June 30, 2025 | |
Comment |
People provided with restored access to rehabilitated water supply services | Value | 0.00 | 542865.00 | 1025000.00 |
Date | April 30, 2021 | April 29, 2024 | June 30, 2025 | |
Comment |
People provided with restored access to rehabilitated water supply services - female | Value | 0.00 | 240062.00 | 0.00 |
Date | ||||
Comment |
People provided with restored access to rehabilitated water supply services - rural | Value | 0.00 | 99410.00 | 150000.00 |
Date | April 30, 2021 | April 29, 2024 | June 30, 2025 | |
Comment |
People provided with restored access to rehabilitated water supply services - urban | Value | 0.00 | 443455.00 | 875000.00 |
Date | April 30, 2021 | April 29, 2024 | June 30, 2025 | |
Comment |
People provided with restored access to rehabilitated sanitation services | Value | 0.00 | 420141.00 | 975000.00 |
Date | April 30, 2021 | April 29, 2024 | June 30, 2025 | |
Comment |
People provided with restored access to rehabilitated sanitation services - female | Value | 0.00 | 187329.00 | 0.00 |
Date | ||||
Comment |
People provided with restored access to rehabilitated sanitation services - rural | Value | 0.00 | 60360.00 | 75000.00 |
Date | April 30, 2021 | April 29, 2024 | June 30, 2025 | |
Comment |
People provided with restored access to rehabilitated sanitation services - urban | Value | 0.00 | 359781.00 | 900000.00 |
Date | April 30, 2021 | April 29, 2024 | June 30, 2025 | |
Comment |