Financier | Commitments |
---|---|
Borrower/Recipient | 995.60 |
IDA Credit | 50.00 |
P176616
Closed
Karthika Radhakrishnan , Mohan Aryal, Maya Sherpa
Nepal Ministry of Education, Science and Technology
April 7, 2021
(as of board presentation)
July 8, 2021
N/A
US$ 1045.60 million
Ministry of Education, Science and Technology
2022
US$ 50.00 million
N/A
September 6, 2022
July 16, 2022
No
BANK APPROVED
Financier | Commitments |
---|---|
Borrower/Recipient | 995.60 |
IDA Credit | 50.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 50.00 |
IBRD + IDA Commitment | 50.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 1045.60 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Percentage of students displaying grade-level competency on core subjects in Grade 8 measured through NASA | Value | - | The NASA for Grade 8 was held but the analysis s p | Year 4: Second competency-based test conducted for |
Date | February 28, 2017 | November 30, 2020 | July 15, 2020 | |
Comment |
NER in basic and secondary education in 15 most disadvantaged districts as ranked in the equity index (disaggregated by gender) | Value | Basic:All: 85.1Boys: 86.5Girls 83.6Secondary: | Basic: Total 89.2; Girls 88.1; Boys: 90.3Seconda | BasicAll: 91.4Boys: 92.8.Girls:90.0Secondary |
Date | July 15, 2016 | November 30, 2020 | July 15, 2021 | |
Comment |
Percentage of funds disbursed to schools in compliance with eligibility and utilization guidelines | Value | 0.00 | 93.60 | 95.00 |
Date | July 15, 2016 | November 30, 2020 | July 15, 2021 | |
Comment |
Percentage of grade 3 students reading grade-level text with proficiency | Value | Total: 12.8; Boys: 11.3; Girls: 14 | Final report is pending | Total: 15 (disaggregated by boys and girls) |
Date | June 30, 2016 | November 30, 2020 | July 15, 2020 | |
Comment |
Enhanced teacher time-spent-teaching (TST) operational | Value | Limited teacher accountability (low levels of TST) | An achievement report of 200 local governments tha | TST monitoring system operational in 229 LGs. |
Date | July 15, 2016 | November 30, 2020 | July 16, 2022 | |
Comment |
Survival rate to Grade 8 and to Grade 12 (disaggregated by gender) | Value | Grade 8 All: 76.6 percentBoys: 75.9 percentGirl | Grade 8 All: 79.3 Girls: 79.6 Grade 12: All: | Grade 8 All: 92 Boys: 91.2 Girls: 93 Grade 12 |
Date | July 15, 2016 | November 30, 2020 | July 15, 2021 | |
Comment |
Number of LGs that have implemented catch-up program | Value | N/A | N/A | 400 |
Date | April 1, 2021 | April 1, 2021 | July 16, 2022 | |
Comment |
Number of LGs that have implemented alternative mode of learning during COVID-19 schools closures | Value | N/A | Data collection ongoing | 171 |
Date | March 15, 2020 | April 1, 2021 | July 16, 2022 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Improved ECED and EGRP | Value | n.a. | The year 3 and 4 status has been delayed due to CO | Number of schools meeting minimum standards for EC |
Date | July 15, 2016 | November 30, 2020 | July 15, 2021 | |
Comment |
Strengthened governance, fiduciary management, data systems, and institutional capacity for results-based program implementation | Value | Enhanced fiduciary system is not in place.85% ac | There is no target for Year 4 | a) Percentage of audit observation of SSDP no more |
Date | July 15, 2016 | November 30, 2020 | July 15, 2021 | |
Comment |
Number of out-of-school children brought to schools or LCs | Value | - | The Year 4 target of 250,000 OOSC brought to schoo | |
Date | February 28, 2017 | November 30, 2020 | July 16, 2022 | |
Comment |
Number of basic education level (pre-primary to Grade 8) students who can access inclusive distance learning supported through the project | Value | 0 | The Project Implementation Manual is currently bei | 1,500,000 |
Date | March 31, 2020 | November 30, 2020 | December 31, 2021 | |
Comment |
National Curriculum Framework (NCF) revised and implemented | Value | Secondary curriculum does not adequately serve the | The target for Year 4 has been partially achieved. | Grade 9 new curriculum implemented |
Date | July 15, 2016 | November 30, 2020 | July 16, 2022 | |
Comment |
Enhancing feedback mechanism to schools | Value | School profile cards not used for conducting socia | Year-three target: "District and school profile ca | School profiles from EMIS generated and used in so |
Date | July 15, 2016 | September 9, 2019 | July 15, 2021 | |
Comment |
Implementation of pro-poor targeted scholarships (PPTS) and pro-science targeted scholarships (PSS) | Value | Scholarship schemes are not pro-poor targetedSha | Year 3 target of PPTS and PPS implemented in all d | (a) Standards, operational policies and guidelines |
Date | July 15, 2016 | November 30, 2020 | July 16, 2022 | |
Comment |
Assessment and examination system reforms undertaken to improve teaching and learning | Value | Letter grading and single-subject certification in | There is no Year 4 target for this indicator. Year | (a) MOEST approves a framework for conducting the |
Date | July 15, 2016 | November 30, 2020 | July 16, 2022 | |
Comment |
Number of secondary schools receiving pro-science grants to offer science stream | Value | Low enrolment of students in science streams | 322 (model schools) | 500 |
Date | July 15, 2016 | November 30, 2020 | July 16, 2022 | |
Comment |
Number of basic education teachers in community schools trained in (i) addressing learning gaps; and (ii) digital skills | Value | 0 | The Project Implementation Manual is currently bei | 15,000 |
Date | March 31, 2020 | November 30, 2020 | December 31, 2021 | |
Comment |
Improved teacher management and accountability | Value | Number of teachers identified nationally for redep | The end-of-project for this indicator was reported | Number of teachers to be redeployed reduced by 60% |
Date | July 15, 2016 | November 30, 2020 | July 16, 2022 | |
Comment |
Share of students enrolled in science subjects in Grades 11 and 12 | Value | Low enrolment of students in science streams | Data was not available during the JRM and will be | 15 |
Date | July 15, 2016 | November 30, 2020 | July 16, 2022 | |
Comment |
Number of grade - specific lessons supported through the project broacasted | Value | 0 | The Project Implementation Manual is currently bei | 3,000 |
Date | March 31, 2020 | November 30, 2020 | December 31, 2021 | |
Comment |
Number of schools receiving block grants | Value | Serious accountability problems in the current mod | 262 schools received block grants against the targ | 700 |
Date | July 15, 2016 | November 30, 2020 | July 16, 2022 | |
Comment |
Students benefiting from direct interventions to enhance learning | Value | 0.00 | 6781876.00 | 6781876.00 |
Date | July 15, 2016 | November 30, 2020 | July 16, 2022 | |
Comment |
Number of children from marginalized background/ with no access to media or internet provide with printed learning packs and materials. | Value | 0 | The Project Implementation Manual is currently bei | 190,000 |
Date | March 31, 2020 | November 30, 2020 | December 31, 2021 | |
Comment |
Number of schools implementing performance-based grants for meeting minimum accountability requirements | Value | Accountability and performance issues are hard to | 3010 community schools received performance grants | Performance based grants for schools implemented i |
Date | July 15, 2016 | November 30, 2020 | July 15, 2022 | |
Comment |
Number of children provided access to programs and sensitization campaigns to minimize the negative impacts of school closures, with a focus on girls | Value | 0 | The Project Implementation Manual is currently bei | 1,500,000 |
Date | March 31, 2020 | November 30, 2020 | December 31, 2021 | |
Comment |
Students benefiting from direct interventions to enhance learning - Female | Value | 0.00 | 3345344.00 | 0.00 |
Date | ||||
Comment |
Large-scale primary/secondary learning assessments completed | Value | 0.00 | 3.00 | 3.00 |
Date | July 15, 2017 | November 30, 2020 | July 15, 2021 | |
Comment |
Learning portal functional | Value | Learning portal developed | The learning portal is functional. | Learning portal functional |
Date | March 31, 2020 | November 30, 2020 | December 31, 2021 | |
Comment |
Number of children supported with accelerated learning program to mitigate the learning loss during school closure | Value | 0 | NA | 400,000 |
Date | March 31, 2020 | December 31, 2021 | December 31, 2021 | |
Comment |
Number of grant-supported schools reopened | Value | 0 | The Project Implementation Manual is currently bei | 3000 |
Date | March 31, 2020 | November 30, 2020 | December 31, 2021 | |
Comment |
Number of of grant-supported schools equipped with minimum hygiene standards for prevention of CoVID 19 | Value | 0 | The Project Implementation Manual is currently bei | 3,000 |
Date | March 31, 2020 | November 30, 2020 | December 31, 2021 | |
Comment |
School reopening framework and distance learning guidelines disseminated to sub-national governments | Value | NA | The school reopening framework was developed, appr | School reopening framework and distance learning g |
Date | March 31, 2020 | November 30, 2020 | December 31, 2021 | |
Comment |
Project Implementation Manual developed | Value | NA | Project Implementation Manual is in the process of | Project Implementation Manual developed |
Date | March 31, 2020 | November 30, 2020 | December 31, 2021 | |
Comment |
Evaluation of distance learning program conducted | Value | NA | The study will be planned after finalization of th | Evaluation of distance learning program conducted |
Date | March 31, 2020 | November 30, 2020 | December 31, 2021 | |
Comment |